Home / Browse projects / Bengaluru Urban, Karnataka / PLATINUM EAST WOODS
PLATINUM EAST WOODS
RG-KA-26441 · RERA PRM/KA/RERA/1251/446/PR/100423/005855 · Last updated on RERA Karnataka portal: 31 Mar 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
PLATINUM EAST WOODS is a Residential/Group Housing project by PLATINUM - NARYA INFRA in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/100423/005855 on 10 Apr 2023. Possession is promised by 30 Mar 2027. 88 of the 188 units on this registration are recorded sold or booked, and 4 of 19 construction stages are filed complete.
At a glance
Project
- NamePLATINUM EAST WOODS
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560067
- Pincode560067
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/100423/005855
- ReraGenie IDRG-KA-26441
Builder
- NamePLATINUM - NARYA INFRA
- Entity typePartnership Firm
- Authorized SignatoryS Yugandhar
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Apr 2023
- Promised completion30 Mar 2027
- Revised completionNone
- Buildings1 building record
- Documents filed136 files
Current status
Figures as on 31 Mar 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 188 | 0 | 188 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 19 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 60%.
Building: 37% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 60% |
| Masonry Construction | 60% |
| Plastering inside , outside & Ceiling | 60% |
| Joinery: Doors, Windows, Ventilators etc | 60% |
| Basic work of Water supply, Sanitary and Electrification | 60% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 0% |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 50% |
| Sewage and Drainage System | Yes | 50% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 50% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Solid waste management and disposal | Yes | 50% |
| Emergency Evacuation services | Yes | 50% |
| Internal Roads & Footpaths | Yes | 50% |
| Electricity supply transformer and substation | Yes | 50% |
| Storm water drains | Yes | 50% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 50% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 50% |
| Club House | No | Not applicable |
| Community Hall | Yes | 50% |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 50% |
| Swimming Pool | Yes | 50% |
| Gym | Yes | 50% |
| Parks | No | Not applicable |
| Power Backup | Yes | 50% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 50% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 50% |
| Lifts | Yes | 50% |
| Corridor/Lobbies | Yes | 50% |
| Fire escapes | Yes | 50% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 50% |
| Basement | Yes | 50% |
| Terrace | Yes | 50% |
| Outer Wall | Yes | 50% |
| Open parking areas | Yes | 50% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 50% |
| Common storage spaces | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| S Chandra Prakash | - | - |
| Yugandhar S | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 95.09 cr | Rs 9.49 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 9.30 cr | Rs 86.32 lakh |
| Payment of taxes | Rs 6.75 cr | Rs 71.82 lakh |
| On-site expenditure-Consultants Fees | Rs 1.00 cr | Rs 50.74 lakh |
| On-site expenditure-Salaries of workers | Rs 80.00 lakh | Rs 9.99 lakh |
| On-site expenditure-Site Overhead | Rs 10.00 lakh | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 10.00 lakh | Rs 57.04 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANI SAMBYAL |
| Engineer | MANOHAR.N |
| Chartered Accountant | A Subramanyam Reddy |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed136
As listed on the registration, under the names the promoter filed them with; the newest 80 of 136 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/100423/005855 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: 12) PLATINUM EAST WOODS - Form -4, Chartered Accountant (QU) - Oct 2025 to Dec 2025.pdf | 31 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: 12) PLATINUM EAST WOODS - Form-5, Architect (QU) - Oct 2025 - Dec 2025.pdf | 31 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: 12) PLATINUM EAST WOODS- Form -6, Engineer (QU) - Oct 2025 to Dec 2025.pdf | 31 Mar 2026 |
| Q3 2025-26 Water supply and sewage board | 31 Mar 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 31 Mar 2026 |
| Q3 2025-26 KPTCL- BESCOM | 31 Mar 2026 |
| Q3 2025-26 Fire and Safety | 31 Mar 2026 |
| Q3 2025-26 Airport Authority of India | 31 Mar 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 31 Mar 2026 |
| PLATINUM CITY DEVELOPERS - Fully Completed and occupied - Nov-2015File: OC Scan Copy.pdf | 1 Apr 2023 |
| Sai Properties -PRM/KA/RERA/1251/310/PR/181022/002088 - 100% Completed and fully occupiedFile: OCCUPANCY CERTIFICATE - SAI PROPERTIES (4).pdf | 1 Apr 2023 |
| Sai Properties- PRM/KA/RERA/1251/310/PR/220922/005260 - 65% completed - under constructionFile: CC_BBMP_Platinum Greenfields.pdf | 1 Apr 2023 |
| Elegant Altima - PRM/KA/RERA/1251/310/PR/190724/002717- 90% Completed / OC attachedFile: OC Elegant Altima.pdf | 1 Apr 2023 |
| PRAMOTERS FINANCIAL DOCUMENTSFile: ITR &BS - SCP - 21-22.pdf | 24 Mar 2023 |
| PRAMOTERS FINANCIAL DOCUMENTSFile: FY 21-22 Yugendhar ITR & Computation.pdf | 24 Mar 2023 |
