SHIVALAY BLISS PHASE-2

By SHIV SHAKTI REALITY

RG-GJ-52778 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA10211/180522 · Last updated on GujRERA portal: 3 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2027Possession promisedno revision filed
25 of 27Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 20%
42 of 167Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SHIVALAY BLISS PHASE-2 is a Mixed Development project by SHIV SHAKTI REALITY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA10211/180522 on 18 May 2022. Possession is promised by 31 Mar 2027. 125 of the 167 units on this registration are recorded sold or booked, and 25 of 27 construction stages are filed complete.

At a glance

Project

  • NameSHIVALAY BLISS PHASE-2
  • TypeMixed Development
  • Location
    • OPP TAKSH AURA
    • BH L & T KNOWLEDGE CITY
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA10211/180522
  • ReraGenie IDRG-GJ-52778

Builder

  • NameSHIV SHAKTI REALITY
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2022PromisedMar 2027

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2027
  • Registered on18 May 2022
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed38 files

Current status

75%125 of 167 units booked
80.5%Of the estimated cost spent so far

Figures as on 3 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER AB---421456
TOWER C---40040
TOWER DE---571471

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 3 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 20%.

TOWER AB89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER DE91%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 3 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes60%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsYes50%
Landscaping and tree plantingYes60%
Street lightingYes70%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes60%
Plinth protectionYes70%
Water tankYes60%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,845 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 22.73 cr
Cost incurredRs 18.30 cr
Spent of the estimate80.49%
BuildingWingEstimatedIncurred
TOWER DENARs 8.82 crRs 4.39 cr
TOWER CNARs 7.50 crRs 7.50 cr
TOWER ABNARs 6.41 crRs 6.41 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHILASH KETANKUMAR PANDYA
EngineerVIRENDRA F PANCHAL

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA10211/180522 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)3 Oct 2024
Engineer's certificate annexure3 Oct 2024
RERA registration certificate18 May 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

75%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHIVALAY BLISS PHASE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmSHIVALAY BLISS PHASE-2Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 152 registered projects within 2 km.

Builder: SHIV SHAKTI REALITY

SHIV SHAKTI REALITY has 2 registrations on GujRERA, including SHIVALAY GREEN and SHIVALAY BLISS PHASE-2. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHIVALAY BLISS PHASE-2 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVALAY BLISS PHASE-2?

The registered promoter entity is SHIV SHAKTI REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVALAY BLISS PHASE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVALAY BLISS PHASE-2?

The professionals named in the filing: Architect: ABHILASH KETANKUMAR PANDYA; Engineer: VIRENDRA F PANCHAL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVALAY BLISS PHASE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVALAY BLISS PHASE-2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVALAY BLISS PHASE-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.