Valid until 30 Sep 2021 Residential/Group Housing project

SURAMYA BUNGALOWS

By RAJENDRABHAI DAHYABHAI PATEL Proprietor of MATAJI INFRA

RG-GJ-33612 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA05302/220419 · Last updated on GujRERA portal: 29 Sep 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Sep 2021Possession promisedno revision filed
4 of 7Construction stages donefurthest along: Internal walls, 99%
5 of 16Units unsoldnot recorded sold or booked
Jump to the 56 documents Report an error

SURAMYA BUNGALOWS is a Residential/Group Housing project by RAJENDRABHAI DAHYABHAI PATEL Proprietor of MATAJI INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA05302/220419 on 22 Apr 2019. Possession is promised by 30 Sep 2021. 11 of the 16 units on this registration are recorded sold or booked, and 4 of 7 construction stages are filed complete.

At a glance

Project

  • NameSURAMYA BUNGALOWS
  • TypeResidential/Group Housing
  • Location
    • OPP SAI NAGAR VIBHAG-I
    • BH KHODIYAR NAGAR NEW VIP ROAD
    • Savad
    • Vadodara
    • 390006
  • Pincode390006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA05302/220419
  • ReraGenie IDRG-GJ-33612

Builder

  • NameRAJENDRABHAI DAHYABHAI PATEL Proprietor of MATAJI INFRA
  • Entity typeIndividual/Propritorship
  • Other registrations2 more →

Key dates

this monthRegisteredApr 2019PromisedSep 2021

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2021
  • Registered on22 Apr 2019
  • Promised completion30 Sep 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed56 files

Current status

69%11 of 16 units booked
84.4%Of the estimated cost spent so far

Figures as on 29 Sep 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---16016

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 29 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 7 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats99%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 29 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes75%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes80%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes80%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,580 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.59 cr
Cost incurredRs 3.03 cr
Spent of the estimate84.4%
BuildingWingEstimatedIncurred
ANARs 3.59 crRs 3.03 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHESH RATHOD
EngineerZARNA ASSOCIATES

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA05302/220419 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)29 Sep 2021
Engineer's certificate (Form 2)29 Sep 2021
Engineer's certificate annexure29 Sep 2021
Accountant's certificate (Form 3)29 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
Site photograph, A28 Sep 2021
RERA registration certificate22 Apr 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

69%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SURAMYA BUNGALOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Savad2,900+ in Vadodara

2 kmSURAMYA BUNGALOWSOther 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: RAJENDRABHAI DAHYABHAI PATEL Proprietor of MATAJI INFRA

RAJENDRABHAI DAHYABHAI PATEL Proprietor of MATAJI INFRA has 3 registrations on GujRERA, including SURAMYA BUNGALOWS and SUHRAD RESIDENCY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SURAMYA BUNGALOWS is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SURAMYA BUNGALOWS?

The registered promoter entity is RAJENDRABHAI DAHYABHAI PATEL Proprietor of MATAJI INFRA, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SURAMYA BUNGALOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SURAMYA BUNGALOWS?

The professionals named in the filing: Architect: MAHESH RATHOD; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SURAMYA BUNGALOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SURAMYA BUNGALOWS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SURAMYA BUNGALOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.