Home / Browse projects / Bengaluru Urban, Karnataka / TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3

Registration approved No litigation declared Residential/Group Housing project

TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3

By TRIFECTA PROJECTS PRIVATE LIMITED

RG-KA-90434 · RERA PRM/KA/RERA/1251/446/PR/060424/006778 · Last updated on RERA Karnataka portal: 4 Sep 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2026Possession promisedno revision filed
15 of 15Construction stages doneevery applicable stage filed complete
1 of 49Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 127 documents Report an error

TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3 is a Residential/Group Housing project by TRIFECTA PROJECTS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/060424/006778 on 6 Apr 2024. Possession is promised by 30 Sep 2026. 48 of the 49 units on this registration are recorded sold or booked, and 15 of 15 construction stages are filed complete.

At a glance

Project

  • NameTRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560067
  • Pincode560067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/060424/006778
  • ReraGenie IDRG-KA-90434

Builder

  • NameTRIFECTA PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200KA2012PTC062831
  • GSTIN29AACCE9717F1ZG
  • Authorized SignatoryVenkata Subbareddy
  • Managing DirectorR V Subba Reddy
  • DirectorsRV Subba Reddy, GEDI SYLENDRAKUMAR, SARADA REDDY RAMIREDDY
  • Project HeadGEDI SYLENDRA KUMAR REDDY
  • Other registrations5 more →

Key dates

this monthRegisteredApr 2024PromisedSep 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Apr 2024
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed127 files

Current status

98%48 of 49 units booked
101.6%Of the estimated cost spent so far

Figures as on 4 Sep 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---40040
B---909

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 4 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 15 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 4 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,284 sq m
Named landowners1
LandownerVillageDistrict
RAMIREDDYVENKATA SUBBA REDDYRAMIREDDYVENKATA SUBBA REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 64.86 cr
Cost incurredRs 65.93 cr
Spent of the estimate101.64%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 53.51 crRs 51.14 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 3.75 crRs 2.70 cr
On-site expenditure-Consultants FeesRs 2.03 crRs 2.05 cr
On-site expenditure-Salaries of workersRs 1.86 crRs 1.85 cr
On-site expenditure-Site OverheadRs 1.86 crRs 1.85 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.86 crRs 1.85 cr
Payment of taxes-Rs 4.48 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectREVATHI S R
EngineerRamesh B
Chartered AccountantB MANOHAR BABU

