ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / RADIANCE GARDENIA

Registration approved No litigation declared Residential/Group Housing project

RADIANCE GARDENIA

By RADIANCE REALTY DEVELOPERS INDIA LIMETED

RG-KA-99523 · RERA PRM/KA/RERA/1251/446/PR/091122/005430 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
17 of 17Construction stages doneevery applicable stage filed complete
0 of 294Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 143 documents Report an error

RADIANCE GARDENIA is a Residential/Group Housing project by RADIANCE REALTY DEVELOPERS INDIA LIMETED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/091122/005430 on 9 Nov 2022. Possession is promised by 31 Dec 2027. 294 of the 294 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRADIANCE GARDENIA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560077
  • Pincode560077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/091122/005430
  • ReraGenie IDRG-KA-99523

Builder

  • NameRADIANCE REALTY DEVELOPERS INDIA LIMETED
  • Entity typeCompany
  • CINU45201TN2007PLC062662
  • GSTIN29AACCN5152H1ZE
  • Authorized SignatoryR VINAYAGAMURTHY
  • Managing DirectorVARUN MANIAN
  • DirectorsMARIA RENAUX, G PANCHAPAGESAN, VARUN MANIAN, CHANDRASEKARAN MURULIDHARAN
  • Project HeadR VINAYAGAMURTHY
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Nov 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings6 building records
  • Documents filed143 files

Current status

100%294 of 294 units booked
0.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---63063
BLOCK B---24024
BLOCK C---32032
BLOCK D---60060
BLOCK E---45045
BLOCK F---70070

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area47,044 sq m
Named landowners5
LandownerVillageDistrict
RADIANCE REALTY DEVELOPERS INDIA LIMITED--
RADIANCE REALTY DEVELOPERS INDIA LIMITED--
RADIANCE REALTY DEVELOPERS INDIA LIMITED--
RADIANCE REALTY DEVELOPERS INDIA LIMITED--
RADIANCE REALTY DEVELOPERS INDIA LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 196.19 cr
Cost incurredRs 1.59 cr
Spent of the estimate0.81%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 155.41 crRs 1.59 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 15.80 cr-
On-site expenditure-Site OverheadRs 14.09 cr-
On-site expenditure-Salaries of workersRs 7.10 cr-
On-site expenditure-Consultants FeesRs 2.77 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.02 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKembhavi Architecture Foundation
EngineerBURO Engineers (I) Private Limited
Chartered AccountantS.NARASIMAN & Co

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00182/2026-RADIANCE REALTY DEVELOPERS INDIA LIMETED26/02/2026

Documents filed143

As listed on the registration, under the names the promoter filed them with; the newest 80 of 143 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/091122/005430 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Sep 26.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Sep 26.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Sep 26.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Horticulture department15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU June 26.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU June 26.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU June 26.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Horticulture department14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU March 26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU March 26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU March 26.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Horticulture department15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Horticulture department13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
RTC, survey 48/1-
Mutation, survey 48/1-
Encumbrance Certificate, survey 48/1-
Conversion/Alienation Order, survey 48/1-
Sale/Title/Gift Deed, survey 48/1-
Khatha, survey 48/1-
RTC, survey 48/2-
Mutation, survey 48/2-
Encumbrance Certificate, survey 48/2-
Conversion/Alienation Order, survey 48/2-
Sale/Title/Gift Deed, survey 48/2-
Khatha, survey 48/2-
RTC, survey 49/1-
Mutation, survey 49/1-
Encumbrance Certificate, survey 49/1-
Conversion/Alienation Order, survey 49/1-
Sale/Title/Gift Deed, survey 49/1-
Khatha, survey 49/1-
RTC, survey 49/2-
Mutation, survey 49/2-
Encumbrance Certificate, survey 49/2-
Conversion/Alienation Order, survey 49/2-
Sale/Title/Gift Deed, survey 49/2-
Khatha, survey 49/2-
RTC, survey 50/2-
Mutation, survey 50/2-
Encumbrance Certificate, survey 50/2-
Conversion/Alienation Order, survey 50/2-
Sale/Title/Gift Deed, survey 50/2-
Khatha, survey 50/2-
Registration CertificateFile: CIN Certificate.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Form 1 CA Certi.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect certi.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer Certi.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation.pdf-
Certificate from Chartered AccountFile: Form 1 CA Certi.pdf-
Balance Sheet 2021 - 2022File: BS.pdf-
Balance Sheet 2020 - 2021File: BS.pdf-
Balance Sheet 2019 - 2020File: BS.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
RADIANCE BLOSSOM PHASE- IIRadiance Realty Developers India Limited, 167/1A,167/1B,167/1C & 128/P10, , Village Mandur,Taluka Bangalore East, , Village Mandur,Taluka Bangalore East , HOSKOTE , Bengaluru Rural, Karnataka - 560049OngoingDec 2024Not delivered
RADIANCE BLOSSOMSY NO’S. 167/2,168/1A, 168/1B, 168/1C, 168/2. MANDUR VILLAGE, BIDARAHALLI HOBLI, BANGALORE EAST TALUKCompleted-No date filed

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep RADIANCE GARDENIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmRADIANCE GARDENIAOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: RADIANCE REALTY DEVELOPERS INDIA LIMETED

RADIANCE REALTY DEVELOPERS INDIA LIMETED has 1 registration on RERA Karnataka, including RADIANCE GARDENIA. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if RADIANCE GARDENIA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of RADIANCE GARDENIA?

The registered promoter entity is RADIANCE REALTY DEVELOPERS INDIA LIMETED, a company as per the filing. Its CIN U45201TN2007PLC062662 and GSTIN 29AACCN5152H1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in RADIANCE GARDENIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RADIANCE GARDENIA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at RADIANCE GARDENIA?

The professionals named in the filing: Architect: Kembhavi Architecture Foundation; Engineer: BURO Engineers (I) Private Limited; Chartered Accountant: S.NARASIMAN & Co. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADIANCE GARDENIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADIANCE GARDENIA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADIANCE GARDENIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.