Home / Browse projects / Bengaluru Urban, Karnataka / SAHASRA SERENITY
SAHASRA SERENITY
RG-KA-71164 · RERA PRM/KA/RERA/1251/446/PR/041122/005407 · Last updated on RERA Karnataka portal: 21 Jan 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
SAHASRA SERENITY is a Residential/Group Housing project by SAHASRA BUILDERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/041122/005407 on 4 Nov 2022. Possession is promised by 31 Mar 2026. The completion date has moved by 12 months from the original filing. 98 of the 125 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.
At a glance
Project
- NameSAHASRA SERENITY
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560067
- Pincode560067
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/041122/005407
- ReraGenie IDRG-KA-71164
Builder
- NameSAHASRA BUILDERS
- Entity typePartnership Firm
- GSTIN29ADLFS3872L1Z8
- Authorized SignatoryYOGESH T
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 Nov 2022
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2025)
- Buildings1 building record
- Documents filed98 files
Current status
Figures as on 21 Jan 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sahasra Serenity | - | - | - | 125 | 0 | 125 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 21 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 17 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities40
As on 21 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 100% |
| Community Hall | Yes | 100% |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 100% |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 100% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Krishna Reddy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 33.56 cr | Rs 31.48 cr |
| Interest on borrowings (estimated interest on bank loan) | Rs 2.40 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 36.00 lakh | - |
| On-site expenditure-Consultants Fees | Rs 15.00 lakh | Rs 3.37 cr |
| Payment of taxes | Rs 15.00 lakh | Rs 5.33 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | G BHANUMATHY |
| Engineer | SRINIVAS RAO BOLIMUNTA |
| Chartered Accountant | K SIVAGURU PRASADA RAO |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAwaiting OC
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed98
As listed on the registration, under the names the promoter filed them with; the newest 80 of 98 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/041122/005407 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 _31-12-2025_sign.pdf | 21 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate form 5 Q3.pdf | 21 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificateForm 6 Q3.pdf | 21 Jan 2026 |
| engineer certificate work completedFile: engineer certificate work completed.pdf | 19 Jun 2025 |
| engineer certificate for pending workFile: engineer certificate for pending work.pdf | 19 Jun 2025 |
| RTC, survey 39/2 | - |
| Mutation, survey 39/2 | - |
| Encumbrance Certificate, survey 39/2 | - |
| Conversion/Alienation Order, survey 39/2 | - |
| Sale/Title/Gift Deed, survey 39/2 | - |
| JDA, survey 39/2 | - |
| Khatha, survey 39/2 | - |
| Registration CertificateFile: Registration Certificate m.pdf | - |
| Partnership DeedFile: Partnership Deed mc.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1 CA certificate.pdf | - |
| Certificate issued by Architect Form 2File: Form 3 Engineer Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form 2 Achitect Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: NON LITIGATION Affidavit.pdf | - |
| Certificate from Chartered AccountFile: Form 1 CA certificate.pdf | - |
| Balance Sheet 2021 - 2022File: Balance sheet 21-22.pdf | - |
| Balance Sheet 2020 - 2021File: Balance sheet 20-21.pdf | - |
| Balance Sheet 2019 - 2020File: Balance sheet 19-20.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss 21-22.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss 20-21.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Profit and Loss 19-20.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR-V Ack 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR-V Ack 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR-V Ack.pdf | - |
| BBMP_LICENCE COPY | - |
| NOC BESCOM with Fee receipt | - |
| NOC BWSSB with receipt | - |
| BBMP SANCTION PLAN SERENITY | - |
| BBMP SANCTION PLAN SERENITY | - |
| BBMP SANCTION PLAN SERENITY | - |
| Project SPECIFICATIONS | - |
| BBMP SANCTION PLAN SERENITY | - |
| BBMP SANCTION PLAN SERENITY | - |
| Structural Stability | - |
| Advocate Search report | - |
| JDA and GPA c | - |
| CDP MASTER EXTRACT | - |
| Title Deed 1970 | - |
| Proforma Agreement Of Sale | - |
| Allotment Letter | - |
| FORM B Affidavit | - |
| NON-VIOLATION Affidavit 2 | - |
| JDA Affidavit 2 | - |
| NOC BESCOM with Fee receipt | - |
| NOC BWSSB with receipt | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| NOC KSPCB with Fee receipt | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| SERENITY GUIDENCE VALUE | - |
| SHARING AGREMENT SERENITY | - |
| SAHASRA GST Certificate | - |
| Registration Certificate - Changed address | - |
| Village Map | - |
| Title Deed 1970 | - |
| GOOGLE MAPS DEMARCATION SERENITY | - |
| STP Design sahasra serenity n | - |
| Clarification on Sold and unsold Units | - |
| BWSSB NOC with Fee receipt | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SAHASRA SERENITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 38 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
DS MAX SKY FIELDS
DS Max Properties Private Limited
Sowparnika Rhythm of Rain
SOWPARNIKA HOMES PRIVATE LIMITED
WORLD OF GARDENS
RLP TRENDSQUARES PROJECTS PRIVATE LIMITED
DS MAX SKYSAMPURN
DS MAX PROPERTIES PRIVATE LIMITED
Amrutha Lake Vista
Amrutha Shelters Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SAHASRA BUILDERS
SAHASRA BUILDERS has 1 registration on RERA Karnataka, including SAHASRA SERENITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SAHASRA SERENITY is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SAHASRA SERENITY?
The registered promoter entity is SAHASRA BUILDERS, a partnership firm as per the filing. Its GSTIN 29ADLFS3872L1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SAHASRA SERENITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAHASRA SERENITY?
The professionals named in the filing: Architect: G BHANUMATHY; Engineer: SRINIVAS RAO BOLIMUNTA; Chartered Accountant: K SIVAGURU PRASADA RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAHASRA SERENITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.