Home / Browse projects / Bengaluru Urban, Karnataka / SLN RESIDENCY

Registration approved No litigation declared Residential/Group Housing project

SLN RESIDENCY

By SKANDAS VENTURES

RG-KA-96957 · RERA PRM/KA/RERA/1251/446/PR/300125/007459 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
13 of 16Construction stages donefurthest along: Railing and Grill fixing, 93%
12 of 28Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 88 documents Report an error

SLN RESIDENCY is a Residential/Group Housing project by SKANDAS VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/300125/007459 on 30 Jan 2025. Possession is promised by 31 Dec 2026. 16 of the 28 units on this registration are recorded sold or booked, and 13 of 16 construction stages are filed complete.

At a glance

Project

  • NameSLN RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560099
  • Pincode560099
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/300125/007459
  • ReraGenie IDRG-KA-96957

Builder

  • NameSKANDAS VENTURES
  • Entity typePartnership Firm
  • GSTIN29AFDFS7929E1ZL
  • Authorized SignatoryK Doraswamy Raju

Key dates

this monthRegisteredJan 2025PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 Jan 2025
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed88 files

Current status

57%16 of 28 units booked
82.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SLN RESIDENCY---28028

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 16 construction stages are filed complete. The stage furthest along is Railing and Grill fixing, at 93%.

Building: 99% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing93%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work93%
Internal and External work including landscapes as per sanctioned drawings93%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes75%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes75%
Parks & Tree plantingYes0%
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes85%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes93%
BasementYes100%
TerraceYes100%
Outer WallYes90%
Open parking areasYes93%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,023 sq m
Named landowners2
LandownerVillageDistrict
Pankaja Bhaskar--
Vanjana N--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.26 cr
Cost incurredRs 8.48 cr
Spent of the estimate82.67%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 10.21 crRs 8.48 cr
Payment of taxesRs 5.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM Ramprasad
EngineerRajendra Babu V C
Chartered AccountantV Sekhar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed88

As listed on the registration, under the names the promoter filed them with; the newest 80 of 88 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/300125/007459 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q2 26 27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM4 Q1 26 27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 Q4 25-26.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SKANDA FORM6 Q1 26 27.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 Q4 25-26.pdf1 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM-5 Q4 25-26.pdf1 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 Q4 25-26.pdf1 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM4 Q3 2025-26.pdf26 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM5 Q3 2025-26.pdf26 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM6 Q3 2025-26.pdf26 Feb 2026
Balance SheetFile: Balance Sheet 2024-25.pdf23 Jan 2025
Common Area DetailsFile: Common Area Details-1.pdf23 Jan 2025
Project SpecificationsFile: Specifications.pdf23 Jan 2025
Section 3 AffidavitFile: Section 3 Affidavit.pdf23 Jan 2025
Updated Agreement for SaleFile: Agreement of Sale Proforma.pdf23 Jan 2025
BESCOM LETTERFile: BESCOM.pdf23 Jan 2025
BESCOM BILLFile: BESCOM Bill.jpeg23 Jan 2025
STP Design PlanFile: STP PLAN-01.pdf23 Jan 2025
STP LocationFile: STP LOCATION-01.pdf23 Jan 2025
Land CalculationFile: Land Cost.pdf23 Jan 2025
Water SourceFile: Project Water source.pdf23 Jan 2025
Water Source BorewellFile: borewell.jpeg23 Jan 2025
Water Source Borewell BillsFile: Borewell Bills.pdf23 Jan 2025
AmenitiesFile: Amenities.pdf23 Jan 2025
Amenities and FacilitiesFile: Amenities and Facilities.jpeg23 Jan 2025
Section and Floor PlansFile: Section and Floor Plans.pdf23 Jan 2025
RTC, survey 27/2-
Mutation, survey 27/2-
Encumbrance Certificate, survey 27/2-
Conversion/Alienation Order, survey 27/2-
Sale/Title/Gift Deed, survey 27/2-
JDA, survey 27/2-
Khatha, survey 27/2-
Registration CertificateFile: Form C.pdf-
GST CertificateFile: GST Registration.pdf-
Partnership DeedFile: Reconstitution Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form-1.pdf-
Certificate issued by Architect Form 2File: Form-2.pdf-
Certificate issued by Engineer Form 3File: Form-3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
CC-
ApprovedSanctioned Plan-
ApprovedSanctioned Plan-
Approved Plan-
ApprovedSanctioned Plan_compressed-
Brocher-
Relinquishment-
Sale Agreement Drsft-
Allotment Letter-
Form-B-
Section 3 Affidavit-
Joint Affidavit-
Legal Report-
BESCOM-
Water Source-
Pankaja KSPCB ack-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
HUSKUR Village Map-
HUSKUR Village Map Survey sketch of Demarcated-
CDP Map-
SLN RESIDENCY HUSKUR -Estimation-
BMRDA Plan Approval Letter-

How this compares with Bengaluru Urban

57%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SLN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSLN RESIDENCYOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: SKANDAS VENTURES

SKANDAS VENTURES has 1 registration on RERA Karnataka, including SLN RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SLN RESIDENCY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SLN RESIDENCY?

The registered promoter entity is SKANDAS VENTURES, a partnership firm as per the filing. Its GSTIN 29AFDFS7929E1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SLN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SLN RESIDENCY?

The professionals named in the filing: Architect: M Ramprasad; Engineer: Rajendra Babu V C; Chartered Accountant: V Sekhar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SLN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SLN RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SLN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.