ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / Pratham Bluets Phase 9

Valid until 31 Dec 2026 Residential/Group Housing project

Pratham Bluets Phase 9

By PRATHAM PROPERTIES

RG-GJ-70965 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA12335/EX1/240326/311226 · Last updated on GujRERA portal: 3 Jan 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 12 months from the original
1 of 9Construction stages donefurthest along: Plinth, 90%
32 of 44Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

Pratham Bluets Phase 9 is a Residential/Group Housing project by PRATHAM PROPERTIES in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA12335/EX1/240326/311226 on 29 Sep 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 12 of the 44 units on this registration are recorded sold or booked, and 1 of 9 construction stages are filed complete.

At a glance

Project

  • NamePratham Bluets Phase 9
  • TypeResidential/Group Housing
  • Location
    • Pratham Bluets
    • Road next to Zydex
    • Opp Shaishav School
    • Off Gotri-Sevasi Road
    • New Alkapuri
    • Vadodara
    • Gujarat
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA12335/EX1/240326/311226
  • ReraGenie IDRG-GJ-70965

Builder

  • NamePRATHAM PROPERTIES
  • Entity typePARTNERSHIP FIRM
  • Other registrations9 more →

Key dates

this monthRegisteredSep 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on29 Sep 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed42 files

Current status

27%12 of 44 units booked
43.3%Of the estimated cost spent so far

Figures as on 3 Jan 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower R---44044

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 3 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 90%.

Tower R: 30% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth90%
Stilt Floor0%
Slabs of Super Structure61%
Internal walls, internal plaster, floorings, doors and windows within flats12%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 3 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes80%
Landscaping and tree plantingYes90%
Street lightingYes80%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes20%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes80%
Drinking water facilitiesYes40%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area40,314 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.20 cr
Cost incurredRs 3.11 cr
Spent of the estimate43.27%
BuildingWingEstimatedIncurred
Tower RNARs 7.20 crRs 3.11 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMehul Patel
EngineerSACPL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA12335/EX1/240326/311226Applied Nov 2025; approved Mar 2026

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA12335/EX1/240326/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)3 Jan 2026
Architect's certificate (Form 1)23 Dec 2025
Engineer's certificate (Form 2)23 Dec 2025
Engineer's certificate annexure23 Dec 2025
Site photograph, Tower R23 Dec 2025
RERA registration certificate29 Sep 2023
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

27%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Pratham Bluets Phase 9 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmPratham Bluets Phase 9Other 157Dot size: filed unitsN

Filed coordinates, straight-line distance. 157 registered projects within 2 km.

Builder: PRATHAM PROPERTIES

PRATHAM PROPERTIES has 10 registrations on GujRERA, including Pratham Bluets Phase-4 and Pratham Ivy. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Pratham Bluets Phase 9 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Pratham Bluets Phase 9?

The registered promoter entity is PRATHAM PROPERTIES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Pratham Bluets Phase 9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Pratham Bluets Phase 9?

The professionals named in the filing: Architect: Mehul Patel; Engineer: SACPL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pratham Bluets Phase 9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pratham Bluets Phase 9. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pratham Bluets Phase 9 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.