Home / Browse projects / Bengaluru Urban, Karnataka / SRI BALAJI SIGNATURE
SRI BALAJI SIGNATURE
RG-KA-08432 · RERA PRM/KA/RERA/1251/446/PR/260522/004922 · Last updated on RERA Karnataka portal: 5 May 2022
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SRI BALAJI SIGNATURE is a Residential/Group Housing project by SRI BALAJI STRUCTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/260522/004922 on 26 May 2022. Possession is promised by 30 Jun 2024.
At a glance
Project
- NameSRI BALAJI SIGNATURE
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560077
- Pincode560077
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/260522/004922
- ReraGenie IDRG-KA-08432
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on26 May 2022
- Promised completion30 Jun 2024
- Revised completionNone
- Buildings1 building record
- Documents filed75 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SRI BALAJI SIGNATURE | - | - | - | 160 | 0 | 160 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 5 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities32
As on 5 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | - |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| N.RAMU | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 42.08 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vijay Associates |
| Engineer | CG Associates |
| Chartered Accountant | VENKATARAMANA P |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed75
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/260522/004922 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| BESCOM Fees paid ReceiptsFile: BESCOM Fees Paid Reciepts.pdf | 5 May 2022 |
| BESCOM NOC Self AttestedFile: BESCOM self attested NOC.pdf | 5 May 2022 |
| Demarcated CDP PlanFile: Demarcated Plan.jpeg | 5 May 2022 |
| BBMP PLAN - Development PlanFile: BBMP PLAN.pdf | 5 May 2022 |
| Sale Agreement ProformaFile: Agreement of Sale Proforma.pdf | 5 May 2022 |
| Partnership DeedFile: Partnership deed.pdf | 22 Mar 2022 |
| RERA Bank Account StatementFile: RERA Bank Account Statement.pdf | 22 Mar 2022 |
| BESCOM Fees paid ReceiptFile: BESCOM Fees Paid Reciepts.pdf | 22 Mar 2022 |
| BWSSB Fees paid ReceiptFile: bwssb receipt.pdf | 22 Mar 2022 |
| STP DrawingFile: STP Drawing.pdf | 22 Mar 2022 |
| Conversion OrderFile: conversion order.pdf | 22 Mar 2022 |
| Sale Agreement ProformaFile: Agreement of Sale Proforma.pdf | 22 Mar 2022 |
| Joint Affidavit Cum DeclarationFile: Joint Affidavit Cum Declaration Signed Copy.pdf | 22 Mar 2022 |
| Clarifications to Queries RaisedFile: Clarifications to Queries.pdf | 22 Mar 2022 |
| PlanFile: BBMP PLAN.pdf | 22 Mar 2022 |
| RTC, survey 25/6 | - |
| Mutation, survey 25/6 | - |
| Encumbrance Certificate, survey 25/6 | - |
| Conversion/Alienation Order, survey 25/6 | - |
| JDA, survey 25/6 | - |
| Khatha, survey 25/6 | - |
| Registration CertificateFile: structures firm registration.pdf | - |
| Partnership DeedFile: Partnership deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: structures form 1 - CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: signature Form 2 - ARCHITECT CERTIFICATE.pdf | - |
| Certificate issued by Engineer Form 3File: signature Form 3 - ENGINEER CERTIFICATE.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non Litigation Affidavit.pdf | - |
| Certificate from Chartered AccountFile: structures form 1 - CA Certificate.pdf | - |
| BESCOM NOC | - |
| BWSSB NOC | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| Specifications | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| Geddelahalli rectification of partnership deed | - |
| JDA uploaded | - |
| conversion order | - |
| Geddelahalli partition deed | - |
| Form B | - |
| Affidavit | - |
| Joint Affidavit Cum Declaration | - |
| BESCOM NOC | - |
| BWSSB NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| KSPCB | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Prospectus/BrochureFile: Sri-Balaji-Signature Brouchure.pdf | - |
| Advertisement Copy 1File: Sri-Balaji-Signature Brouchure.pdf | - |
| Occupancy CertificateFile: oc signature (1).pdf | - |
| Completion certificate issued by the competent authorityFile: oc signature (1).pdf | - |
| Registered Agreement of SaleFile: SALE AGREEMENT.pdf | - |
| Registered conveyance deed for an individual unitFile: SALE AGREEMENT.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SRI BALAJI SIGNATURE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
NAVA VRUKSHA
NAVA JYOTHI SHELTERS PRIVATE LIMITED
POULOMI FLORIQUE
POULOMI FLORIQUE LLP
Mirabelle
G Corp Homes Private Limited
DNR PARKLINK PHASE 2
DNR CORPORATION PVT LTD
NAVA SKANDA BELLAVITA
NAVA SKANDA PROJECTS
DNR PARKLINK PHASE 1
DNR CORPORATION PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: SRI BALAJI STRUCTURES
SRI BALAJI STRUCTURES has 2 registrations on RERA Karnataka, including SRI BALAJI SIGNATURE and SRI BALAJI SERENE. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SRI BALAJI SIGNATURE is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SRI BALAJI SIGNATURE?
The registered promoter entity is SRI BALAJI STRUCTURES, a partnership firm as per the filing. Its GSTIN 29AENFS5280H1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SRI BALAJI SIGNATURE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SRI BALAJI SIGNATURE?
The professionals named in the filing: Architect: Vijay Associates; Engineer: CG Associates; Chartered Accountant: VENKATARAMANA P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SRI BALAJI SIGNATURE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback