Home / Browse projects / Vadodara, Gujarat / OM RESIDENCY
OM RESIDENCY
RG-GJ-74096 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA06893/130320 · Last updated on GujRERA portal: 22 Apr 2024
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
OM RESIDENCY is a Residential/Group Housing project by OM DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA06893/130320 on 13 Mar 2020. Possession is promised by 30 Jun 2024. 37 of the 38 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.
At a glance
Project
- NameOM RESIDENCY
- TypeResidential/Group Housing
- Location
- Navapura
- Waghodia
- Vaghodiya
- Vadodara
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA06893/130320
- ReraGenie IDRG-GJ-74096
Builder
- NameOM DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations36 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2024
- Registered on13 Mar 2020
- Promised completion30 Jun 2024
- Revised completionNone
- Buildings1 building record
- Documents filed41 files
Current status
Figures as on 22 Apr 2024, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAW HOUSE | - | - | - | 38 | 0 | 38 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building1
As on 22 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.
RAW HOUSE: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 22 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | No | Not applicable |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 100% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RAW HOUSE | NA | Rs 2.30 cr | Rs 2.30 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASHWIN R PATEL |
| Engineer | DHARMESH SHAH |
Documents filed41
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA06893/130320 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 22 Apr 2024 |
| Engineer's certificate (Form 2) | 21 Apr 2024 |
| Engineer's certificate annexure | 21 Apr 2024 |
| Architect's certificate (Form 1) | 20 Apr 2024 |
| Site photograph, RAW HOUSE | 20 Apr 2024 |
| RERA registration certificate | 13 Mar 2020 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep OM RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vaghodiya2,900+ in Vadodara
Filed coordinates, straight-line distance. 6 registered projects within 2 km.
PMAY, EWS, TP 28, FP 152/1+152/2, R.S.no.585/1
VADODARA MUNICIPAL CORPORATION
AGORA CITY CENTER
MANAV INFRASTRUCTURE PRIVATE LIMITED
49 shops + 1560 EWS - II at Gorwa, Phase 5
GUJARAT HOUSING BOARD
PMAY-KHATAMBA
VADODARA URBAN DEVELOPMENT AUTHORITY
Akshar Pavilion
AKSHAR PHC REALCON
NAZARBAUG PALACE PHASE-1
ONS BUILDTECH LLP
See every Vadodara project, with the district possession charts
Builder: OM DEVELOPERS
OM DEVELOPERS has 37 registrations on GujRERA, including SARTHAK HABITAT and SAKAR EAST. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if OM RESIDENCY is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of OM RESIDENCY?
The registered promoter entity is OM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in OM RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at OM RESIDENCY?
The professionals named in the filing: Architect: ASHWIN R PATEL; Engineer: DHARMESH SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OM RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback