Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2028Possession promisedno revision filed
102 of 135Construction stages doneacross 15 buildings; furthest along: External plumbing and external plaster, 90%
23 of 86Units unsoldnot recorded sold or booked
Jump to the 56 documents Report an error

SHIVAM BLISS is a Residential/Group Housing project by SHREE UMA ENTERPRISE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA11642/210423 on 21 Apr 2023. Possession is promised by 28 Jun 2028. 63 of the 86 units on this registration are recorded sold or booked, and 102 of 135 construction stages are filed complete.

At a glance

Project

  • NameSHIVAM BLISS
  • TypeResidential/Group Housing
  • Location
    • Revenue Survey 865/3
    • T.P. No. - 52
    • F.P. No. - 865/3/1 (Phase-1) & 865/3/2 (Phase-2)
    • Moje - Tarsali
    • Taluka-District: Vadodara
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA11642/210423
  • ReraGenie IDRG-GJ-04103

Builder

  • NameSHREE UMA ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2023PromisedJun 2028

Key facts

Registration and timeline

  • StatusValid until 28 Jun 2028
  • Registered on21 Apr 2023
  • Promised completion28 Jun 2028
  • Revised completionNone
  • Buildings15 building records
  • Documents filed56 files

Current status

73%63 of 86 units booked
78.3%Of the estimated cost spent so far

Figures as on 3 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PLOT 21---101
PLOT 1 TO 20---20020
PLOT 23 TO 38---16016
PLOT 22---101
PLOT 52---101
PLOT 39 TO 51---13013
PLOT 54 TO 63---10010
PLOT 53---101
PLOT 65---101
PLOT 64---101
PLOT 76---101
PLOT 66 TO 75---10010
PLOT 78 TO 85---808
PLOT 77---101
PLOT 86---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building15

As on 3 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

102 of 135 construction stages are filed complete across 15 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

PLOT 21100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
PLOT 1 TO 20100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
PLOT 23 TO 38100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
PLOT 22100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
PLOT 5287%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 39 TO 5170%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats81%
Sanitary fittings within the flats46%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 54 TO 6369%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 5371%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 6583%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 6483%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 7678%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 66 TO 7578%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 78 TO 8585%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats87%
Sanitary fittings within the flats87%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 7788%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
PLOT 8666%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 3 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,840 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 23.50 cr
Cost incurredRs 18.40 cr
Spent of the estimate78.29%
BuildingWingEstimatedIncurred
PLOT 1 TO 20NARs 5.47 crRs 5.47 cr
PLOT 23 TO 38NARs 4.37 crRs 4.37 cr
PLOT 39 TO 51NARs 3.55 crRs 2.19 cr
PLOT 66 TO 75NARs 2.73 crRs 2.22 cr
PLOT 54 TO 63NARs 2.73 crRs 1.06 cr
PLOT 78 TO 85NARs 2.19 crRs 1.17 cr
PLOT 21NARs 27.41 lakhRs 27.41 lakh
PLOT 22NARs 27.41 lakhRs 27.41 lakh
PLOT 52NARs 27.41 lakhRs 18.16 lakh
PLOT 53NARs 27.41 lakhRs 15.66 lakh
PLOT 64NARs 27.41 lakhRs 14.51 lakh
PLOT 65NARs 27.41 lakhRs 26.11 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN RASHIKBHAI PATEL
EngineerDHRUV C PATEL

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA11642/210423 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)3 Apr 2026
Architect's certificate (Form 1)2 Apr 2026
Engineer's certificate (Form 2)2 Apr 2026
Engineer's certificate annexure2 Apr 2026
Site photograph, PLOT 212 Apr 2026
Site photograph, PLOT 1 TO 202 Apr 2026
Site photograph, PLOT 23 TO 382 Apr 2026
Site photograph, PLOT 222 Apr 2026
Site photograph, PLOT 522 Apr 2026
Site photograph, PLOT 39 TO 512 Apr 2026
Site photograph, PLOT 54 TO 632 Apr 2026
Site photograph, PLOT 532 Apr 2026
Site photograph, PLOT 652 Apr 2026
Site photograph, PLOT 642 Apr 2026
Site photograph, PLOT 762 Apr 2026
Site photograph, PLOT 66 TO 752 Apr 2026
Site photograph, PLOT 78 TO 852 Apr 2026
Site photograph, PLOT 772 Apr 2026
Site photograph, PLOT 862 Apr 2026
Site photograph, PLOT 862 Apr 2026
RERA registration certificate21 Apr 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

73%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHIVAM BLISS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmSHIVAM BLISSOther 121Dot size: filed unitsN

Filed coordinates, straight-line distance. 121 registered projects within 2 km.

Builder: SHREE UMA ENTERPRISE

SHREE UMA ENTERPRISE has 1 registration on GujRERA, including SHIVAM BLISS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHIVAM BLISS is delayed beyond 28 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVAM BLISS?

The registered promoter entity is SHREE UMA ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVAM BLISS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVAM BLISS?

The professionals named in the filing: Architect: KIRAN RASHIKBHAI PATEL; Engineer: DHRUV C PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVAM BLISS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVAM BLISS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVAM BLISS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.