ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / SHREE SIDDHESHWAR PRIME PLUS

Valid until 30 Apr 2027 Mixed Development project

SHREE SIDDHESHWAR PRIME PLUS

By S P INFRA

RG-GJ-09205 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA10280/080622 · Last updated on GujRERA portal: 21 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
2 of 9Construction stages donefurthest along: Slabs of Super Structure, 90%
80 of 173Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SHREE SIDDHESHWAR PRIME PLUS is a Mixed Development project by S P INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA10280/080622 on 8 Jun 2022. Possession is promised by 30 Apr 2027. 93 of the 173 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHREE SIDDHESHWAR PRIME PLUS
  • TypeMixed Development
  • Location
    • SHREE SIDDHESHWAR PRIME PLUS BESIDE SHREE SIDDHESHWAR PARADISE
    • NEAR BRIGHT SCHOOL 30 MTR HARNI SAMA LINK ROAD HARNI
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA10280/080622
  • ReraGenie IDRG-GJ-09205

Builder

  • NameS P INFRA
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredJun 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on8 Jun 2022
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Current status

54%93 of 173 units booked
60.5%Of the estimated cost spent so far

Figures as on 21 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIDDHESHWAR PRIME PLUS---36137173

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

SIDDHESHWAR PRIME PLUS: 48% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats30%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 21 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,898 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 18.40 cr
Cost incurredRs 11.13 cr
Spent of the estimate60.5%
BuildingWingEstimatedIncurred
SIDDHESHWAR PRIME PLUSNARs 18.40 crRs 11.13 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAMTA SHAH & ASSOCIATES
EngineerZARNA ASSOCIATES

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA10280/080622 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)21 Oct 2024
Engineer's certificate annexure21 Oct 2024
RERA registration certificate8 Jun 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

54%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHREE SIDDHESHWAR PRIME PLUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmSHREE SIDDHESHWAR PRIME Other 175Dot size: filed unitsN

Filed coordinates, straight-line distance. 175 registered projects within 2 km.

Builder: S P INFRA

S P INFRA has 3 registrations on GujRERA, including SIDDHESHWAR PLAZA and SHREE SIDDHESHWAR PARADISE. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHREE SIDDHESHWAR PRIME PLUS is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE SIDDHESHWAR PRIME PLUS?

The registered promoter entity is S P INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE SIDDHESHWAR PRIME PLUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE SIDDHESHWAR PRIME PLUS?

The professionals named in the filing: Architect: MAMTA SHAH & ASSOCIATES; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SIDDHESHWAR PRIME PLUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SIDDHESHWAR PRIME PLUS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SIDDHESHWAR PRIME PLUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.