SAMRUDDHI PRARAMBH PHASE - II

By PRANAV BUILDTECH

RG-GJ-73617 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA12428/121023 · Last updated on GujRERA portal: 24 Dec 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
2 of 9Construction stages donefurthest along: Stilt Floor, 0%
43 of 99Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SAMRUDDHI PRARAMBH PHASE - II is a Mixed Development project by PRANAV BUILDTECH in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA12428/121023 on 12 Oct 2023. Possession is promised by 30 Apr 2029. 56 of the 99 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.

At a glance

Project

  • NameSAMRUDDHI PRARAMBH PHASE - II
  • TypeMixed Development
  • Location
    • OPP GAYATRI MANDIR NR AKSHAR GURUKUL HOSTEL
    • KHATAMBA WAGHODIYA ROAD
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA12428/121023
  • ReraGenie IDRG-GJ-73617

Builder

  • NamePRANAV BUILDTECH
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2023PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on12 Oct 2023
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

57%56 of 99 units booked
18.6%Of the estimated cost spent so far

Figures as on 24 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING TOWER 1---811899

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 24 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

BUILDING TOWER 1: 22% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 24 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,441 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 12.42 cr
Cost incurredRs 2.31 cr
Spent of the estimate18.6%
BuildingWingEstimatedIncurred
BUILDING TOWER 1NARs 12.42 crRs 2.31 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR KIRAN PATEL
EngineerCHIRAG A SHAH

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA12428/121023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)24 Dec 2025
Engineer's certificate annexure24 Dec 2025
Accountant's certificate (Form 3)24 Dec 2025
Architect's certificate (Form 1)23 Dec 2025
Site photograph, BUILDING TOWER 123 Dec 2025
RERA registration certificate12 Oct 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

57%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SAMRUDDHI PRARAMBH PHASE - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmSAMRUDDHI PRARAMBH PHASEOther 64Dot size: filed unitsN

Filed coordinates, straight-line distance. 64 registered projects within 2 km.

Builder: PRANAV BUILDTECH

PRANAV BUILDTECH has 2 registrations on GujRERA, including SAMRUDDHI PRARAMBH PHASE - I and SAMRUDDHI PRARAMBH PHASE - II. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SAMRUDDHI PRARAMBH PHASE - II is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAMRUDDHI PRARAMBH PHASE - II?

The registered promoter entity is PRANAV BUILDTECH, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAMRUDDHI PRARAMBH PHASE - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAMRUDDHI PRARAMBH PHASE - II?

The professionals named in the filing: Architect: AR KIRAN PATEL; Engineer: CHIRAG A SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMRUDDHI PRARAMBH PHASE - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMRUDDHI PRARAMBH PHASE - II. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMRUDDHI PRARAMBH PHASE - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.