ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / OM RESIDENCY

Valid until 31 May 2026 Mixed Development project

OM RESIDENCY

By KEYA BUILDCON

RG-GJ-16998 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA08986/EX1/EX2/220725/310526 · Last updated on GujRERA portal: 14 Jul 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 23 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
May 2026Possession promisedmoved 23 months from the original
8 of 9Construction stages donefurthest along: Installation of lifts, 90%
13 of 50Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

OM RESIDENCY is a Mixed Development project by KEYA BUILDCON in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA08986/EX1/EX2/220725/310526 on 4 Sep 2021. Possession is promised by 31 May 2026. The completion date has moved by 23 months from the original filing. 37 of the 50 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameOM RESIDENCY
  • TypeMixed Development
  • Location
    • Revenue Servey No- 470
    • TP Scheme No-10
    • FP No- 20
    • Opp Kunj Villa Township
    • Near C K Prajapati School
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA08986/EX1/EX2/220725/310526
  • ReraGenie IDRG-GJ-16998

Builder

  • NameKEYA BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2021First promiseJun 2024Revised toMay 2026

Key facts

Registration and timeline

  • StatusValid until 31 May 2026
  • Registered on4 Sep 2021
  • Promised completion31 May 2026
  • Revised completionRevised to 31 May 2026 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed41 files

Current status

74%37 of 50 units booked
100.0%Of the estimated cost spent so far

Figures as on 14 Jul 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---401050

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 14 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Installation of lifts, at 90%.

A: 99% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%

Progress on shared amenities19

As on 14 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area929 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.72 cr
Cost incurredRs 4.72 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 4.72 crRs 4.72 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHarsh Pandya & Associates
EngineerChirag Shah

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA08986/EX1/050824/290625Applied Jun 2024; approved Aug 2024
PR/GJ/VADODARA/VADODARA/Others/MAA08986/EX1/EX2/220725/310526Applied Jun 2025; approved Jul 2025

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA08986/EX1/EX2/220725/310526 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)14 Jul 2025
Architect's certificate (Form 1)10 Jul 2025
Engineer's certificate (Form 2)10 Jul 2025
Engineer's certificate annexure10 Jul 2025
Site photograph, A9 Jul 2025
RERA registration certificate4 Sep 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

74%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 23 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep OM RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmOM RESIDENCYOther 166Dot size: filed unitsN

Filed coordinates, straight-line distance. 166 registered projects within 2 km.

Builder: KEYA BUILDCON

KEYA BUILDCON has 1 registration on GujRERA, including OM RESIDENCY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if OM RESIDENCY is delayed beyond 31 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OM RESIDENCY?

The registered promoter entity is KEYA BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OM RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OM RESIDENCY?

The professionals named in the filing: Architect: Harsh Pandya & Associates; Engineer: Chirag Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.