Home / Browse projects / Vadodara, Gujarat / SHREE TWO

Valid until 31 Mar 2023 Residential/Group Housing project

SHREE TWO

By SHREEJI INFRA

RG-GJ-52511 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA04817/EX1/060422 · Last updated on GujRERA portal: 7 Dec 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2023Possession promisedmoved 11 months from the original
36 of 48Construction stages doneacross 6 buildings; furthest along: Installation of lifts, 95%
21 of 84Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

SHREE TWO is a Residential/Group Housing project by SHREEJI INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA04817/EX1/060422 on 8 Feb 2019. Possession is promised by 31 Mar 2023. The completion date has moved by 11 months from the original filing. 63 of the 84 units on this registration are recorded sold or booked, and 36 of 48 construction stages are filed complete.

At a glance

Project

  • NameSHREE TWO
  • TypeResidential/Group Housing
  • Location
    • 'SHREE TWO'
    • F.P. 54
    • T.P. 2 (BHAYLI-2)
    • NR. NILAMBER PALMS BUNGALOWS
    • BHAYLI
    • VADODARA
    • Bhayli
    • Vadodara
    • 391101
  • Pincode391101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA04817/EX1/060422
  • ReraGenie IDRG-GJ-52511

Builder

  • NameSHREEJI INFRA
  • Entity typePARTNERSHIP FIRM
  • Other registrations31 more →

Key dates

this monthRegisteredFeb 2019First promiseApr 2022Revised toMar 2023

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2023
  • Registered on8 Feb 2019
  • Promised completion31 Mar 2023
  • Revised completionRevised to 31 Mar 2023 (originally 1 Apr 2022)
  • Buildings6 building records
  • Documents filed46 files

Current status

75%63 of 84 units booked
90.9%Of the estimated cost spent so far

Figures as on 7 Dec 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---14014
B---14014
C---14014
D---14014
E---14014
F---14014

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 7 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 48 construction stages are filed complete across 6 buildings. The stage furthest along is Installation of lifts, at 95%.

A87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
B86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
C85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
D85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
E85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
F87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 7 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes85%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes20%
Fire fightingYes90%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,329 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 13.67 cr
Cost incurredRs 12.42 cr
Spent of the estimate90.87%
BuildingWingEstimatedIncurred
ANARs 2.28 crRs 2.07 cr
BNARs 2.28 crRs 2.07 cr
CNARs 2.28 crRs 2.07 cr
DNARs 2.28 crRs 2.07 cr
ENARs 2.28 crRs 2.07 cr
FNARs 2.28 crRs 2.07 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMISHAL BHARATBHAI DODIA
EngineerGIRISH H DHANWANI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA04817/EX1/060422Applied Feb 2022; approved Apr 2022

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA04817/EX1/060422 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Dec 2022
Engineer's certificate (Form 2)7 Dec 2022
Engineer's certificate annexure7 Dec 2022
Accountant's certificate (Form 3)7 Dec 2022
Site photograph, A7 Dec 2022
Site photograph, B7 Dec 2022
Site photograph, C7 Dec 2022
Site photograph, D7 Dec 2022
Site photograph, E7 Dec 2022
Site photograph, F7 Dec 2022
RERA registration certificate8 Feb 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

75%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 11 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHREE TWO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhayli2,900+ in Vadodara

2 kmSHREE TWOOther 397Dot size: filed unitsN

Filed coordinates, straight-line distance. 397 registered projects within 2 km.

Builder: SHREEJI INFRA

SHREEJI INFRA has 32 registrations on GujRERA, including AUROVILLE and STHAPATYA SHREEM. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHREE TWO is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE TWO?

The registered promoter entity is SHREEJI INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE TWO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE TWO?

The professionals named in the filing: Architect: MISHAL BHARATBHAI DODIA; Engineer: GIRISH H DHANWANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE TWO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE TWO. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE TWO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.