ReraGenieLog inGet a buyer report

Home / Browse projects / Dharwad, Karnataka / SAI NANDAN APARTMENT

Registration approved No litigation declared Residential/Group Housing project

SAI NANDAN APARTMENT

By VANISHREE BUILDERS

RG-KA-10798 · RERA PRM/KA/RERA/1259/410/PR/030525/007708 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2028Possession promisedno revision filed
9 of 16Construction stages donefurthest along: Dadoing, 90%
5 of 12Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 73 documents Report an error

SAI NANDAN APARTMENT is a Residential/Group Housing project by VANISHREE BUILDERS in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/030525/007708 on 3 May 2025. Possession is promised by 30 Jun 2028. 7 of the 12 units on this registration are recorded sold or booked, and 9 of 16 construction stages are filed complete.

At a glance

Project

  • NameSAI NANDAN APARTMENT
  • TypeResidential/Group Housing
  • Location
    • Dharwad
    • 580007
  • Pincode580007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1259/410/PR/030525/007708
  • ReraGenie IDRG-KA-10798

Builder

  • NameVANISHREE BUILDERS
  • Entity typePartnership Firm
  • GSTIN29AALFV7166P1Z0
  • Authorized SignatoryCHANDRAKANT MEGHARAJ
  • Other registrations18 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredMay 2025PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on3 May 2025
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed73 files

Current status

58%7 of 12 units booked
68.8%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI NANDAN---12012

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 16 construction stages are filed complete. The stage furthest along is Dadoing, at 90%.

Building: 75% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing50%
Painting80%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes85%
LiftsYes35%
Corridor/LobbiesYes65%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes50%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area455 sq m
Named landowners2
LandownerVillageDistrict
Prabhugouda--
Mahadevagouda--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.65 cr
Cost incurredRs 3.20 cr
Spent of the estimate68.84%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.11 crRs 3.20 cr
Payment of taxesRs 37.00 lakh-
Administrative CostsRs 12.00 lakh-
On-site expenditure-Consultants FeesRs 5.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARUN PATTAR
EngineerNikhil Katwe
Chartered AccountantPooja Katigar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed73

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/030525/007708 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4 Chatrered Account.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) (4).pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 enginer.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 SAI NANDAN.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM - 6 ENGINEER CERTIFICATE.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Sai Nandan Apartment- Q4 FY2025-26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) (23).pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer Certificate.pdf14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Nandan Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Nandan Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Nandan Q3 25-26.pdf15 Jan 2026
Registration CertificateFile: REGISTRATION CERTIFICATE.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: Partnership Deed and Supplementary Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 CA Certificate Sai Nandan.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Cert Sai Nandan.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer cert Sai Nandan.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit - Non Litigation.pdf-
Balance Sheet 2023 - 2024File: Balance Sheet 2023-24.pdf-
Balance Sheet 2022 - 2023File: Balance sheet 23.pdf-
Balance Sheet 2021 - 2022File: Balance Shhet 22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Profit and Loss statement 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss 23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss 22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: IT Return Acknowledgment and Statement.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: IT Returns 202223.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 22.pdf-
Approval letter - HDMC-
Approved Plan - HDMC-
Approved Plan - HDMC-
Stability certificate sai nandan-
Project Specification of Sai Nandan-
SAI NANDAN AGREEMENT FOR SALE-
Sai Nandan Proforma Allotment Letter-
Affidavit Form B-
Affidavit - Sec 3(1)-
Affidavit Cum Declaration - JD-
Legal Report-
HESCOM NOC with fees Receipt - SAI NANDAN-
Water NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Extract Patil 21-12-2023-
Gift Deed-
GPA SAI NANDAN-
Mother Deed-
Mutation Patil 21-12-2023-
CDP SAI NANDAN-
ESTIMATION SAI NANDAN-
Common and Amenities Area Details sai nandan-
Land cost calculation sai nandan-
STP Sai Nandan-
AREA STATEMENT SAI NANDAN-

How this compares with Dharwad

58%of this project is bookeddistrict median 38%
29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SAI NANDAN APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

2 kmSAI NANDAN APARTMENTOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: VANISHREE BUILDERS

VANISHREE BUILDERS has 19 registrations on RERA Karnataka, including SAI GOPAL APARTMENT and SAI NANDAN APARTMENT. Its filings declare 5 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SAI NANDAN APARTMENT is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAI NANDAN APARTMENT?

The registered promoter entity is VANISHREE BUILDERS, a partnership firm as per the filing. Its GSTIN 29AALFV7166P1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAI NANDAN APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAI NANDAN APARTMENT?

The professionals named in the filing: Architect: ARUN PATTAR; Engineer: Nikhil Katwe; Chartered Accountant: Pooja Katigar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI NANDAN APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI NANDAN APARTMENT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI NANDAN APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.