Home / Browse projects / Bengaluru Urban, Karnataka / SRI SAI BHARATH TOWERS

Registration approved No litigation declared Residential/Group Housing project

SRI SAI BHARATH TOWERS

By SRI BHARATH DEVELOPRS

RG-KA-04749 · RERA PRM/KA/RERA/1251/309/PR/200126/008413 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
4 of 16Construction stages donefurthest along: RCC or MS Framed structure, 80%
75 of 76Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 100 documents Report an error

SRI SAI BHARATH TOWERS is a Residential/Group Housing project by SRI BHARATH DEVELOPRS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/200126/008413 on 20 Jan 2026. Possession is promised by 31 Dec 2029. 1 of the 76 units on this registration are recorded sold or booked, and 4 of 16 construction stages are filed complete.

At a glance

Project

  • NameSRI SAI BHARATH TOWERS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560077
  • Pincode560077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/200126/008413
  • ReraGenie IDRG-KA-04749

Builder

  • NameSRI BHARATH DEVELOPRS
  • Entity typeProprietorship
  • GSTIN29AAMPO3054C1ZP
  • Authorized SignatoryObulu Reddy

Key dates

this monthRegisteredJan 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed100 files

Current status

1%1 of 76 units booked
60.0%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Block---44044
B Block---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 80%.

Building: 56% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure80%
Masonry Construction80%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification70%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing30%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)20%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes50%
Corridor/LobbiesYes70%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes90%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,045 sq m
Named landowners1
LandownerVillageDistrict
Manjunatha K P--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.46 cr
Cost incurredRs 12.28 cr
Spent of the estimate60.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 20.46 crRs 12.28 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT V Srinivas
EngineerM Venkat Ramana Reddy
Chartered AccountantSathisha Rajanna

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed100

As listed on the registration, under the names the promoter filed them with; the newest 80 of 100 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/200126/008413 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Scan of FORM 04 OF K RERA OF OBULU REDDY --.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: SKM_36726100300310.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: SKM_36726100300311.pdf13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA CERTIFICATER Q1 2026 27.pdf12 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: S55BW-9e26070810120.pdf12 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: S55BW-9e26070810110.pdf12 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SRI BHARATH DEVELOPERS RERA CERTIFICATE.pdf11 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: SRI BHARATH ENG.pdf11 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: SRI BHARATH ART.pdf11 May 2026
JDA BETWEEN LAND OWNER AND PROMOTERFile: JD Manjunath.pdf13 Jan 2026
BUILDING LICENSEFile: Building license.pdf13 Jan 2026
ALL FLOOR PLANFile: Plan.pdf13 Jan 2026
SURVEY SKETCHFile: Survey sketch.pdf13 Jan 2026
GPA BETWEEN LAND OWNER AND PROMOTERFile: GPA Manjunath.pdf13 Jan 2026
STRUTURAL STABILITY CERTIFICATEFile: Structural Stability Form.pdf13 Jan 2026
ENGINEER SELF ATTESTED LICENSEFile: Engineer license.pdf13 Jan 2026
PROFORMA OF AGREEMENT OF SALEFile: Agreement of Sale Proforma final.pdf19 Dec 2025
MODEL FOR M OF ALLOTMENT LETTERFile: MODEL FORM OF ALLOTMENT LETTER.pdf19 Dec 2025
ENGINEER SELF ATTESTEDFile: Engineer self attested.pdf19 Dec 2025
SECTION 3(1) VIOLATION AFFIDAVITFile: Section 3 violation affidavit.pdf19 Dec 2025
PROJECT BRIEF ESTIMATED COSTFile: Project brief estimated cost.pdf19 Dec 2025
STRUCTURAL STABILITY CERTIFICATEFile: Strutural stability certificate.pdf19 Dec 2025
FEASIBILITY REPORT STPFile: Feasibility report.pdf19 Dec 2025
STP DRAWINGFile: STP drawing 45 KLD.pdf19 Dec 2025
CLARIFICATION OF LAND COST CALCULATIONFile: Clarification of Land Cost.pdf19 Dec 2025
COMMON AREA STATEMENTFile: Area statement.pdf19 Dec 2025
BESCOM NOCFile: Bescom NOC.pdf19 Dec 2025
BUILDING COMMENCEMENT CERTIFICATE CLARIFICATIONFile: Clarification of Building commencement.pdf19 Dec 2025
KSPCB NOCFile: KSPCB.pdf19 Dec 2025
PLANFile: Plan.pdf19 Dec 2025
BUILDING LICENCEFile: Building license.pdf19 Dec 2025
SURVEY SKETCHFile: Survey sketch.pdf19 Dec 2025
VILLAGE MAPFile: Village Map.pdf19 Dec 2025
CA CERTIFICATE FORM 1File: Form 1 CA certificate new.pdf19 Dec 2025
BANK ACCOUNTFile: Bank account.pdf19 Dec 2025
BANK AFFIDAVITFile: Bank Affidavit.pdf19 Dec 2025
FINANCIAL STATEMENT 2025File: Financial statement 2025 11zon.pdf19 Dec 2025
FINANCIAL STATEMENT 2024File: Financial statement 2024 11zon.pdf19 Dec 2025
FINANCIAL STATEMENT 2023File: Financial statement 2023 11zon.pdf19 Dec 2025
SOURCE OF FUNDFile: Sources Of Funds.pdf19 Dec 2025
LATEST RTCFile: Latest RTC.pdf19 Dec 2025
CONVERSION ORDERFile: Conversion order.pdf19 Dec 2025
EC FROM 01/04/2010 TO TILL DATEFile: EC.pdf19 Dec 2025
FORM B AFFIDAVITFile: Form B Affidavit.pdf19 Dec 2025
AKARBAND UTARFile: Akarband utar.pdf19 Dec 2025
TITLE DEEDFile: Title deed.pdf19 Dec 2025
RECORD OF RIGHTSFile: Title deed 1.pdf19 Dec 2025
MRFile: MR.pdf19 Dec 2025
PARTITION DEED COURT DECREEFile: Partition deed court decree.pdf19 Dec 2025
RTC, survey 29/2-
Mutation, survey 29/2-
Encumbrance Certificate, survey 29/2-
Conversion/Alienation Order, survey 29/2-
JDA, survey 29/2-
Khatha, survey 29/2-
Registration CertificateFile: Print _ Udyam Registration Certificate Bharath developers (1).pdf-
GST CertificateFile: GST.pdf-
Certificate issued by CA Form 1File: Form 1 CA certificate new.pdf-
Certificate issued by Architect Form 2File: Form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: SBD non litigation affidavit.pdf-
Balance Sheet 2024 - 2025File: 2024-25.pdf-
Balance Sheet 2023 - 2024File: 2023-24.pdf-
Balance Sheet 2022 - 2023File: 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: COMPUTATION 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: COMPUTATION 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: COMPUTATION 2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: COMPUTATION 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: COMPUTATION 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: COMPUTATION 2022-23.pdf-
Bharath developers lisence kothanur-
BBMP Approved Plan-
BBMP Approved Plan-
PRJ_5788_25-26 (1)-
SBD Specifications-
SBD Specifications-
Unnamed document-

How this compares with Bengaluru Urban

1%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SRI SAI BHARATH TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSRI SAI BHARATH TOWERSOther 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: SRI BHARATH DEVELOPRS

SRI BHARATH DEVELOPRS has 1 registration on RERA Karnataka, including SRI SAI BHARATH TOWERS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SRI SAI BHARATH TOWERS is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SRI SAI BHARATH TOWERS?

The registered promoter entity is SRI BHARATH DEVELOPRS, a proprietorship as per the filing. Its GSTIN 29AAMPO3054C1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SRI SAI BHARATH TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SRI SAI BHARATH TOWERS?

The professionals named in the filing: Architect: T V Srinivas; Engineer: M Venkat Ramana Reddy; Chartered Accountant: Sathisha Rajanna. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SRI SAI BHARATH TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SRI SAI BHARATH TOWERS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SRI SAI BHARATH TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.