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed127

As listed on the registration, under the names the promoter filed them with; the newest 80 of 127 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/060424/006778 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA Q1 - Row house-III.pdf4 Sep 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect RH-3, 30062026.pdf4 Sep 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer RH-3, 30062026.pdf4 Sep 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA Q1 - Row house-III.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect RH-3, 30062026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer RH-3, 30062026.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA CERTIFICATE Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect RH-3, 31032026.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer RH-3, 31032026.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 RowHouse Phase 3 Q3.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect RH-3, 31122025.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer RH-3, 31122025.pdf13 Jan 2026
Clarifiication for Annual Returns and Quarterly UpdatesFile: Clarifiication for Annual Returns and Quarterly Updates.pdf31 Mar 2024
CA certificate with CA signatureFile: CA certificate with CA signature.pdf31 Mar 2024
Bank account bank affidavitFile: Bank Affidavit.pdf31 Mar 2024
sources of fund to completeFile: Source of Funds.pdf31 Mar 2024
ECfrom 1-4-2007 to till dateFile: EC.pdf31 Mar 2024
title deed of the land ownerFile: Title deed of the land owner.pdf31 Mar 2024
notarized non-litigation affidavitFile: Affidivate non litigation.pdf31 Mar 2024
notarized form-BFile: notarized form-B.pdf31 Mar 2024
notaized JDcum affidavitFile: AFFIDAVIT CUM DECLARATION.pdf31 Mar 2024
advocate search reportFile: Advocate search report.pdf31 Mar 2024
approved planFile: Approved Plan.pdf31 Mar 2024
Break up of types of units (BHK wise)File: Clarification for Inventory Breakup.pdf31 Mar 2024
FAR As per the sanction plan is not matching with the details enteredFile: Clarification for FAR.pdf31 Mar 2024
Single plot layoutFile: Single plot layout.pdf31 Mar 2024
Single plot layout orderFile: Single plot layout Order.pdf31 Mar 2024
certified carpet area calculationFile: Carpet Area Statement.pdf31 Mar 2024
CDP map showing the proposed site. In partially residential park and open space upload CLFile: ROW HOUS PHASE-3 CDP MARKED.pdf31 Mar 2024
Upload village map showing the proposed siteFile: Village male with site mark.pdf31 Mar 2024
Area /number of units in KSPCB CFE. is not matching with sanction planFile: KSPCB NOC.pdf31 Mar 2024
Area /number of units in KSPCB CFE. is not matching with sanction planFile: Sanction Plan.pdf31 Mar 2024
Upload relinquishment deedFile: Relinquishment Deed.pdf31 Mar 2024
Upload building licenseFile: Building license.pdf31 Mar 2024
Upload Architects certificate with valid COA numberFile: Architects certificate with COA number.pdf31 Mar 2024
Upload ZR copy for nala bufferFile: ZR.pdf31 Mar 2024
Exclusive Common Area Allottee and Common Area Alloted To AssociationFile: Exclusive Common Area Allottee and Common Area Alloted To Association.pdf31 Mar 2024
Area calculation sheet certified by the EngineerFile: Area calculation sheet certified by the Engineer.pdf31 Mar 2024
upload the latest dated self attested copy of the Engineer license certificateFile: Self attested copy of the Engineer license certificate.pdf31 Mar 2024
Updated Amenities and Common area details are incorrect. Please update the same properly as per theFile: Area calculation sheet certified by the Engineer.pdf31 Mar 2024
Updated Amenities and Common area details are incorrect. Please update the same properly as per theFile: Exclusive Common Area Allottee and Common Area Alloted To Association.pdf31 Mar 2024
upload the Engineer certificate in the prescribed formatFile: Form3 Trifecra verda phase 3.pdf31 Mar 2024
upload the Certificate from Registered Engineer indicating the structural safety adopted for the proFile: STRUCTURAL STABILITY CERTI FICATE.pdf31 Mar 2024
project name and project address and upload the project specification certified by the EngineerFile: Project specifications Trifecta verda en respolnder phase 3.pdf31 Mar 2024
project name and project address and upload the section 3(1) notarized affidavit.File: Form B Notarized.pdf31 Mar 2024
upload the brief estimated cost of construction certified by the EngineerFile: Brief Estimated cost of construction certified by the Engineer.pdf31 Mar 2024
uploaded STP design drawing does not tally with the KPSCB NOC. Therefore Please upload the STP desigFile: KSPCB.pdf31 Mar 2024
upload the self-attested copy of the NOC issued by BESCOM and BWSSB along with the copy of the fee rFile: self-attested copy of the NOC issued by BESCOM.pdf31 Mar 2024
upload the self-attested copy of the NOC issued by BESCOM and BWSSB along with the copy of the fee rFile: self-attested copy of the NOC issued by Water NOC.pdf31 Mar 2024
upload the Land cost calculation sheet as per the guidance value(self-attested copy)File: Land Calculation of as per Sub register Guidelines.pdf31 Mar 2024
Please clarify the source of water supply to the project along with the supporting documents and phoFile: Water Source.pdf31 Mar 2024
proforma of the Allotment letterFile: proforma of the Allotment letter.pdf31 Mar 2024
proforma of the Agreement for SaleFile: proforma of the agreement for sale.pdf31 Mar 2024
RTC, survey 123\2-
Mutation, survey 123\2-
Encumbrance Certificate, survey 123\2-
Conversion/Alienation Order, survey 123\2-
Sale/Title/Gift Deed, survey 123\2-
Khatha, survey 123\2-
Registration CertificateFile: Incorporation Certificate after change of name (1) (1).pdf-
Certificate issued by CA Form 1File: Form 1.pdf-
Certificate issued by Architect Form 2File: Form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: WhatsApp Image.pdf-
Certificate from Chartered AccountFile: Form 1.pdf-
Balance Sheet 2022 - 2023File: TRIFECTA Balance Sheet-2023.pdf-
Balance Sheet 2021 - 2022File: TRIFECTA Balance Sheet-2022.pdf-
Balance Sheet 2020 - 2021File: TRIFECTA Balance Sheet-2021.pdf-
Audited Profit and Loss Statement 2022 - 2023File: TRIFECTA P-L-2023.pdf-
Audited Profit and Loss Statement 2021 - 2022File: TRIFECTA P_L -2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: TRIFECTA P_L -2021.pdf-
Director's Report 2022 - 2023File: WhatsApp Image.pdf-
Director's Report 2021 - 2022File: Directors Report 2022.pdf-
Director's Report 2020 - 2021File: Direct Report 2021_compressed.pdf-
Cash Flow Statement 2022 - 2023File: TRIFECTA CF 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: TRIFECTA CF 2021-22.pdf-
Auditor's Report 2022 - 2023File: WhatsApp Image.pdf-

How this compares with Bengaluru Urban

98%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE- on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: TRIFECTA PROJECTS PRIVATE LIMITED

TRIFECTA PROJECTS PRIVATE LIMITED has 6 registrations on RERA Karnataka, including Trifecta Veranza and TRIFECTA RETTO. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3 is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3?

The registered promoter entity is TRIFECTA PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U45200KA2012PTC062831 and GSTIN 29AACCE9717F1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3?

The professionals named in the filing: Architect: REVATHI S R; Engineer: Ramesh B; Chartered Accountant: B MANOHAR BABU. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE- to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.