Home / Browse projects / Bengaluru Urban, Karnataka / Mahendra Solterra Aarya Phase-2

Registration approved No litigation declared Residential/Group Housing project

Mahendra Solterra Aarya Phase-2

By Mahendra Homes Private Limited

RG-KA-19619 · RERA PRM/KA/RERA/1251/310/PR/281125/008282 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 0%
522 of 522Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 204 documents Report an error

Mahendra Solterra Aarya Phase-2 is a Residential/Group Housing project by Mahendra Homes Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/281125/008282 on 28 Nov 2025. Possession is promised by 31 Dec 2030. 0 of the 522 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameMahendra Solterra Aarya Phase-2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560099
  • Pincode560099
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/281125/008282
  • ReraGenie IDRG-KA-19619

Builder

  • NameMahendra Homes Private Limited
  • Entity typeCompany
  • CINU70102KA2011PTC060295
  • GSTIN29AAHCM5688C1Z3
  • Authorized SignatoryB T Nagaraj Reddy
  • Managing DirectorB T Nagaraj Reddy
  • DirectorsB T Nagaraj Reddy, Shanthamma, Nikitha N, Chaithra B N
  • Project HeadKumar Achari
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2025PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Nov 2025
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed204 files

Current status

0%0 of 522 units booked
1.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E---2020202
F---86086
G---2340234

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work0%
Foundation footing work0%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area33,791 sq m
Named landowners9
LandownerVillageDistrict
Mahendra Homes Private Limited--
Mahendra Homes Private Limited--
Mahendra Homes Private Limited--
Mahendra Homes Private Limited--
Mahendra Homes Private Limited--
Mahendra Homes Private Limited--
Srinivas U--
Srinivas U--
Mahendra Homes Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 303.87 cr
Cost incurredRs 3.45 cr
Spent of the estimate1.13%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 234.50 crRs 2.57 cr
Payment of taxesRs 42.21 crRs 40.13 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 15.00 crRs 44.57 lakh
On-site expenditure-Site OverheadRs 7.03 cr-
On-site expenditure-Consultants FeesRs 3.45 crRs 3.35 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.68 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGirish S
EngineerRajesh Shirakol
Chartered AccountantCA Vinaykumar Munolimath

