Home / Browse projects / Kalaburagi, Karnataka / BHARAT PRIDE PARK WING C & D

Registration approved No litigation declared Residential/Group Housing project

BHARAT PRIDE PARK WING C & D

By BHARAT DALL AND OIL INDUSTRIES

RG-KA-77881 · RERA PRM/KA/RERA/1263/419/PR/300523/005954 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
9 of 16Construction stages donefurthest along: Railing and Grill fixing, 80%
144 of 190Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 130 documents Report an error

BHARAT PRIDE PARK WING C & D is a Residential/Group Housing project by BHARAT DALL AND OIL INDUSTRIES in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/300523/005954 on 30 May 2023. Possession is promised by 31 Dec 2028. 46 of the 190 units on this registration are recorded sold or booked, and 9 of 16 construction stages are filed complete.

At a glance

Project

  • NameBHARAT PRIDE PARK WING C & D
  • TypeResidential/Group Housing
  • Location
    • Kalaburagi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1263/419/PR/300523/005954
  • ReraGenie IDRG-KA-77881

Builder

  • NameBHARAT DALL AND OIL INDUSTRIES
  • Entity typePartnership Firm
  • GSTIN29AABFB4629B2ZS
  • Authorized SignatoryGopal Krishna Agarwal
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 May 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed130 files

Current status

24%46 of 190 units booked
2.3%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---1170117
D---73073

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 16 construction stages are filed complete. The stage furthest along is Railing and Grill fixing, at 80%.

Building: 88% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification75%
Dadoing, Skirting, Flooring, Tiles work (All types)65%
Railing and Grill fixing80%
Electrification, Water supply and Sanitary Finishing80%
Painting70%
Fire prevention and fire fighting fitting and fixture with network70%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings60%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes85%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes95%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Solid waste management and disposalYes65%
Emergency Evacuation servicesYes55%
Internal Roads & FootpathsYes65%
Electricity supply transformer and substationYes80%
Storm water drainsYes85%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes85%
Parks & Tree plantingYes85%
Street LightingYes70%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes95%
LiftsYes95%
Corridor/LobbiesYes90%
Fire escapesYes90%
Common entrance and exit for the building/common portico/foyer/verandahYes85%
BasementYes100%
TerraceYes80%
Outer WallYes80%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes75%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
BHARAT DALL AND OIL INDUSTRIES--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 56.00 cr
Cost incurredRs 1.29 cr
Spent of the estimate2.3%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 56.00 crRs 1.29 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYALAVARTHI LAKSHMI DIVYA
EngineerYALAVARTHI NARASIMHA RAO
Chartered AccountantMAHAVEER CHAND SINGHVI

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed130

As listed on the registration, under the names the promoter filed them with; the newest 80 of 130 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/300523/005954 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: ca certificate.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Form.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Form.pdf13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Bharat Pride RERA Certificate.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: architect form.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: architect_compressed.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca certif.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: architect.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: eng certi.pdf15 Jan 2026
Title Deed In The Name Of Nandalal And Others (Sold To Promoter)File: Madan Lal And Others Title Deed Dated.pdf18 May 2023
CTS Record 688/1 And 822 For Sy No. 21 And 125File: cts.pdf18 May 2023
CLARIFICATION OF Promoter To Narendra Rathod For Sy No. 21 And 125 Dtd: 16.05.2019File: nr.pdf18 May 2023
Sale Deed 2475/1967-68 Dtd: 30.11.1967File: Madan Lal And Others Title Deed Dated.pdf18 May 2023
Fire ForceFile: noc fire.pdf18 May 2023
Rectified Copy Of The Proforma Of Agreement For Sale(Afs)File: aos.pdf18 May 2023
UPDATED ENGINEER CERTIFICATEFile: updated enginner certificate.pdf18 May 2023
Pollution Control Board NOCFile: KSPCB NOC.pdf26 Apr 2023
All Sanctioned Drawings Floor Plans, Sectional Drawings And ElevationsFile: all sanctioned drawings final.pdf26 Apr 2023
The NOC Of SEIAAFile: SEIAA NOC FINAL.pdf26 Apr 2023
The Building License Highlighting The Renewal SignatureFile: building license.pdf26 Apr 2023
Fire Force NOCFile: FIRE NOC.pdf26 Apr 2023
Updated the Booking Amount In Percentage Mentioned In The Para 7.1,And Uploaded the revised AOSFile: aos updated.pdf26 Apr 2023
NA COPY CLARIFICATIONFile: na order final.pdf26 Apr 2023
RTCFile: RTC.pdf6 Apr 2023
MR ExtractsFile: MR EXTRACTS.pdf6 Apr 2023
NA ORDERFile: na order.pdf6 Apr 2023
Advocate Search Report based on OriginalsFile: ADVOCATE SERCH REPORT NEW.pdf6 Apr 2023
Clear and legible copy of the Fire NOCFile: Fire NOC.pdf6 Apr 2023
Airport NOCFile: airport noc.jpeg6 Apr 2023
Updated proforma of Agreement for sale(AFS) as per the GOK notifiedFile: updated aos.pdf6 Apr 2023
Number of parking mentionedFile: No of car parking as per plan.pdf6 Apr 2023
certified Carpet area calculationFile: carpet area certification.pdf6 Apr 2023
village map of kapnoorFile: Kapnoor Village Map.pdf6 Apr 2023
KSPCB CFEFile: Pollution Control Board.pdf6 Apr 2023
relinquishment deedFile: Relinquishment Deed.pdf6 Apr 2023
all sanctioned drawings Floor plans, sectional drawings and elevationsFile: all sanctioned drawings final.pdf6 Apr 2023
SEIAA NOCFile: SEIAA NOC.pdf6 Apr 2023
Building LicenseFile: building license.pdf6 Apr 2023
Partnership registration Certificate Form-CFile: partnership registration certificate Form C.pdf27 Feb 2023
profit and loss accout with schedules along with UDIN FY 19-20File: pl 2021.pdf27 Feb 2023
profit and loss accout with schedules along with UDIN FY 20-21File: pl 2122.pdf27 Feb 2023
profit and loss accout with schedules along with UDIN FY 21-22File: pl 2223.pdf27 Feb 2023
Balance Sheet with schedules along with UDIN FY 19-20File: bs 2021.pdf27 Feb 2023
Balance Sheet with schedules along with UDIN FY 20-21File: bs 2122.pdf27 Feb 2023
Balance Sheet with schedules along with UDIN FY 21-22File: bs 2223.pdf27 Feb 2023
Chartered Accountant Certificate in the form -01File: ca certificate.pdf27 Feb 2023
RTC and MRFile: RTC AND MUTATION.pdf27 Feb 2023
Advocate Search ReportFile: Advocate Search Report.pdf27 Feb 2023
TITLE DEED / SALE DEEDFile: Sale Deed.pdf27 Feb 2023
CONVERSION ORDER FOR FULL PROJECTFile: conversion of project extent.pdf27 Feb 2023
Architect CertificateFile: architect certificate.pdf27 Feb 2023
Engineer CertificateFile: enginner certificate.pdf27 Feb 2023
PHASE WISE DEMARCATION DRAWING CERTIFIED BY ENGINEERFile: MASTER PLAN 22 LAKSHMI.pdf27 Feb 2023
NOC issued by GESCOMFile: GESCOM NOC1.pdf27 Feb 2023
Water supply NOCFile: NOC WATER BOARD FINAL.pdf27 Feb 2023
FIRE NOCFile: fire noc_compressed.pdf27 Feb 2023
SPECIFICATION WITH the project name and project address SIGNEDFile: specifications.pdf27 Feb 2023
Affadavit of Section 3(1) mentioning the project name and project addressFile: section 3 Affidavit.pdf27 Feb 2023
STP design drawing and STP demarcation drawingFile: stp drawing.pdf27 Feb 2023
Proforma of Allotment letterFile: allotment letter.pdf27 Feb 2023
Agreement for sale(AFS) highlight the any insertions, modifications, additional clausesFile: aos.pdf27 Feb 2023
Built up area Mentioned in the project detailsFile: BULIT UP AREA IN PLAN PLAYOUT.pdf27 Feb 2023
Number of parking mentioned in the project detailsFile: NO OF PARKING MENTIONED IN PLAN.pdf27 Feb 2023
Single plot layoutFile: Single Plot LAYOUT.pdf27 Feb 2023
Single plot layout OrderFile: Single plot approval order copy.pdf27 Feb 2023
certified Carpet area calculationFile: CARPET AREA DETAILS CERTIFIED.pdf27 Feb 2023
CDP map showing the proposed siteFile: CDP map.pdf27 Feb 2023
Village map showing the proposed siteFile: vilage map.pdf27 Feb 2023
KSPCB CFEFile: Pollution Control Board.pdf27 Feb 2023
Relinquishment DeedFile: Relinquishment Deed.pdf27 Feb 2023
Building LicenseFile: Building License.pdf27 Feb 2023
TYPICAL FLOOR 2ND TO 6TH PLANFile: TYPICAL FLOOR PLAN 2 TO 6 TH FLOORS COMPRESS.pdf27 Feb 2023
SEIAA NOCFile: SEIAA NOC.pdf27 Feb 2023
Phase wise demarcation drawingFile: DEMARCATED PLAN CERTIFIED BY ENGINEER.pdf27 Feb 2023
Elevation & SectionsFile: Elevation & Sections-ABCDE.pdf27 Feb 2023
BASEMENT 1 AND 2 PLAN OF C AND D WINGFile: BASEMENT 1 AND 2 PLAN OF C AND D WING.pdf27 Feb 2023
Ground Floor PLANFile: ground floor_compressed.pdf27 Feb 2023

How this compares with Kalaburagi

24%of this project is bookeddistrict median 0%
32%of Kalaburagi projects moved their completion datethis one has not
0%of Kalaburagi registrations are shown as withdrawn or revokedthis one is not

Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.

Keep BHARAT PRIDE PARK WING C & D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalaburagi210+ in Kalaburagi

Builder: BHARAT DALL AND OIL INDUSTRIES

Bharat Dall and Oil Industries has 2 registrations on RERA Karnataka, including BHARAT PRIDE PARK WING A & B and BHARAT PRIDE PARK WING C & D. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Kalaburagi district page.

Frequently asked questions

What are my rights if BHARAT PRIDE PARK WING C & D is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BHARAT PRIDE PARK WING C & D?

The registered promoter entity is BHARAT DALL AND OIL INDUSTRIES, a partnership firm as per the filing. Its GSTIN 29AABFB4629B2ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BHARAT PRIDE PARK WING C & D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BHARAT PRIDE PARK WING C & D?

The professionals named in the filing: Architect: YALAVARTHI LAKSHMI DIVYA; Engineer: YALAVARTHI NARASIMHA RAO; Chartered Accountant: MAHAVEER CHAND SINGHVI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHARAT PRIDE PARK WING C & D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHARAT PRIDE PARK WING C & D. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHARAT PRIDE PARK WING C & D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.