Home / Browse projects / Vadodara, Gujarat / SEVEN9 IMPERIA

Valid until 1 Nov 2027 Mixed Development project

SEVEN9 IMPERIA

By VANSH DEVELOPERS

RG-GJ-13467 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA07490/EX1/280825/010726 · Last updated on GujRERA portal: 16 Aug 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Nov 2027Possession promisedmoved 28 months from the original
24 of 27Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 50%
66 of 158Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SEVEN9 IMPERIA is a Mixed Development project by VANSH DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA07490/EX1/280825/010726 on 23 Sep 2020. Possession is promised by 1 Nov 2027. The completion date has moved by 28 months from the original filing. 92 of the 158 units on this registration are recorded sold or booked, and 24 of 27 construction stages are filed complete.

At a glance

Project

  • NameSEVEN9 IMPERIA
  • TypeMixed Development
  • Location
    • SEVEN9 IMPERIA
    • OPP. DARSHANAM 99
    • BH. LILLERIA PARTY PLOT
    • SAMA SAVLI
    • Sama
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA07490/EX1/280825/010726
  • ReraGenie IDRG-GJ-13467

Builder

  • NameVANSH DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2020First promiseJul 2025Revised toNov 2027

Key facts

Registration and timeline

  • StatusValid until 1 Nov 2027
  • Registered on23 Sep 2020
  • Promised completion1 Nov 2027
  • Revised completionRevised to 1 Nov 2027 (originally 1 Jul 2025)
  • Buildings3 building records
  • Documents filed41 files

Current status

58%92 of 158 units booked
121.8%Of the estimated cost spent so far

Figures as on 16 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---46652
B---46854
C---46652

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 16 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 50%.

A94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 16 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,249 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 13.00 cr
Cost incurredRs 15.84 cr
Spent of the estimate121.82%
BuildingWingEstimatedIncurred
BNARs 5.54 crRs 6.68 cr
ANARs 3.73 crRs 4.58 cr
CNARs 3.73 crRs 4.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTALIB F.E
EngineerHITESH H VORA

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA07490/EX1/280825/010726Applied Jul 2025; approved Aug 2025
ExtensionApplied Jun 2026; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA07490/EX1/280825/010726 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)16 Aug 2025
Engineer's certificate (Form 2)31 Jul 2025
Engineer's certificate annexure31 Jul 2025
Architect's certificate (Form 1)10 Jul 2025
Site photograph, A10 Jul 2025
Site photograph, B10 Jul 2025
Site photograph, C10 Jul 2025
RERA registration certificate23 Sep 2020
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

58%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 28 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SEVEN9 IMPERIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sama2,900+ in Vadodara

2 kmSEVEN9 IMPERIAOther 187Dot size: filed unitsN

Filed coordinates, straight-line distance. 187 registered projects within 2 km.

Builder: VANSH DEVELOPERS

VANSH DEVELOPERS has 1 registration on GujRERA, including SEVEN9 IMPERIA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SEVEN9 IMPERIA is delayed beyond 1 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SEVEN9 IMPERIA?

The registered promoter entity is VANSH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SEVEN9 IMPERIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SEVEN9 IMPERIA?

The professionals named in the filing: Architect: TALIB F.E; Engineer: HITESH H VORA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SEVEN9 IMPERIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SEVEN9 IMPERIA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SEVEN9 IMPERIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.