SHUKAN AROMA

By SHREE JAY AMBE INFRA SPACE

RG-GJ-67534 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX2/EX3/151025/311225 · Last updated on GujRERA portal: 1 Oct 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 34 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 34 months from the original
36 of 54Construction stages doneacross 6 buildings; furthest along: Installation of lifts, 95%
70 of 252Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SHUKAN AROMA is a Mixed Development project by SHREE JAY AMBE INFRA SPACE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX2/EX3/151025/311225 on 30 Oct 2018. Possession is promised by 31 Dec 2025. The completion date has moved by 34 months from the original filing. 182 of the 252 units on this registration are recorded sold or booked, and 36 of 54 construction stages are filed complete.

At a glance

Project

  • NameSHUKAN AROMA
  • TypeMixed Development
  • Location
    • SHUKAN AROMA
    • VIJAY NAGAR
    • SANGAM CHAAR RASTA
    • HARNI ROAD
    • VADODARA
    • Vadodara
    • 390006
  • Pincode390006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX2/EX3/151025/311225
  • ReraGenie IDRG-GJ-67534

Builder

  • NameSHREE JAY AMBE INFRA SPACE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2018First promiseFeb 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on30 Oct 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 27 Feb 2023)
  • Buildings6 building records
  • Documents filed43 files

Current status

72%182 of 252 units booked
84.3%Of the estimated cost spent so far

Figures as on 1 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER F---32032
TOWER A---282048
TOWER B---281644
TOWER C---282048
TOWER D---48048
TOWER E---32032

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 1 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Installation of lifts, at 95%.

TOWER F86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
TOWER A88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
TOWER B85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
TOWER C86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
TOWER D85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
TOWER E88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 1 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyNoNot applicable
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes70%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes95%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,987 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 34.14 cr
Cost incurredRs 28.80 cr
Spent of the estimate84.35%
BuildingWingEstimatedIncurred
TOWER DNARs 6.87 crRs 5.65 cr
TOWER ANARs 6.25 crRs 5.26 cr
TOWER CNARs 6.25 crRs 5.21 cr
TOWER BNARs 5.62 crRs 4.80 cr
TOWER ENARs 4.58 crRs 3.93 cr
TOWER FNARs 4.58 crRs 3.95 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHITESH ENGINEERS ARCHITECT & INTERIOR DESIGNER
EngineerHITESH ENGINEERS ARCHITECT & INTERIOR DESIGNER

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX1/260923Applied Feb 2023; approved Sep 2023
PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX2/301024/311224Applied Jul 2024; approved Oct 2024
PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX2/EX3/151025/311225Applied Sep 2025; approved Oct 2025

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA03893/EX2/EX3/151025/311225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)1 Oct 2025
Engineer's certificate (Form 2)9 Sep 2025
Engineer's certificate annexure9 Sep 2025
Architect's certificate (Form 1)8 Sep 2025
Site photograph, TOWER F5 Sep 2025
Site photograph, TOWER A5 Sep 2025
Site photograph, TOWER B5 Sep 2025
Site photograph, TOWER C5 Sep 2025
Site photograph, TOWER D5 Sep 2025
Site photograph, TOWER E5 Sep 2025
RERA registration certificate30 Oct 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

72%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 34 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHUKAN AROMA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmSHUKAN AROMAOther 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: SHREE JAY AMBE INFRA SPACE

SHREE JAY AMBE INFRA SPACE has 1 registration on GujRERA, including SHUKAN AROMA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHUKAN AROMA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHUKAN AROMA?

The registered promoter entity is SHREE JAY AMBE INFRA SPACE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHUKAN AROMA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHUKAN AROMA?

The professionals named in the filing: Architect: HITESH ENGINEERS ARCHITECT & INTERIOR DESIGNER; Engineer: HITESH ENGINEERS ARCHITECT & INTERIOR DESIGNER. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUKAN AROMA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUKAN AROMA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUKAN AROMA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.