Home / Browse projects / Vadodara, Gujarat / SHREE HARI

Valid until 31 Dec 2021 Mixed Development project

SHREE HARI

By SHREE HARI DEVELOPERS

RG-GJ-27947 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA01922/EX1/030821 · Last updated on GujRERA portal: 31 Dec 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Separate project account declared
Dec 2021Possession promisedmoved 6 months from the original
2 of 7Construction stages donefurthest along: Internal walls, 98%
6 of 77Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SHREE HARI is a Mixed Development project by SHREE HARI DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA01922/EX1/030821 on 7 Mar 2018. Possession is promised by 31 Dec 2021. The completion date has moved by 6 months from the original filing. 71 of the 77 units on this registration are recorded sold or booked, and 2 of 7 construction stages are filed complete.

At a glance

Project

  • NameSHREE HARI
  • TypeMixed Development
  • Location
    • Shri Hari
    • FP 94
    • TP 33
    • RS No 308
    • Maneja
    • Maneja
    • Vadodara
    • 390013
  • Pincode390013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA01922/EX1/030821
  • ReraGenie IDRG-GJ-27947

Builder

  • NameSHREE HARI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations28 more →

Key dates

this monthRegisteredMar 2018First promiseJun 2021Revised toDec 2021

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2021
  • Registered on7 Mar 2018
  • Promised completion31 Dec 2021
  • Revised completionRevised to 31 Dec 2021 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed38 files

Current status

92%71 of 77 units booked
93.6%Of the estimated cost spent so far

Figures as on 31 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER ABCD---68977

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 31 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 7 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

TOWER ABCD: 99% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%

Progress on shared amenities19

As on 31 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes98%
Water supplyYes98%
Sewerage (chamber, lines, septic tank, STP)Yes98%
Storm water drainsYes98%
Landscaping and tree plantingYes98%
Street lightingYes98%
Community buildingsYes98%
Treatment and disposal of sewage and sullage waterYes98%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes98%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,760 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.25 cr
Cost incurredRs 3.98 cr
Spent of the estimate93.64%
BuildingWingEstimatedIncurred
TOWER ABCDNARs 4.25 crRs 3.98 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRISHI ARCHITECT AND INTERIOR DESIGNER
EngineerZARNA ASSOCIATES

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA01922/EX1/030821Applied Jun 2021; approved Aug 2021

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA01922/EX1/030821 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)31 Dec 2021
Engineer's certificate (Form 2)31 Dec 2021
Engineer's certificate annexure31 Dec 2021
Accountant's certificate (Form 3)31 Dec 2021
Site photograph, TOWER ABCD31 Dec 2021
RERA registration certificate7 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

92%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 6 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHREE HARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Maneja2,900+ in Vadodara

2 kmSHREE HARIOther 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: SHREE HARI DEVELOPERS

SHREE HARI DEVELOPERS has 29 registrations on GujRERA, including AMBIKA DHAM and Shyam Shree. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHREE HARI is delayed beyond 31 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE HARI?

The registered promoter entity is SHREE HARI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE HARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE HARI?

The professionals named in the filing: Architect: RISHI ARCHITECT AND INTERIOR DESIGNER; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE HARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE HARI. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE HARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.