ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / Shivalik Residency

Valid until 30 Apr 2029 Residential/Group Housing project

Shivalik Residency

By SHIVALIK RESIDENCY

RG-GJ-96845 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA12424/121023 · Last updated on GujRERA portal: 3 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
5 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 11%
65 of 69Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Shivalik Residency is a Residential/Group Housing project by SHIVALIK RESIDENCY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA12424/121023 on 12 Oct 2023. Possession is promised by 30 Apr 2029. 4 of the 69 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.

At a glance

Project

  • NameShivalik Residency
  • TypeResidential/Group Housing
  • Location
    • Shivalik Residency
    • Near Desaipura
    • Karodiya
    • Vadodara
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA12424/121023
  • ReraGenie IDRG-GJ-96845

Builder

  • NameSHIVALIK RESIDENCY
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2023PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on12 Oct 2023
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed38 files

Current status

6%4 of 69 units booked
11.7%Of the estimated cost spent so far

Figures as on 3 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE-AA---34034
TYPE-A---35035

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 3 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 11%.

TYPE-AA23%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor3%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats3%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing3%
TYPE-A36%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor11%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats6%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing6%

Progress on shared amenities23

As on 3 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,342 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.00 cr
Cost incurredRs 34.97 lakh
Spent of the estimate11.66%
BuildingWingEstimatedIncurred
TYPE-AANARs 1.60 crRs 13.97 lakh
TYPE-ANARs 1.40 crRs 21.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARSH P PANDYA (HARSH PANDYA & ASSOCIATES)
EngineerCHETAN M KAMBAD

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA12424/121023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)3 Oct 2024
Engineer's certificate annexure3 Oct 2024
RERA registration certificate12 Oct 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

6%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Shivalik Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmShivalik ResidencyOther 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: SHIVALIK RESIDENCY

SHIVALIK RESIDENCY has 1 registration on GujRERA, including Shivalik Residency. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Shivalik Residency is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Shivalik Residency?

The registered promoter entity is SHIVALIK RESIDENCY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Shivalik Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shivalik Residency?

The professionals named in the filing: Architect: HARSH P PANDYA (HARSH PANDYA & ASSOCIATES); Engineer: CHETAN M KAMBAD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shivalik Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shivalik Residency. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shivalik Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.