Home / Browse projects / Kheda, Gujarat / Vitthal Vinayak

Valid until 30 Jun 2024 Mixed Development project

Vitthal Vinayak

By VITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED

RG-GJ-17154 · RERA PR/GJ/KHEDA/MEHMEDABAD/AUDA/MAA06474/EX2/140624/300624 · Last updated on GujRERA portal: 28 May 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2024Possession promisedmoved 24 months from the original
3 of 9Construction stages donefurthest along: Internal walls, 98%
53 of 60Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

Vitthal Vinayak is a Mixed Development project by VITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED in Kheda, Gujarat, registered with GujRERA as PR/GJ/KHEDA/MEHMEDABAD/AUDA/MAA06474/EX2/140624/300624 on 17 Dec 2019. Possession is promised by 30 Jun 2024. The completion date has moved by 24 months from the original filing. 7 of the 60 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameVitthal Vinayak
  • TypeMixed Development
  • Location
    • Vitthal Vinayak
    • Opp- Reliance Petrol Pump
    • Dakor Road
    • Mahemdabad
    • Mahemdabad
    • Mehmedabad
    • Kheda
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/KHEDA/MEHMEDABAD/AUDA/MAA06474/EX2/140624/300624
  • ReraGenie IDRG-GJ-17154

Builder

  • NameVITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredDec 2019First promiseJun 2022Revised toJun 2024

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2024
  • Registered on17 Dec 2019
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed45 files

Current status

12%7 of 60 units booked
96.8%Of the estimated cost spent so far

Figures as on 28 May 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E+F---382260

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 28 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

E+F: 95% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor93%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 28 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes85%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes60%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes85%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes45%
Fire fightingYes65%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes10%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,159 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.56 cr
Cost incurredRs 3.45 cr
Spent of the estimate96.84%
BuildingWingEstimatedIncurred
E+FNARs 3.56 crRs 3.45 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDahyabhai H Patel
EngineerDahyabhai H Patel

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/KHEDA/MEHMEDABAD/AUDA/MAA06474/EX1/230622Applied May 2022; approved Jun 2022
PR/GJ/KHEDA/MEHMEDABAD/AUDA/MAA06474/EX2/140624/300624Applied Nov 2023; approved Jun 2024

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/KHEDA/MEHMEDABAD/AUDA/MAA06474/EX2/140624/300624 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)28 May 2024
Architect's certificate (Form 1)27 Oct 2023
Site photograph, E+F27 Oct 2023
Site photograph, E+F27 Oct 2023
Site photograph, E+F27 Oct 2023
Site photograph, E+F27 Oct 2023
Site photograph, E+F27 Oct 2023
RERA registration certificate17 Dec 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Kheda

12%of this project is bookeddistrict median 62%
12%of Kheda projects moved their completion datethis one moved by 24 months

Computed across the 77 Kheda projects on ReraGenie, from their own filings.

Keep Vitthal Vinayak on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mahemdabad77 in Kheda

2 kmVitthal VinayakOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: VITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED

VITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED has 1 registration on GujRERA, including Vitthal Vinayak. Read the full track record. See more projects on the Kheda district page.

Frequently asked questions

What are my rights if Vitthal Vinayak is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Vitthal Vinayak?

The registered promoter entity is VITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Vitthal Vinayak?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Vitthal Vinayak?

The professionals named in the filing: Architect: Dahyabhai H Patel; Engineer: Dahyabhai H Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vitthal Vinayak?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vitthal Vinayak. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vitthal Vinayak to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.