ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / PRATHNA

Valid until 31 Jan 2027 Mixed Development project

PRATHNA

By SAKAR HOMES PRIVATE LIMITED

RG-GJ-46339 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA09031/EX1/240326/310127 · Last updated on GujRERA portal: 5 Feb 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jan 2027Possession promisedmoved 12 months from the original
9 of 27Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 83%
84 of 118Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

PRATHNA is a Mixed Development project by SAKAR HOMES PRIVATE LIMITED in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA09031/EX1/240326/310127 on 9 Sep 2021. Possession is promised by 31 Jan 2027. The completion date has moved by 12 months from the original filing. 34 of the 118 units on this registration are recorded sold or booked, and 9 of 27 construction stages are filed complete.

At a glance

Project

  • NamePRATHNA
  • TypeMixed Development
  • Location
    • PRATHNA
    • R.S.NO.179
    • TP.NO.36
    • FP.NO.131
    • JAMBWA
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA09031/EX1/240326/310127
  • ReraGenie IDRG-GJ-46339

Builder

  • NameSAKAR HOMES PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredSep 2021First promiseJan 2026Revised toJan 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jan 2027
  • Registered on9 Sep 2021
  • Promised completion31 Jan 2027
  • Revised completionRevised to 31 Jan 2027 (originally 31 Jan 2026)
  • Buildings3 building records
  • Documents filed44 files

Current status

29%34 of 118 units booked
30.3%Of the estimated cost spent so far

Figures as on 5 Feb 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A---383068
TOWER B---161026
TOWER C---16824

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 5 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 83%.

TOWER A39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats5%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TOWER B47%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure83%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TOWER C56%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor5%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 5 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,829 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.82 cr
Cost incurredRs 2.07 cr
Spent of the estimate30.31%
BuildingWingEstimatedIncurred
TOWER ANARs 3.79 crRs 66.86 lakh
TOWER CNARs 1.52 crRs 90.00 lakh
TOWER BNARs 1.52 crRs 50.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRTI SHETH
EngineerVINUBHAI PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA09031/EX1/240326/310127Applied Jan 2026; approved Mar 2026

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA09031/EX1/240326/310127 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)5 Feb 2026
Architect's certificate (Form 1)4 Feb 2026
Engineer's certificate (Form 2)4 Feb 2026
Engineer's certificate annexure4 Feb 2026
Site photograph, TOWER A4 Feb 2026
Site photograph, TOWER B4 Feb 2026
Site photograph, TOWER C4 Feb 2026
RERA registration certificate9 Sep 2021
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

29%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep PRATHNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmPRATHNAOther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: SAKAR HOMES PRIVATE LIMITED

SAKAR HOMES PRIVATE LIMITED has 1 registration on GujRERA, including PRATHNA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if PRATHNA is delayed beyond 31 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PRATHNA?

The registered promoter entity is SAKAR HOMES PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PRATHNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRATHNA?

The professionals named in the filing: Architect: KIRTI SHETH; Engineer: VINUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRATHNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRATHNA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRATHNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.