New projects and RERA data in Kheda district, Gujarat

77 projects are registered in Kheda district: 5,955 units across them, 9 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

77Projects covered
9Registered, last 12 months
5,955Units declared
10Completion dates revised

Of the 77 covered registrations, 10 have revised their promised completion date. Of the 72 that file a booking figure, the median is 62% booked as of the current data. Every figure comes from the projects' own GujRERA filings.

How far Kheda possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 10 of 77 projects (13%) have moved at least once; the median move is 14 months and the longest is 90 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

05101520Originally due 2018: 1 projects kept the original date, 100% of the year’18Originally due 2019: 5 projects kept the original date, 71% of the yearOriginally due 2019: 1 projects moved by under 2 years, 14% of the yearOriginally due 2019: 1 projects moved by 2 years or more, 14% of the year’19Originally due 2020: 2 projects kept the original date, 100% of the year’20Originally due 2021: 1 projects kept the original date, 50% of the yearOriginally due 2021: 1 projects moved by under 2 years, 50% of the year’21Originally due 2022: 1 projects moved by under 2 years, 50% of the yearOriginally due 2022: 1 projects moved by 2 years or more, 50% of the year’22Originally due 2023: 4 projects kept the original date, 80% of the yearOriginally due 2023: 1 projects moved by 2 years or more, 20% of the year’23Originally due 2024: 9 projects kept the original date, 75% of the yearOriginally due 2024: 2 projects moved by under 2 years, 17% of the yearOriginally due 2024: 1 projects moved by 2 years or more, 8% of the year’24Originally due 2025: 4 projects kept the original date, 80% of the yearOriginally due 2025: 1 projects moved by under 2 years, 20% of the year’25Originally due 2026: 4 projects kept the original date, 100% of the year’26Originally due 2027: 12 projects kept the original date, 100% of the year’27Originally due 2028: 12 projects kept the original date, 100% of the year’28Originally due 2029: 7 projects kept the original date, 100% of the year’29Originally due 2030: 6 projects kept the original date, 100% of the year’30

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

05001,0001,5002,000Originally due 2018: 48 flats kept the original date, 100% of the year’18Originally due 2019: 879 flats kept the original date, 71% of the yearOriginally due 2019: 15 flats moved by under 2 years, 14% of the yearOriginally due 2019: 92 flats moved by 2 years or more, 14% of the year’19Originally due 2020: 216 flats kept the original date, 100% of the year’20Originally due 2021: 14 flats kept the original date, 50% of the yearOriginally due 2021: 95 flats moved by under 2 years, 50% of the year’21Originally due 2022: 24 flats moved by under 2 years, 50% of the yearOriginally due 2022: 60 flats moved by 2 years or more, 50% of the year’22Originally due 2023: 326 flats kept the original date, 80% of the yearOriginally due 2023: 154 flats moved by 2 years or more, 20% of the year’23Originally due 2024: 455 flats kept the original date, 75% of the yearOriginally due 2024: 342 flats moved by under 2 years, 17% of the yearOriginally due 2024: 249 flats moved by 2 years or more, 8% of the year’24Originally due 2025: 227 flats kept the original date, 80% of the yearOriginally due 2025: 54 flats moved by under 2 years, 20% of the year’25Originally due 2026: 212 flats kept the original date, 100% of the year’26Originally due 2027: 1,084 flats kept the original date, 100% of the year’27Originally due 2028: 643 flats kept the original date, 100% of the year’28Originally due 2029: 378 flats kept the original date, 100% of the year’29Originally due 2030: 388 flats kept the original date, 100% of the year’30

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Where in Kheda: projects by taluka

77 of the 77 registrations on this page name their taluka.

TalukaProjectsShare
Nadiad4964%
Mehmedabad1722%
Kheda912%
1 other taluka23%

Projects in Kheda

Showing 1 to 60 of 77 projects.

Largest first, by the unit count in the filing.