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed204

As listed on the registration, under the names the promoter filed them with; the newest 80 of 204 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/281125/008282 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2 FY 2026-27 CA Certificate Form 4 Mahendra Solterra Aarya Phase-2_compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2 FY 2026-27 Architects Certificate Form 5 - Mahendra Solterra Aarya Phase-2 Project.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2 FY 2026-27 Engineers Certificate Form 6 - Mahendra Solterra Aarya Phase-2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q1_FY_2026-27_CA_Certificate_Form_4_Mahendra_Solterra_Aarya_Phase-2.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Q1_FY_2026-27_Architects_Certificate_Form_5_-_Mahendra_Solterra_Aarya_Phase-2_Project.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q1_FY_2026-27_Engineers_Certificate_Form_6_-_Mahendra_Solterra_Aarya_Phase-2.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA_Certificate-Solterra_Aarya-2-Q4-2025-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Q4_FY_2025-26_Architects_Certificate_Form_5_-_Mahendra_Solterra_Aarya_Project.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4_FY_2025-26_Engineers_Certificate_Form_6_-_Mahendra_Solterra_Aarya_Phase-2.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate-Solterra Arya-2-Q3-2025-26.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Arch-MH_Slt_-_Rera_25Dec.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg-cert_form-6_Aarya_Phase_2.pdf31 Mar 2026
Q3 2025-26 Water supply and sewage board31 Mar 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)31 Mar 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)31 Mar 2026
Q3 2025-26 KPTCL- BESCOM31 Mar 2026
Q3 2025-26 Fire and Safety31 Mar 2026
Q3 2025-26 Airport Authority of India31 Mar 2026
Q3 2025-26 BSNL/Telecommunication Department31 Mar 2026
Phodi MR-T7 Sy No 8 5 (Old Sy No 8 1)File: 1 Phodi MR-T7 Sy No 8 5 (Old Sy No 8 1).pdf27 Nov 2025
Form 3 Engineer CertificateFile: 3 Form 3 Engineer Certificate.pdf27 Nov 2025
Engineer LicenseFile: 3 Engineer License.pdf27 Nov 2025
Abstract EstimationFile: 3 Abstract Estimation.pdf27 Nov 2025
Structural Stability CertificateFile: 4 Structural Stability Certificate.pdf27 Nov 2025
Form-B-AffidavitFile: Form-B-Affidavit.pdf27 Nov 2025
Reply to QueryFile: Reply to Query.pdf27 Nov 2025
Reply to QueryFile: Reply to Query.pdf19 Nov 2025
OC -Aarna 5File: 1 OC -Aarna 5.pdf19 Nov 2025
Balance Sheet FY 24-25File: 2 Balance Sheet FY 24-25.pdf19 Nov 2025
Profit and Loss FY 24-25File: 2 Profit and Loss FY 24-25.pdf19 Nov 2025
Source of fund and Balance sheetFile: 3 Source of fund and Balance sheet.pdf19 Nov 2025
Declaration on Sales and Revenue from operationFile: 4 Declaration on Sales and Revenue from operation.pdf19 Nov 2025
RTC Sy No 7-2File: 5 RTC Sy No 7-2.pdf19 Nov 2025
RTC Sy No 7-3File: 5 RTC Sy No 7-3.pdf19 Nov 2025
RTC Sy No 8-2File: 5 RTC Sy No 8-2.pdf19 Nov 2025
RTC Sy No 8-3File: 5 RTC Sy No 8-3.pdf19 Nov 2025
RTC Sy No 8-5File: 5 RTC Sy No 8-5.pdf19 Nov 2025
RTC Sy No 11-2File: 5 RTC Sy No 11-2.pdf19 Nov 2025
RTC Sy No 11-3File: 5 RTC Sy No 11-3.pdf19 Nov 2025
RTC Sy No 14-1File: 5 RTC Sy No 14-1.pdf19 Nov 2025
RTC Sy No 34-3File: 5 RTC Sy No 34-3.pdf19 Nov 2025
MR H1 Sy No 7 2File: 6 MR H1 Sy No 7 2.pdf19 Nov 2025
MR 11 Sy No 11 and 14File: 6 MR 11 Sy No 11 and 14.pdf19 Nov 2025
MR T48 Sy No 11 3File: 6 MR T48 Sy No 11 3.pdf19 Nov 2025
MR T2 Sy No 14 1File: 6 MR T2 Sy No 14 1.pdf19 Nov 2025
MR-H2 Sy No 34 3File: 6 MR-H2 Sy No 34 3.pdf19 Nov 2025
MR T3 22-23 Sy No 34 2(Court Order)File: 6 MR T3 22-23 Sy No 34 2(Court Order).png19 Nov 2025
MR T3 Sy No 34 3File: 6 MR T3 Sy No 34 3.pdf19 Nov 2025
Grant OrderFile: 6 Grant Order.pdf19 Nov 2025
Partition DeedFile: 7 Partition Deed.pdf19 Nov 2025
Grant OrderFile: 7 Grant Order.pdf19 Nov 2025
EC Sy No 7-2 (01-01-2010 to 12-11-2025)File: 8 EC Sy No 7-2 (01-01-2010 to 12-11-2025).pdf19 Nov 2025
EC Sy No 7-3 (01-01-2010 to 12-11-2025)File: 8 EC Sy No 7-3 (01-01-2010 to 12-11-2025).pdf19 Nov 2025
EC Sy No 8-2 (01-01-2010 to 12-11-2025)File: 8 EC Sy No 8-2 (01-01-2010 to 12-11-2025).pdf19 Nov 2025
EC Sy No 8-3 (01-01-2010 to 12-11-2025)File: 8 EC Sy No 8-3 (01-01-2010 to 12-11-2025).pdf19 Nov 2025
EC Sy No 8-5 (01-04-2004 to 11-11-2025)File: 8 EC Sy No 8-5 (01-04-2004 to 11-11-2025).pdf19 Nov 2025
EC Sy No 11-2 (01-04-2010 to 12-11-2025)File: 8 EC Sy No 11-2 (01-04-2010 to 12-11-2025).pdf19 Nov 2025
EC Sy No 11-3 (01-04-2010 to 12-11-2025)File: 8 EC Sy No 11-3 (01-04-2010 to 12-11-2025).pdf19 Nov 2025
EC Sy No 14 1 (01-01-2010 to 12-11-2025)File: 8 EC Sy No 14 1 (01-01-2010 to 12-11-2025).pdf19 Nov 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Mahendra AaryaSy No. 6/1, 8/4, 9/2, 10/1, 12/1 & 13, Andapura Village, Attibele Hobli, Anekal Taluk, BengaluruOngoingDec 2025Not delivered

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Mahendra Solterra Aarya Phase-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMahendra Solterra Aarya Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: Mahendra Homes Private Limited

Mahendra Homes Private Limited has 3 registrations on RERA Karnataka, including M5 ECHELON and Mahendra AARNA 5. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Mahendra Solterra Aarya Phase-2 is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Mahendra Solterra Aarya Phase-2?

The registered promoter entity is Mahendra Homes Private Limited, a company as per the filing. Its CIN U70102KA2011PTC060295 and GSTIN 29AAHCM5688C1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Mahendra Solterra Aarya Phase-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Mahendra Solterra Aarya Phase-2?

The professionals named in the filing: Architect: Girish S; Engineer: Rajesh Shirakol; Chartered Accountant: CA Vinaykumar Munolimath. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahendra Solterra Aarya Phase-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahendra Solterra Aarya Phase-2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahendra Solterra Aarya Phase-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.