Home / Browse projects / Vadodara, Gujarat / STONEGATE

Valid until 31 Dec 2021 Mixed Development project

STONEGATE

By OM INFRA

RG-GJ-62500 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA02336/EX2/A1M/210921 · Last updated on GujRERA portal: 22 Dec 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Dec 2021Possession promisedmoved 24 months from the original
36 of 36Construction stages doneacross 4 buildings; every applicable stage filed complete
18 of 102Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

STONEGATE is a Mixed Development project by OM INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA02336/EX2/A1M/210921 on 11 Apr 2018. Possession is promised by 31 Dec 2021. The completion date has moved by 24 months from the original filing. 84 of the 102 units on this registration are recorded sold or booked, and 36 of 36 construction stages are filed complete.

At a glance

Project

  • NameSTONEGATE
  • TypeMixed Development
  • Location
    • "STONEGATE"
    • OPP. SANGANI SKYZ
    • TP: 02
    • VASNA BHAYLI ROAD
    • ( Bhayli )
    • Vadodara
    • 391101
  • Pincode391101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA02336/EX2/A1M/210921
  • ReraGenie IDRG-GJ-62500

Builder

  • NameOM INFRA
  • Entity typePARTNERSHIP FIRM
  • Other registrations11 more →

Key dates

this monthRegisteredApr 2018First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2021
  • Registered on11 Apr 2018
  • Promised completion31 Dec 2021
  • Revised completionRevised to 31 Dec 2021 (originally 31 Dec 2019)
  • Buildings4 building records
  • Documents filed41 files

Current status

82%84 of 102 units booked
100.0%Of the estimated cost spent so far

Figures as on 22 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---191029
B---19827
C---22022
D---24024

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 22 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 36 construction stages are filed complete across 4 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 22 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,408 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.56 cr
Cost incurredRs 6.56 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 1.64 crRs 1.64 cr
BNARs 1.64 crRs 1.64 cr
CNARs 1.64 crRs 1.64 cr
DNARs 1.64 crRs 1.64 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRISHI ARCHITECT
EngineerZARNA ASSOCIATES

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA02336/EX1/120220Applied Dec 2019; approved Feb 2020
PR/GJ/VADODARA/VADODARA/Others/MAA02336/EX2/210921Applied Sep 2021; approved Sep 2021

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA02336/EX2/A1M/210921 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)22 Dec 2021
Engineer's certificate (Form 2)22 Dec 2021
Engineer's certificate annexure22 Dec 2021
Accountant's certificate (Form 3)22 Dec 2021
Site photograph, A22 Dec 2021
Site photograph, B22 Dec 2021
Site photograph, C22 Dec 2021
Site photograph, D22 Dec 2021
RERA registration certificate11 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

82%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 24 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep STONEGATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near ( Bhayli )2,900+ in Vadodara

2 kmSTONEGATEOther 353Dot size: filed unitsN

Filed coordinates, straight-line distance. 353 registered projects within 2 km.

Builder: OM INFRA

OM INFRA has 12 registrations on GujRERA, including STONEGATE and OM RESIDENCY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if STONEGATE is delayed beyond 31 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of STONEGATE?

The registered promoter entity is OM INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in STONEGATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at STONEGATE?

The professionals named in the filing: Architect: RISHI ARCHITECT; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in STONEGATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About STONEGATE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save STONEGATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.