ReraGenieLog inGet a buyer report

Home / Browse projects / Kalaburagi, Karnataka / Kashikamal Phase 2

Registration approved No litigation declared Residential/Group Housing project

Kashikamal Phase 2

By M.G. ASSOCIATES

RG-KA-65932 · RERA PRM/KA/RERA/1263/419/PR/190226/008475 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 15Construction stages donefurthest along: Earth work and other leveling..., 30%
147 of 164Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 134 documents Report an error

Kashikamal Phase 2 is a Residential/Group Housing project by M.G. ASSOCIATES in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/190226/008475 on 19 Feb 2026. Possession is promised by 31 Dec 2029. 17 of the 164 units on this registration are recorded sold or booked, and 0 of 15 construction stages are filed complete.

At a glance

Project

  • NameKashikamal Phase 2
  • TypeResidential/Group Housing
  • Location
    • Kalaburagi
    • 585103
  • Pincode585103
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1263/419/PR/190226/008475
  • ReraGenie IDRG-KA-65932

Builder

  • NameM.G. ASSOCIATES
  • Entity typePartnership Firm
  • GSTIN29AARFM5415C1Z6
  • Authorized SignatoryRAGHAVENDRA KASHINATH MAILAPUR
  • Other registrations2 more →

Key dates

this monthRegisteredFeb 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Feb 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed134 files

Current status

10%17 of 164 units booked
8.4%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KK6---1640164

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 15 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 30%.

Building: 3% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work30%
Foundation footing work10%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,996 sq m
Named landowners4
LandownerVillageDistrict
M.G ASSOCIATES--
M.G ASSOCIATES--
M.G ASSOCIATES--
M.G ASSOCIATES--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 19.00 cr
Cost incurredRs 1.60 cr
Spent of the estimate8.42%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 19.00 crRs 1.60 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL Khamitkar
EngineerKhaja Ameer Khusroo
Chartered AccountantAkash Gilda

