RG-KA-72878 · RERA PRM/KA/RERA/1263/419/PR/291025/008201 · Last updated on RERA Karnataka portal: 12 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SK-TOWER is a Residential/Group Housing project by RAVINDRA. S/O SHIVASHARANAPPA. K in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/291025/008201 on 29 Oct 2025. Possession is promised by 30 Dec 2028. 0 of the 16 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.
At a glance
Project
- NameSK-TOWER
- TypeResidential/Group Housing
- Location
- Kalaburagi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1263/419/PR/291025/008201
- ReraGenie IDRG-KA-72878
Builder
- NameRAVINDRA. S/O SHIVASHARANAPPA. K
- Entity typeProprietorship
- Authorized SignatoryRAVINDRA. S/O SHIVASHARANAPPA. K
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on29 Oct 2025
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed71 files
Current status
Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| S K TOWER | - | - | - | 16 | 0 | 16 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 16 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 95%.
Building: 53% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 95% |
| Retaining wall (All types) | 80% |
| RCC or MS Framed structure | 85% |
| Masonry Construction | 79% |
| Plastering inside , outside & Ceiling | 88% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 60% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 60% |
Progress on shared amenities40
As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 60% |
| Sewage and Drainage System | Yes | 70% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 80% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 80% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 70% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 80% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 85% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 70% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 70% |
| Basement | Yes | 85% |
| Terrace | Yes | 65% |
| Outer Wall | Yes | 70% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RAVINDRA. S/O SHIVASHARANAPPA. K | - | - |
| SHWETA D/O ARUN KUMAR AMBERKHANE | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1.41 cr | Rs 14.13 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | FIRDOUS KHANAM |
| Engineer | ER. MOHAMMED WAJEED ALI |
| Chartered Accountant | CA AEJAZ AHMED |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed71
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/291025/008201 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Certificate issued by Chartered Accountant.pdf | 12 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Certificate Issued by Architect.pdf | 12 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Certificate issued by Engineer.pdf | 12 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Certificate issued by Chartered Accountant.pdf | 9 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Certificate Issued by Architect.pdf | 9 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Certificate issued by Engineer.pdf | 9 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Certificate issued by Chartered Accountant.pdf | 7 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Certificate Issued by Architect.pdf | 7 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Certificate issued by Engineer.pdf | 7 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 7 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Certificate issued by Chartered Accountant.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Certificate Issued by Architect.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Certificate issued by Engineer.pdf | 13 Jan 2026 |
| POWER SUPPLY NOCFile: POWER SUPPLY NOC.pdf | 22 Oct 2025 |
| WATER SUPPLY NOCFile: WATER SUPPLY NOC.pdf | 22 Oct 2025 |
| Affidavit for GESCOMFile: Affidavit for GESCOM.pdf | 22 Oct 2025 |
| GESCOM BILL & RECEIPTFile: GESCOM BILL & RECEIPT.pdf | 22 Oct 2025 |
| DECLARATION REGARDING PROPRETORSHIPCERTIFICATEFile: DECLARATION REGARDING PROPRETORSHIPCERTIFICATE.pdf | 15 Sep 2025 |
| DECLARATION REGARDING GST CERTIFICATEFile: DECLARATION REGARDING GST CERTIFICATE.pdf | 15 Sep 2025 |
| DETAILS OF 3 BANK ACCOUNT WITH CA CERTIFICATE & BANK AFFIDAVITFile: Details of 3 Bank Account with CA Certificate & Bank Affidavit.pdf | 15 Sep 2025 |
| SOURCES OF FUNDFile: Sources Of Fund From RERA.pdf | 15 Sep 2025 |
| CLARIFICATION ON SALESFile: Clarification on Sales.pdf | 15 Sep 2025 |
| EC UPTO DATE FROM 11-08-2025 TO 10-09-2025File: EC Upto Date.pdf | 15 Sep 2025 |
| MOU FROM OWNER TO PROMOTER.File: MOU From Owner to Promoter.pdf | 15 Sep 2025 |
| FORM-6 ENGINEER CERTIFICATEFile: Form-6 Engineer Certificate.pdf | 15 Sep 2025 |
| AGREEMENT FOR SALE PROFORMA (AOS)File: Agreement for Sale AoS.pdf | 15 Sep 2025 |
| PROFORMA ALLOTMENT LETTER WITH POSSESSION DATEFile: Proforma Allotment Letter.pdf | 15 Sep 2025 |
| TITLE DEED FLOW OF TITLE TO THE OWNERFile: TITLE DEED FLOW OF TITLE TO THE OWNER.pdf | 15 Sep 2025 |
| Certificate issued by CA Form 1File: Certificate issued by CA Form 1.pdf | - |
| Certificate issued by Architect Form 2File: Certificate issued by Architect Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Certificate issued by Engineer Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non Litigation Affidavit.pdf | - |
| Balance Sheet 2023 - 2024File: Balance Sheet 2023 24.pdf | - |
| Balance Sheet 2022 - 2023File: Balance Sheet 2022 23.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Audited Profit and Loss Statement .pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Audited Profit and Loss Statement.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR 2022-23.pdf | - |
| Approval letter fror Authority | - |
| Approved Building Plan | - |
| Sectional Drawing of the apartments | - |
| Structural Stability | - |
| Project Specification | - |
| Brochure | - |
| Proforma of Agreement for Sale | - |
| Profarma Allotment Letter (1) | - |
| Declaration (Form B) | - |
| Section 3(1) Notarized Affidavit | - |
| JD AFFIDAVIT CUM DECLARATION | - |
| GESCOM NOC | - |
| Affidavit Cum Declaration waterboard | - |
| Land Cost Calculation | - |
| Authorization Letter | - |
| Amagamation Safety Order Copy | - |
| CTS COPY 1 | - |
| CTS Copy | - |
| Permission copy | - |
| Property Card | - |
| Rural Drinking Water & SS kalaburagi 1 | - |
| Rural Drinking Water & SS kalaburagi | - |
| Soil Test | - |
| Test Report Soil | - |
| CA certified Turn over copy | - |
| Zonal Regulations copy | - |
| Estimate Copy | - |
| Master Plan Extract Copy | - |
| Layout Order Copy | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kalaburagi
Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.
Keep SK-TOWER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalaburagi210+ in Kalaburagi
Kashi Kamal Gruh Yojana
M G Associates
BHARAT PRIDE PARK WING A & B
Bharat Dall and Oil Industries
BHARAT PRIDE PARK WING C & D
BHARAT DALL AND OIL INDUSTRIES
Kashikamal Phase 2
M.G. ASSOCIATES
G.V RAGHOJI ARCADE
M/s. R R BUILDERS AND DEVELOPERS
English County
Mahalaxmi Builder And developers
See every Kalaburagi project, with the district possession charts
Builder: RAVINDRA. S/O SHIVASHARANAPPA. K
RAVINDRA. S/O SHIVASHARANAPPA. K has 1 registration on RERA Karnataka, including SK-TOWER. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Kalaburagi district page.
Frequently asked questions
What are my rights if SK-TOWER is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SK-TOWER?
The registered promoter entity is RAVINDRA. S/O SHIVASHARANAPPA. K, a proprietorship as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SK-TOWER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SK-TOWER?
The professionals named in the filing: Architect: FIRDOUS KHANAM; Engineer: ER. MOHAMMED WAJEED ALI; Chartered Accountant: CA AEJAZ AHMED. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SK-TOWER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback