RG-KA-60645 · RERA PRM/KA/RERA/1251/310/PR/120625/007819 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 3 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Apr 2030Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 90%
58 of 344Units unsoldnot recorded sold or booked
3Complaints at RERA Karnatakaon this registration
Jump to the 133 documents Report an error

SHRIRAM SONGS OF THE EARTH is a Residential/Group Housing project by Shriram Properties Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/120625/007819 on 12 Jun 2025. Possession is promised by 28 Apr 2030. 286 of the 344 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSHRIRAM SONGS OF THE EARTH
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560099
  • Pincode560099
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/120625/007819
  • ReraGenie IDRG-KA-60645

Builder

  • NameShriram Properties Limited
  • Entity typeCompany
  • CINU72200TN2000PLC044560
  • GSTIN29AAFCS5801D1ZI
  • Authorized SignatoryKRISHNA VEERARAGHAVAN
  • Director & Chief Operating OfficerKRISHNA VEERARAGHAVAN
  • DirectorsM Murali, Vaidyanathan Ramamurthy, Kulumani Gopalrathnam Krishnamurthy, Thai Salas Vijayan, Anita Kapoor, Ashish Pradeep Deora
  • Project HeadSunil Kumar Rana
  • Other registrations4 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredJun 2025PromisedApr 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 Jun 2025
  • Promised completion28 Apr 2030
  • Revised completionNone
  • Buildings6 building records
  • Documents filed133 files

Current status

83%286 of 344 units booked
5.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower-1---58058
TOWER 2---58058
Tower 3---56056
Tower 4---56056
Tower 5---58058
Tower 6---58058

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.

Building: 12% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work90%
Foundation footing work60%
Upto Plinth Level15%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)5%
Retaining wall (All types)36%
RCC or MS Framed structure1%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities38

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,256 sq m
Named landowners2
LandownerVillageDistrict
Shriram Properties Limited--
Shriram Properties Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 175.69 cr
Cost incurredRs 8.73 cr
Spent of the estimate4.97%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 151.24 crRs 7.56 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 23.00 crRs 1.05 cr
On-site expenditure-Consultants FeesRs 1.45 crRs 12.39 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectED+ ARCHITECTURE
EngineerInnotech Engineering Consultant Pvt Ltd
Chartered AccountantVivek Gupta

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
01376/2025-Shriram Properties Limited12/11/2025
00413/2026-Shriram Properties Limited17/04/2026
00517/2026-Shriram Properties Limited13/05/2026