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed134

As listed on the registration, under the names the promoter filed them with; the newest 80 of 134 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/190226/008475 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: ca.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Artichet Certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: kk ca certificate.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Kashi Kamal Phase-2 ARCHGITECT.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: KK Form-6 Engineer Certificate (QU) (1).pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Declaration_Non_Availability_CA_Architect_Engineer_Kashikamal_Phase2.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Declaration_Non_Availability_CA_Architect_Engineer_Kashikamal_Phase2.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Declaration_Non_Availability_CA_Architect_Engineer_Kashikamal_Phase2.pdf15 Apr 2026
Clarification for noticeFile: Kashi Kamal Gruh Yojana Response.pdf6 Feb 2026
Clarification on KASHI KAMAL GRIH YOJANA QuarterlyFile: Kashi Kamal Declaration.pdf13 Jan 2026
katha extract of the project property issued by corporationFile: Final Khata Merge (2).pdf13 Nov 2025
Parking details with clarificationFile: Parking_merged.pdf13 Nov 2025
Correct title deed in favor of landowner for sno 37/1, 37/3 - 2 Copies attachedFile: Sale Deed Copies.pdf14 Oct 2025
latest katha extract of the project property issued by corporationFile: Final Khata Merge.pdf14 Oct 2025
Allotment LetterFile: ALLOTMENT_LETTER_KASHIKAMAL_PHASE_ FINAL.pdf14 Oct 2025
Upload partnership registration certificateFile: Point No 1 M G ASSOCIATES PARTNERSHIP DEED 2018-2019.pdf12 Sep 2025
Correct title deed in favour of landowner for sno 37/1, 37/3, 37/6 & 37/8File: Land Sale Deeds.pdf12 Sep 2025
Conversion order issued by deputy commissioner for sno 37/1, 37/3, 37/6 & 37/8File: Conversion Order for all serial numbers.pdf12 Sep 2025
Building License from Local Authority Original CopyFile: Commencement Certificate and Building Licence.pdf12 Sep 2025
ADLR ClarificationFile: Non Availability of ADLR.pdf12 Sep 2025
Sanction Plan with clear demarcation of Kashi Kamal PhaseFile: Kashi Kamal Clear Map with Demarcation along with Elevation and Floor Plan.jpg12 Sep 2025
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Kashi Kamal Clear Map with Demarcation along with Elevation and Floor Plan.jpg12 Sep 2025
Upload commencement certificateFile: Commencement Certificate and Building Licence.pdf12 Sep 2025
Clarification on Plan ValidityFile: Clarification on Plan Approval Validity.pdf12 Sep 2025
Non Applicability of KTCP Act NOCFile: Non Applicability of KTCP Act provisions and approvals.pdf12 Sep 2025
Once again informed to kindly upload the brief estimated cost of construction certifiedFile: Submission of Cost of Construction.pdf12 Sep 2025
Upload the bank affidavit in the prescribed formatFile: BANK AFFIDAVIT KK PHASE.pdf12 Sep 2025
Non LitigationFile: NON LITIGATION AFFIDAVIT KK PHASE 2.PDF12 Sep 2025
Amenities and common area details properly on the project with Engineer signFile: Amenities and common Engineer Certified.pdf12 Sep 2025
What are all sources of fund to complete the project with supporting documentsFile: Sources of funds.pdf12 Sep 2025
Upload Bank name should be as per bank account direction circular.File: RERA BANK ACCOUNT DETAILS.pdf12 Sep 2025
Water NOCFile: Water Board Letter Merged.pdf12 Sep 2025
STP EngineerFile: STP Self attested with engineer.pdf12 Sep 2025
Village MapFile: Village Map.pdf12 Sep 2025
Demarcation of proposed land in Approved Master plan Certified by the concern authority.File: CDP Map.pdf12 Sep 2025
KhataFile: Latest Khata.pdf12 Sep 2025
Once again informed to kindly upload the Land cost calculation sheet as per the guidance valueFile: Land Govt Guidance Value (2).pdf12 Sep 2025
KSPCB NOCFile: Pollution Control Board NOC.pdf12 Sep 2025
Agreement to saleFile: Agreement of Sale Proforma final kashikamal Phase 2.pdf12 Sep 2025
AllotmentFile: Allotment Letter.pdf12 Sep 2025
Applicability of Non Applicability of JDA AffidavitFile: Non Applicability of JDA.pdf12 Sep 2025
Approval cost and Construction Cost DetailsFile: Cost Letter Clarification.pdf12 Sep 2025
Point-wise Query Response and Document Status SheetFile: Point-wise Query Response and Document Status Sheet.pdf12 Sep 2025
Partnership Registration CertificateFile: Partnership DEED (3).pdf26 Jul 2025
Upload profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CFile: Annual Audit Report_compressed.pdf26 Jul 2025
Upload CA certificate in prescribed format form-01File: ca updated certificate.pdf26 Jul 2025
Upload Bank account detailsFile: KK6_RERA BANK ACCOUNT DETAILS.pdf26 Jul 2025
related conversion order issued by deputy commissioner for sno 37/1, 37/3, 37/6 & 37/8File: NA Order.pdf26 Jul 2025
Single Plan Layout PlanFile: Single Plan Layout Plan.pdf26 Jul 2025
Building License from Local Authority Original Copy.File: GDA Approved Letter_Kashi Kamal-6-7.pdf26 Jul 2025
Sale and Title DeedFile: Sale Deed.pdf26 Jul 2025
Water Permission LetterFile: L&T Letter_Water Board_KK.pdf26 Jul 2025
Electricity Permission LetterFile: Electricity Permission Letter.pdf26 Jul 2025
Electricity LetterFile: Electricity Letter.pdf26 Jul 2025
Audit Report 2024-25File: AUDIT REPORT 2024-25.pdf4 Jun 2025
CA CertificateFile: CA Certificate.pdf4 Jun 2025
Bank Account DetailsFile: RERA BANK ACCOUNT DETAILS.pdf4 Jun 2025
Encumbrance CertificateFile: EC.pdf4 Jun 2025
Encumbrance CertificateFile: KK-6 Building EC.pdf4 Jun 2025
Sale DeedFile: Sale Deed.pdf4 Jun 2025
KhataFile: Khata.pdf4 Jun 2025
NA Order Copy & Single Plot Layout Plan & GDA Approved Letter_Kashi KamalFile: NA Order Copy & Single Plot Layout Plan & GDA Approved Letter_Kashi Kamal.pdf4 Jun 2025
Affidavit Cum DeclarationFile: Affidavit Cum Declaration_Signed Copy.pdf4 Jun 2025
AffidavitFile: Affidavit.pdf4 Jun 2025
Form BFile: Form B.pdf4 Jun 2025
Certificate By EngineerFile: Certificate By Engineer.pdf4 Jun 2025
Electricity Permission LetterFile: Electricity Permission Letter.pdf4 Jun 2025
Karnataka Urban Water SupplyFile: Karnataka Urban Water Supply.jpg4 Jun 2025
Land Govt. Guidance ValueFile: Land Govt Guidance Value.pdf4 Jun 2025
Engineer CertificateFile: Updated Engineer Certificate.pdf4 Jun 2025
RTC, survey 37/1-
Mutation, survey 37/1-
Encumbrance Certificate, survey 37/1-
Conversion/Alienation Order, survey 37/1-
Sale/Title/Gift Deed, survey 37/1-
Khatha, survey 37/1-
RTC, survey 37/3-
Mutation, survey 37/3-
Encumbrance Certificate, survey 37/3-

How this compares with Kalaburagi

10%of this project is bookeddistrict median 0%
32%of Kalaburagi projects moved their completion datethis one has not
0%of Kalaburagi registrations are shown as withdrawn or revokedthis one is not

Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.

Keep Kashikamal Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalaburagi210+ in Kalaburagi

2 kmKashikamal Phase 2Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: M.G. ASSOCIATES

M G Associates has 3 registrations on RERA Karnataka, including Kashi Kamal Gruh Yojana and Mahalaxmi Amman Arcade. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Kalaburagi district page.

Frequently asked questions

What are my rights if Kashikamal Phase 2 is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Kashikamal Phase 2?

The registered promoter entity is M.G. ASSOCIATES, a partnership firm as per the filing. Its GSTIN 29AARFM5415C1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Kashikamal Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Kashikamal Phase 2?

The professionals named in the filing: Architect: RAHUL Khamitkar; Engineer: Khaja Ameer Khusroo; Chartered Accountant: Akash Gilda. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kashikamal Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kashikamal Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kashikamal Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.