ProjectDeveloperUnitsBookedRegisteredStatus
RADHE KISHAN PARKMahemdabad, 387130SONI ASSOCIATES381-24 Sep 2018Valid until 25 Jan 2019
NEXUS-5SAHJANAND DEVELOPERS33855%17 Jul 2021Valid until 30 Apr 2027
Karmvir Business ParkSANTRAM DEVELOPERS32239%1 Jan 2022Valid until 31 Aug 2025
NEXUS-6SOLID CONSTRUCTION COMPANY25953%18 Apr 2022Valid until 30 Apr 2028
192 Out of 256 EWS, Package-22, Phase-3, MahemdabadMahemdabad, 387130GUJARAT HOUSING BOARD256-4 Sep 2018Valid until 31 Mar 2019
Karmvir Nadiad GatewayKARMVIR INFRASTRUCTURE DEVELOPERS2494%19 Mar 2022Valid until 22 Dec 2026
FK ELEGANCE Phase-2NADIAD, 387002ELEGANCE DEVELOPERS1855%19 Nov 2024Valid until 30 Aug 2027
DEV HERITAGEKakarpadi, 387230ASHIRWAD CORPORATION17183%27 Sep 2018Valid until 30 Sep 2020
AKSHAR RESIDENCE & COMMERCIALKhatraj, 387130VATSALYA INFRASTRUCTURE PRIVATE LIMITED15474%7 Aug 2019Valid until 15 Mar 2026
CITY CENTERMatar, 387530AARAV DEVELOPERS15492%12 Mar 2018Valid until 31 Dec 2019
Pratistha BungalowsKakarkhad, 387003Shri Shantram Encon149100%18 Jun 2019Valid until 30 Sep 2023
Gateway By TulsiTULSI CONSTRUCTION14466%22 May 2023Valid until 30 Apr 2029
TRIDENT SKYLINENadiad, 387001TRISHUL CONSTRUCTION1401%6 Feb 2025Valid until 29 Jan 2030
CITY POINTVasoUMA GROUP12861%14 May 2020Valid until 31 Jul 2023
Prakruti ResidencyNadiad, 387002Shree Santram Corporation1140%8 Jul 2026Valid until 31 Dec 2030
FK ELEGANCE Phase-1NADIAD, 387002ELEGANCE DEVELOPERS1080%12 Nov 2024Valid until 30 Aug 2027
PARKER AVENUENADIAD, 387002HARIKRISHNA BUILDCON10686%26 Dec 2022Valid until 30 Apr 2027
PUSHPVAN BUNGLOWS & ARCADEMahemdavad, 387130SUMADHUR CORPORATION9522%3 Jan 2019Valid until 31 Dec 2021
Sankalp ResidencyNadiadShree Laxminarayan Buildcon9599%28 Aug 2020Valid until 31 Mar 2024
SHRINATH RESIDENCYKhatraj, 387130Shreenath Developers9274%28 Feb 2018Valid until 28 Jun 2027
City PointSHREE KESHAV DEVELOPERS9043%20 Dec 2021Valid until 31 Dec 2024
SHREE YOGIKRUPA AVENUEMAHEMDABAD, 387130SHREE YOGIKRUPA ASSOCIATES9059%26 Dec 2022Valid until 30 Apr 2029
Om HarmonyNADIAD, 387003OM ASSOCIATE8993%26 Apr 2019Valid until 30 Sep 2025
Ram Vihar ResidencySHREE RAM NARAYAN DEVELOPERS8674%29 Sep 2023Valid until 30 Apr 2027
Krishna ParkMahemdavad, 387130JALARAM ASSOCIATES7871%23 Oct 2017Valid until 30 Jun 2026
Shubh Residency 2SHREE NARAYAN BUILDCON7384%6 May 2023Valid until 30 Apr 2028
Kant ArcadeSIDHIVINAYAK DEVELOPER7166%1 Oct 2021Valid until 30 Apr 2027
Parijat PrideNadiad, 387002SHREE SANTRAM BUILDTECH7086%24 May 2024Valid until 31 Dec 2026
Palladium PlazaJAY MAHARAJ BUILDCON6993%30 Jul 2022Valid until 31 Dec 2025
Parijat ResidencyShree Santram Corporation6994%13 Dec 2021Valid until 31 Mar 2024
Shubh Residency 2 Phase 2Nadiad, 387001SHREE NARAYAN BUILDCON650%11 Jul 2025Valid until 30 Apr 2028
64 OUT OF 256 EWS,PACKAGE-22,PHASE-3,MEHEMDABADMahemdabad, 387130GUJARAT HOUSING BOARD64-1 Nov 2018Valid until 31 Dec 2019
KAMLA MANGAL - ANAVINCHANDRA MANGALBHAI PATEL AND OTHERS620%14 Oct 2022Valid until 31 Dec 2025
Vitthal VinayakMahemdabadVITTHAL CONSTRUCTION (GUJARAT) PRIVATE LIMITED6012%17 Dec 2019Valid until 30 Jun 2024
RAMDHAMNARESHBHAI JIVANBHAI PATEL AND OTHERS5446%23 May 2023Valid until 31 Mar 2026
GANESH RESIDENCYPATEL INFRA5353%12 Jun 2023Valid until 30 Jun 2027
SHREEJI KRISHNA VATIKAMahemdavadNilesh H. Thakkar (Proprietor of Shreeji Jalaram Estate & Developers5398%26 Nov 2019Valid until 30 Mar 2024
SHREEJI KRISHNA VIHARNilesh H. Thakkar (Proprietor of Shreeji Jalaram Estate & Developers5287%22 Mar 2022Valid until 31 Dec 2026
MERCURY 23MINESHKUMAR C. PATEL (SOLE PROPIETOR OF MERCURY CREATOR)4871%23 Mar 2022Valid until 30 Apr 2027
SATYAM BUNGLOWSRaskaRINKESH DEVELOPERS48-1 Sep 2017Valid until 31 Dec 2018
FORTUNE HEIGHTS AND RESIDENCY - 1NADIAD, 387002SHREEDHAR BUILDCON450%27 Apr 2026Valid until 31 Mar 2030
Malbar HillNadiad ( Chaklasy Party ), 387001Ananta Developers4587%24 Jul 2018Valid until 15 Jan 2020
THE CAPITALTULSI CONSTRUCTION4582%12 May 2023Valid until 31 Dec 2024
RADHE ICONBHAVESHKUMAR MANIBHAI PATEL4482%2 Mar 2023Valid until 30 Apr 2028
Parna KutirNadiad, 387001Shree Santram Infratech430%9 Sep 2026Valid until 31 Dec 2030
OMKAR BUSINESS HUBMAHEMDABAD, 387130PATEL VIPULKUMAR R proprietor of V R CONSTRUCTION410%12 Jun 2025Valid until 30 Apr 2028
SAHAJANAND ELYSIUMNADIAD ( Lakhavad Party ), 387002SIDDHIVINAYAK INFRA PROJECTS3614%25 Jul 2024Valid until 30 Apr 2029
NEXUS ELEGANCENADIAD, 387001J D BUILDCON3462%21 Oct 2024Valid until 30 Apr 2028
RHYTHM RESIDENCYMAHEMDABAD, 387130LABH CORPORATION330%19 Feb 2026Valid until 30 Apr 2029
GANESH VIHARPATEL INFRA29100%25 Feb 2021Valid until 30 Jun 2024
Keshav VatikaNADIAD, 387001SHAKTI DEVELOPERS2941%29 Apr 2024Valid until 30 Apr 2028
IMPERIAL ONENadiad, 387001ADEPT DEVELOPERS280%23 Apr 2026Valid until 31 Dec 2029
Kriss 2NADIAD, 387002SHREE JALA INFRA2832%15 Jul 2025Valid until 30 Apr 2028
OM RESIDENCYDakorOM SHARNAM DEVELOPERS2875%11 Dec 2020Valid until 30 Sep 2024
Karmvir Nadiad Gateway Phase-2KARMVIR INFRASTRUCTURE DEVELOPERS27100%28 Jun 2022Valid until 31 Dec 2023
SANTRAM SANIDHYAKRISHNA REALTY2722%12 Dec 2022Valid until 31 Dec 2027
KANT EPITOMENADIAD, 387001VASUPUJYA REALITY250%25 May 2026Valid until 31 Dec 2029
Om OpulenceNadiad, 387002OM DEVELOPERS2536%10 Jun 2024Valid until 30 Apr 2028
SolitaireNadiad, 387003SUNSHINE DEVELOPERS2596%14 Aug 2019Valid until 30 Jun 2024
Himalaya FlatsNadiad, 387001Antra Developers2475%14 May 2019Valid until 31 Mar 2023

Developers active in Kheda

Nilesh H. Thakkar (Proprietor of Shreeji Jalaram Estate & Developers (3), GUJARAT HOUSING BOARD (2), KARMVIR INFRASTRUCTURE DEVELOPERS (2), ELEGANCE DEVELOPERS (2), TULSI CONSTRUCTION (2), Shree Santram Corporation (2). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Kheda projects listed above?

Compare each project against its neighbours, not against the brochure. Of the 72 projects on this page that file a booking figure, the median is 62% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Kheda project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What if a Kheda project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own GujRERA filings, and we read every report.

Report an errorShare feedback

Data from official GujRERA filings.