Home / Browse projects / Bengaluru Rural, Karnataka / DS MAX SKY FIELDS

Registration approved No litigation declared Residential/Group Housing project

DS MAX SKY FIELDS

By DS Max Properties Private Limited

RG-KA-61323 · RERA PRM/KA/RERA/1250/304/PR/251024/007179 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Sep 2030Possession promisedno revision filed
5 of 18Construction stages donefurthest along: RCC or MS Framed structure, 0%
625 of 870Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 153 documents Report an error

DS MAX SKY FIELDS is a Residential/Group Housing project by DS Max Properties Private Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/251024/007179 on 25 Oct 2024. Possession is promised by 30 Sep 2030. 245 of the 870 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameDS MAX SKY FIELDS
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 560067
  • Pincode560067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/251024/007179
  • ReraGenie IDRG-KA-61323

Builder

  • NameDS Max Properties Private Limited
  • Entity typeCompany
  • CINU70102KA2007PTC041508
  • GSTIN29AACCD6168M1Z3
  • Authorized SignatoryShivashankar Chikkeri
  • MdK V SATISH
  • DirectorsK V SATISH, Asha Satish, S P Dayanand
  • Project HeadS HIMAVANTHA REDDY
  • Other registrations38 more →
  • Declared earlier projects31 →

Key dates

this monthRegisteredOct 2024PromisedSep 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Oct 2024
  • Promised completion30 Sep 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed153 files

Current status

28%245 of 870 units booked
44.1%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---8700870

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 0%.

Building: 28% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes20%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes20%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes20%
LiftsYes20%
Corridor/LobbiesYes20%
Fire escapesYes20%
Common entrance and exit for the building/common portico/foyer/verandahYes20%
BasementYes100%
TerraceYes20%
Outer WallYes20%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,006 sq m
Named landowners3
LandownerVillageDistrict
DS-MAX PROPERTIES PRIVATE LIMITED--
DS-MAX PROPERTIES PRIVATE LIMITED--
DS-MAX PROPERTIES PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 144.31 cr
Cost incurredRs 63.62 cr
Spent of the estimate44.08%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 144.31 crRs 55.25 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 2.43 cr
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 5.94 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMunendra Babu
EngineerSwarapananda Goud K S
Chartered AccountantK Somanatham

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01128/2026-DS Max Properties Private Limited15/09/2026

Documents filed153

As listed on the registration, under the names the promoter filed them with; the newest 80 of 153 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/251024/007179 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Sky Fields_0001.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Sky Fields_0001.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Sky Fields_0001.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: SKY FIELDS_0006.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5, Q1 2026-27,DS Max Sky Fields.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SKY FIELDS_0005.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Sky Fielda_0001.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5,Q4,2025-26,DS Max Sky Fields.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sky Fields CE Mar 26_0001.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Sky Fields_0002.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5, Q3,2025-26,DS Max Sky Fields.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sky Fields CE.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Q3 2025-26 Fire and Safety12 Jan 2026
Q3 2025-26 Airport Authority of India12 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department12 Jan 2026
RERA Bank Accounts Sky FieldFile: 1 RERA Bank Accounts Sky Field.pdf24 Oct 2024
Annual Audit ClarificationFile: 2 Annual Audit Clarification.pdf24 Oct 2024
ADLR SketchFile: 1 ADLR Sketch.pdf24 Oct 2024
Commence CertificateFile: 2 Commence Certificate.pdf24 Oct 2024
LOWER BASEMENT FLOOR PLANFile: 1 LOWER BASEMENT FLOOR PLAN.pdf24 Oct 2024
UPPER BASEMENT FLOOR PLANFile: 2 UPPER BASEMENT FLOOR PLAN.pdf24 Oct 2024
SITE PLANFile: 3 SITE PLAN.pdf24 Oct 2024
GROUND FLOOR PLANFile: 4 GROUND FLOOR PLAN.pdf24 Oct 2024
TYPICAL 1ST -14TH FLOOR PLANFile: 5 TYPICAL 1ST -14TH FLOOR PLAN.pdf24 Oct 2024
CDP Map DemarcationFile: 3 CDP Map Demarcation.pdf24 Oct 2024
Village Map DemarcationFile: 4 Village Map Demarcation.pdf24 Oct 2024
KSPCB NOC with Fees receiptFile: 5 KSPCB NOC with Fees receipt.pdf24 Oct 2024
BMRDA CLU ORDER COPYFile: 6 BMRDA CLU ORDER COPY.pdf24 Oct 2024
Clarification on HAL NOCFile: Clarification on HAL NOC.pdf24 Oct 2024
Sky fields phodi copyFile: Sky fields phodi copy.pdf24 Oct 2024
Clarification on Building license from local authorityFile: 7 Clarification on Building license from local authority.pdf24 Oct 2024
Amenities and Common Areas Eng CertificateFile: 8 Amenities and Common Areas Eng Certificate.pdf24 Oct 2024
SKY FEILDS SANCTION DP COLOURFile: 9 SKY FEILDS SANCTION DP COLOUR.pdf24 Oct 2024
Guidelines Value self-attestedFile: 10 Guidelines Value self-attested.pdf24 Oct 2024
SKY FIELD_STP_8_RERA DRGFile: 11 SKY FIELD_STP_8_RERA DRG.pdf24 Oct 2024
CLU COPY OF SAMETHANAHALLI VILLAGEFile: CLU COPY OF SAMETHANAHALLI VILLAGE.pdf24 Oct 2024
RTC, survey 234/1-
Mutation, survey 234/1-
Encumbrance Certificate, survey 234/1-
Conversion/Alienation Order, survey 234/1-
Sale/Title/Gift Deed, survey 234/1-
Khatha, survey 234/1-
RTC, survey 234/2-
Mutation, survey 234/2-
Encumbrance Certificate, survey 234/2-
Conversion/Alienation Order, survey 234/2-
Sale/Title/Gift Deed, survey 234/2-
Khatha, survey 234/2-
RTC, survey 234/3-
Mutation, survey 234/3-
Encumbrance Certificate, survey 234/3-
Conversion/Alienation Order, survey 234/3-
Sale/Title/Gift Deed, survey 234/3-
Khatha, survey 234/3-
Registration CertificateFile: Certificate of Incorporation.pdf-
Memorandum of AssociationFile: MOA.pdf-
Article of AssociationFile: AOA.pdf-
Organization StructureFile: DSMax Properties Pvt Ltd Organisation Chart.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect - SKY FIELDS.pdf-

How this compares with Bengaluru Rural

28%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep DS MAX SKY FIELDS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmDS MAX SKY FIELDSOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: DS Max Properties Private Limited

DS Max Properties Private Limited has 39 registrations on RERA Karnataka, including DS MAX SKY SISIRA and DS MAX SKY SAMURAI. Its filings declare 31 earlier projects, 18 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if DS MAX SKY FIELDS is delayed beyond 30 Sep 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DS MAX SKY FIELDS?

The registered promoter entity is DS Max Properties Private Limited, a company as per the filing. Its CIN U70102KA2007PTC041508 and GSTIN 29AACCD6168M1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DS MAX SKY FIELDS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DS MAX SKY FIELDS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at DS MAX SKY FIELDS?

The professionals named in the filing: Architect: Munendra Babu; Engineer: Swarapananda Goud K S; Chartered Accountant: K Somanatham. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DS MAX SKY FIELDS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DS MAX SKY FIELDS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DS MAX SKY FIELDS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.