Home / Browse projects / Vadodara, Gujarat / ROYAL VILLA

Valid until 30 Jun 2023 Residential/Group Housing project

ROYAL VILLA

By ROYAL BUILDERS

RG-GJ-51483 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02729/EX2/060123 · Last updated on GujRERA portal: 9 Jan 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2023Possession promisedmoved 24 months from the original
7 of 9Construction stages donefurthest along: Stilt Floor, 0%
0 of 43Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

ROYAL VILLA is a Residential/Group Housing project by ROYAL BUILDERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02729/EX2/060123 on 28 May 2018. Possession is promised by 30 Jun 2023. The completion date has moved by 24 months from the original filing. 43 of the 43 units on this registration are recorded sold or booked, and 7 of 9 construction stages are filed complete.

At a glance

Project

  • NameROYAL VILLA
  • TypeResidential/Group Housing
  • Location
    • NR. RAJPUT SAMAJ WADI
    • OPP. VOLTAMP TRANSFOMAR
    • MANEJA-JAMBUVA ROAD
    • Jambuva
    • Vadodara
    • 390013
  • Pincode390013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02729/EX2/060123
  • ReraGenie IDRG-GJ-51483

Builder

  • NameROYAL BUILDERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2018First promiseJun 2021Revised toJun 2023

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2023
  • Registered on28 May 2018
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed38 files

Current status

100%43 of 43 units booked
95.0%Of the estimated cost spent so far

Figures as on 9 Jan 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DUPLEX---43043

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 9 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

DUPLEX: 78% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 9 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,961 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.00 cr
Cost incurredRs 6.65 cr
Spent of the estimate94.97%
BuildingWingEstimatedIncurred
DUPLEXNARs 7.00 crRs 6.65 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHOKBHAI G PATEL
EngineerVINUBHAI PATEL

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA02729/EX1/300721Applied Jun 2021; approved Jul 2021
PR/GJ/VADODARA/VADODARA/Others/RAA02729/EX2/060123Applied Jan 2023; approved Jan 2023

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02729/EX2/060123 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)9 Jan 2025
Engineer's certificate (Form 2)6 Jan 2025
Engineer's certificate annexure6 Jan 2025
Architect's certificate (Form 1)30 Dec 2024
Site photograph, DUPLEX29 Dec 2024
RERA registration certificate28 May 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

100%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 24 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep ROYAL VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Jambuva2,900+ in Vadodara

2 kmROYAL VILLAOther 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 74 registered projects within 2 km.

Builder: ROYAL BUILDERS

ROYAL BUILDERS has 1 registration on GujRERA, including ROYAL VILLA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if ROYAL VILLA is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ROYAL VILLA?

The registered promoter entity is ROYAL BUILDERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ROYAL VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ROYAL VILLA?

The professionals named in the filing: Architect: ASHOKBHAI G PATEL; Engineer: VINUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.