Documents filed133

As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/120625/007819 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Songs of the Earth Sep'26.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) _SOE_Q2 2026-27.PDF15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate (QU) Songs of the earth Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Songs of the Earth June'26.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) _SOE_Q1 2026-27.PDF13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate (QU) Songs of the earth.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Songs of the Earth March'26.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate (QU) SOE.PDF13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate (QU) Songs of the earth.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Songs of the Earth Dec'25.pdf7 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) _Songs of the Earth_Q3 2025-26.PDF7 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate (QU) Q3 Songs of the earth.pdf7 Feb 2026
previous project quarterly updates up to dateFile: Screenshot 2025-05-26 182726.png26 May 2025
previous project quarterly updates up to dateFile: Screenshot 2025-05-26 182549.png26 May 2025
previous project quarterly updates up to dateFile: Screenshot 2025-05-26 182414.png26 May 2025
directors report for 2023-24File: Directors Report FY24.pdf26 May 2025
directors report for 2023-24File: Directors Report FY24.pdf26 May 2025
Loan amount deposited into RERA designated accountFile: Loan amount.pdf26 May 2025
copy of current year RTCFile: 202 3.pdf26 May 2025
copy of current year RTCFile: 202 2.pdf26 May 2025
copy of current year RTCFile: 202 1.pdf26 May 2025
copy of current year RTCFile: 199 2.pdf26 May 2025
copy of current year RTCFile: 199 1.pdf26 May 2025
free EC from 1/4/2011 to till dateFile: ilovepdf_merged.pdf26 May 2025
title deedFile: TITTLE DATED.pdf26 May 2025
notarized affidavitFile: Affidavit for Non-Litigation.pdf26 May 2025
Layout/Development/single plan approved letterFile: Development Plan Pillai Land Project Clr scan1579.pdf26 May 2025
Layout/Development/ single approval planFile: Site Plan Pillai Land Project Clr scan1580.pdf26 May 2025
Building plan Blue print in readable format.File: Development Plan Pillai Land Project Clr scan1579.pdf26 May 2025
Building licenseFile: Building LIcense.pdf26 May 2025
Master Plan proposed area with consent authority seal and signature.File: MASTER PLAN.pdf26 May 2025
Village Map.File: Village Map.pdf26 May 2025
ZR copy with consent authority seal and signature.File: ANEKAL- ZONAL REGULATIONS.pdf26 May 2025
JOINT ADLR Survey Sketch.File: ADLR SKETCH.pdf26 May 2025
floor plan and section plan.File: TYPICAL FLOOR AND TERRACE FLOOR PLAN.pdf26 May 2025
KSPCB NOCFile: NOC KSPCB.pdf26 May 2025
SEIAA NOCFile: NOC SEIAA.pdf26 May 2025
project Engineer details according to Engineer licenseFile: Engineer-4-Self attested copy of Engineer License.pdf26 May 2025
Engineer certificate in the prescribed format certified by an registered Engineer instead of an ArcFile: Form - 3 Engineer Certificate - With Construction cost brief (003) NEW.pdf26 May 2025
STP design drawing does not tally with the KPSCB NOC.File: STP REPORT 270 KLD.pdf26 May 2025
STP design drawing as per the Guidelines of KSPCB NOC certified by the Engineer.File: STP 270 KLD LAYOUT.pdf26 May 2025
NOC issued by BESCOMFile: NOC BESCOM dated 17 December 24 Pillai Land Project Anekal Pages 04 STech_931824122613080.26 May 2025
HAL NOC.File: Shriram Pillai Land HAL Acknowledgement.pdf26 May 2025
HAL NOC LETTERFile: Letter - HAL NOC acknowledgement submission.pdf26 May 2025
Land cost calculation sheet as per the guidance valueFile: Land cost.pdf26 May 2025
Payment plan in percentage and upload the proforma of the Agreement for Sale.File: 17-4-2025-RERA Format- Agreement for Sale-Songs of the Earth.pdf26 May 2025
annexure-A and upload the proforma of the Allotment letter.File: Annexture-87 Allotment letter witn Annexure A.pdf26 May 2025
brief estimated cost of construction certified by the Engineer.File: COST OF CONSTRUCTION.pdf26 May 2025
CPD PLANFile: CDP - SONGS OF THE EARTH-.pdf26 May 2025
Section and elevationFile: SECTION AND ELEVATION_.pdf26 May 2025
RTC, survey 199/1-
Mutation, survey 199/1-
Encumbrance Certificate, survey 199/1-
Conversion/Alienation Order, survey 199/1-
Sale/Title/Gift Deed, survey 199/1-
Khatha, survey 199/1-
RTC, survey 202/1-
Mutation, survey 202/1-
Encumbrance Certificate, survey 202/1-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date3 under way, not due yet
ProjectLocationStatusPromisedDelivered
SHRIRAM SERENITYSY.NO 74/8, 74/10, 74/12, 74/13 & 74/15 ADDEVISWANATHAPURA VILLAGE, HESARAGHATTA HOBLI , YELAHANKA TALUK BANGALORE URBAN , Bengaluru North , Bengaluru Urban, Karnataka - 560064OngoingJul 2029Not due yet
SHRIRAM SAPPHIRESy.No-72, Bommasandra Village, Attibele-Hobli , Anekal Taluk, Bangalore-Urban , Bengaluru South , Bengaluru Urban, Karnataka - 560099OngoingNov 2028Not due yet
SHRIRAM ESQUIREPID No-600005711 Site No-91 to 98 at HBCS LTD , Nirguna Mandir Layout , Bengaluru South , Bengaluru Urban, Karnataka - 560034OngoingJan 2027Not due yet
SHRIRAM MYSTIQUE15/2 ROYAL STREET, MYDRAHALLI YESHWANTHAPURA HOBLI BBMP WARD NO 12 BANGALORE 560090OngoingApr 2025Not delivered

How this compares with Bengaluru Urban

83%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHRIRAM SONGS OF THE EARTH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHRIRAM SONGS OF THE EAROther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: Shriram Properties Limited

SHRIRAM PROPERTIES LIMITED has 5 registrations on RERA Karnataka, including SHRIRAM SERENITY and SHRIRAM ESQUIRE. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHRIRAM SONGS OF THE EARTH is delayed beyond 28 Apr 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM SONGS OF THE EARTH?

The registered promoter entity is Shriram Properties Limited, a company as per the filing. Its CIN U72200TN2000PLC044560 and GSTIN 29AAFCS5801D1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM SONGS OF THE EARTH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRIRAM SONGS OF THE EARTH?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SHRIRAM SONGS OF THE EARTH?

The professionals named in the filing: Architect: ED+ ARCHITECTURE; Engineer: Innotech Engineering Consultant Pvt Ltd; Chartered Accountant: Vivek Gupta. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM SONGS OF THE EARTH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM SONGS OF THE EARTH. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM SONGS OF THE EARTH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.