| sources of fund- Loan Term Sheet & Partner ITRFile: Source of Funds, Loan Letter and ITR.pdf | 8 Mar 2023 |
| P&L and BS -2021-22 along with SCHEDULES , Not Required UDIN due to Non Tax Audit - no turonverFile: All Platinm Narya Balance sheet 2022 with Schedules.pdf | 8 Mar 2023 |
| profit and loss account and balance sheet, 2020-21File: All Platinm Narya Balance sheet 2021 with Schedules.pdf | 22 Feb 2023 |
| profit and loss account and balance sheet, 2021-22File: All Platinm Narya Balance sheet 2022 with Schedules.pdf | 22 Feb 2023 |
| Source of FundsFile: Source of Funds.pdf | 22 Feb 2023 |
| partnership deedFile: PARTNERSHIP DEED PLATINUM NARYA INFRA.pdf | 22 Feb 2023 |
| Certified copy Sub-registrar regarding value of the property- guidance valueFile: Guidance Valuation.pdf | 22 Feb 2023 |
| Amendment partnership DeedFile: Platinum narya infra amendment partnership Deed.pdf | 22 Feb 2023 |
| Single plot layout -Since the area of the plot under 5 acres, development plan is not mandatoryFile: Single Plot Layout.pdf | 22 Feb 2023 |
| Single plot layout order-Since the area of the plot under 5 acres, development plan is not mandatoryFile: Single Plot Layout.pdf | 22 Feb 2023 |
| certified Carpet areaFile: Carpet Area.pdf | 22 Feb 2023 |
| Certified Carpet AreaFile: Platinum East Woods - Carpet Area detail-2.pdf | 22 Feb 2023 |
| Relinquishment deed not yet done once it’s done as per the rules will upload in the later stageFile: Relinquishment Deed.pdf | 22 Feb 2023 |
| KSPCB NOC_ADDENDUMFile: KSPCB_ADDENDUM.pdf | 22 Feb 2023 |
| SEIAA_corrigendumFile: SEIAA_corrigendum 188 units.pdf | 22 Feb 2023 |
| Common Area Allotted To AssociationFile: Common Area Alloted Letter.pdf | 22 Feb 2023 |
| Estimated cost of constructionFile: PLATINUM EAST WOODS - ESTIMATE.pdf | 22 Feb 2023 |
| STRUCTURAL STABILITY CERTIFICATEFile: STRUCTURAL STABILITY CERTIFICATE.pdf | 22 Feb 2023 |
| Allotment letterFile: profoma of allotments letter.pdf | 22 Feb 2023 |
| Profoma of Sale AggrementFile: Profoma of Sale Aggrement.pdf | 22 Feb 2023 |
| Building LicenseFile: Building License.pdf | 22 Feb 2023 |
| RTC, survey 191 | - |
| Mutation, survey 191 | - |
| Encumbrance Certificate, survey 191 | - |
| Conversion/Alienation Order, survey 191 | - |
| Sale/Title/Gift Deed, survey 191 | - |
| Khatha, survey 191 | - |
| Registration CertificateFile: Form C PLATINUM NARYA INFRA.pdf | - |
| Partnership DeedFile: PARTNERSHIP DEED PLATINUM NARYA INFRA.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1.pdf | - |
| Certificate issued by Architect Form 2File: PLATINUM EAST WOODS -Form -2, Architect-1.pdf | - |
| Certificate issued by Engineer Form 3File: PLATINUM EAST WOODS -Form -3,Engineer-1.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit Non-Litigation.pdf | - |
| Certificate from Chartered AccountFile: Form 1.pdf | - |
| Balance Sheet 2021 - 2022File: BS_21-22.pdf | - |
| Balance Sheet 2020 - 2021File: BS_20-21.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: P&L_21-22.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: P&L_20-21.pdf | - |
| Director's Report 2021 - 2022File: RERA NA-1.pdf | - |
| Director's Report 2020 - 2021File: RERA NA-1.pdf | - |
| Cash Flow Statement 2021 - 2022File: All Platinm Narya Balance sheet 2022.pdf | - |
| Cash Flow Statement 2020 - 2021File: ALl Platinum Narya Balance sheet 2021.pdf | - |
| Auditor's Report 2021 - 2022File: All Platinm Narya Balance sheet 2022.pdf | - |
| Auditor's Report 2020 - 2021File: ALl Platinum Narya Balance sheet 2021.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR 2020-2021.pdf | - |
| BDA Licence | - |
| BESCOM_NOC & Receipt | - |
| Water_NOC | - |
| Approved plan | - |
| Sanction Plan | - |
| Sanction Plan | - |
| Specification Platinum Narya infra | - |
| CDP Site Marking | - |
| RERA NA-1 | - |
| 0 Advocate Search Report | - |
| Conversion Certificate | - |
| Conversion Certificate | - |
| Proforma of Agreement for Sale | - |
| Allotment Letter | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep PLATINUM EAST WOODS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 33 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
DS MAX SKY FIELDS
DS Max Properties Private Limited
Sowparnika Rhythm of Rain
SOWPARNIKA HOMES PRIVATE LIMITED
WORLD OF GARDENS
RLP TRENDSQUARES PROJECTS PRIVATE LIMITED
DS MAX SKYSAMPURN
DS MAX PROPERTIES PRIVATE LIMITED
Amrutha Lake Vista
Amrutha Shelters Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: PLATINUM - NARYA INFRA
PLATINUM - NARYA INFRA has 1 registration on RERA Karnataka, including PLATINUM EAST WOODS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if PLATINUM EAST WOODS is delayed beyond 30 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of PLATINUM EAST WOODS?
The registered promoter entity is PLATINUM - NARYA INFRA, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in PLATINUM EAST WOODS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at PLATINUM EAST WOODS?
The professionals named in the filing: Architect: ANI SAMBYAL; Engineer: MANOHAR.N; Chartered Accountant: A Subramanyam Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PLATINUM EAST WOODS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback