Valid until 31 Mar 2024 Residential/Group Housing project

OM AURA

By OMKAR DEVELOPERS

RG-GJ-91424 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA09679/070122 · Last updated on GujRERA portal: 30 Mar 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2024Possession promisedno revision filed
28 of 36Construction stages doneacross 4 buildings; furthest along: Plinth, 0%
0 of 14Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

OM AURA is a Residential/Group Housing project by OMKAR DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA09679/070122 on 7 Jan 2022. Possession is promised by 31 Mar 2024. 14 of the 14 units on this registration are recorded sold or booked, and 28 of 36 construction stages are filed complete.

At a glance

Project

  • NameOM AURA
  • TypeResidential/Group Housing
  • Location
    • B/H GOVERDHAN TOWNSHIP
    • WAGHODIA DABHOI RING ROAD
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA09679/070122
  • ReraGenie IDRG-GJ-91424

Builder

  • NameOMKAR DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations13 more →

Key dates

this monthRegisteredJan 2022PromisedMar 2024

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2024
  • Registered on7 Jan 2022
  • Promised completion31 Mar 2024
  • Revised completionNone
  • Buildings4 building records
  • Documents filed45 files

Current status

100%14 of 14 units booked
92.6%Of the estimated cost spent so far

Figures as on 30 Mar 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIPLEX D1-1 TO D2-6---606
TRIPLEX C1-7 TO C2-9---303
TRIPLEX B2-10 TO B1-13---404
TRIPLEX A-14---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 30 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Plinth, at 0%.

TRIPLEX D1-1 TO D2-6100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TRIPLEX C1-7 TO C2-9100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TRIPLEX B2-10 TO B1-13100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TRIPLEX A-1411%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 30 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,914 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.12 cr
Cost incurredRs 2.89 cr
Spent of the estimate92.6%
BuildingWingEstimatedIncurred
TRIPLEX A-14NARs 77.95 lakhRs 66.41 lakh
TRIPLEX B2-10 TO B1-13NARs 77.95 lakhRs 66.41 lakh
TRIPLEX C1-7 TO C2-9NARs 77.95 lakhRs 77.95 lakh
TRIPLEX D1-1 TO D2-6NARs 77.95 lakhRs 77.95 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN PATEL
EngineerSUJAL SHAH

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA09679/070122 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)30 Mar 2024
Architect's certificate (Form 1)19 Mar 2024
Engineer's certificate (Form 2)19 Mar 2024
Engineer's certificate annexure19 Mar 2024
Site photograph, TRIPLEX D1-1 TO D2-616 Mar 2024
Site photograph, TRIPLEX D1-1 TO D2-616 Mar 2024
Site photograph, TRIPLEX C1-7 TO C2-916 Mar 2024
Site photograph, TRIPLEX B2-10 TO B1-1316 Mar 2024
Site photograph, TRIPLEX A-1416 Mar 2024
RERA registration certificate7 Jan 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

100%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep OM AURA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmOM AURAOther 185Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: OMKAR DEVELOPERS

Omkar Developers has 14 registrations on GujRERA, including EARTH PARADISE and HARIAKSHA AVENUE. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if OM AURA is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OM AURA?

The registered promoter entity is OMKAR DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OM AURA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OM AURA?

The professionals named in the filing: Architect: KIRAN PATEL; Engineer: SUJAL SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM AURA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM AURA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM AURA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.