Home / Browse projects / Bengaluru Urban, Karnataka / NCC URBAN RETREAT

Registration approved Litigation declared Residential/Group Housing project

NCC URBAN RETREAT

By NCC URBAN INFRASTRUCTURE LIMITED

RG-KA-35438 · RERA PRM/KA/RERA/1251/446/PR/300125/007457 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2028Possession promisedno revision filed
0 of 15Construction stages donefurthest along: Foundation footing work, 98%
42 of 50Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 86 documents Report an error

NCC URBAN RETREAT is a Residential/Group Housing project by NCC URBAN INFRASTRUCTURE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/300125/007457 on 30 Jan 2025. Possession is promised by 30 Jun 2028. 8 of the 50 units on this registration are recorded sold or booked, and 0 of 15 construction stages are filed complete.

At a glance

Project

  • NameNCC URBAN RETREAT
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560077
  • Pincode560077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/300125/007457
  • ReraGenie IDRG-KA-35438

Builder

  • NameNCC URBAN INFRASTRUCTURE LIMITED
  • Entity typeCompany
  • GSTIN29AACCN2301G1ZV
  • Authorized SignatoryJ S R Raju
  • MdN R Alluri
  • DirectorsJ S R Raju, N R Alluri
  • Project HeadVenkatamohan Rao E
  • Other registrations4 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredJan 2025PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 Jan 2025
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed86 files

Current status

16%8 of 50 units booked
44.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---19019
B---14014
C---17017
D---101

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 15 construction stages are filed complete. The stage furthest along is Foundation footing work, at 98%.

Building: 37% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work80%
Foundation footing work98%
Upto Plinth Level98%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure92%
Masonry Construction80%
Plastering inside , outside & Ceiling40%
Joinery: Doors, Windows, Ventilators etc4%
Basic work of Water supply, Sanitary and Electrification20%
Dadoing, Skirting, Flooring, Tiles work (All types)4%
Railing and Grill fixing4%
Electrification, Water supply and Sanitary Finishing4%
Painting4%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work20%
Internal and External work including landscapes as per sanctioned drawings4%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes20%
Sewage and Drainage SystemYes20%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes20%
Electricity supply transformer and substationYes0%
Storm water drainsYes20%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes10%
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningYes0%
StaircasesYes90%
LiftsYes16%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes80%
Outer WallYes80%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,400 sq m
Named landowners1
LandownerVillageDistrict
SMT.KAMALA RAMAN,--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 87.88 cr
Cost incurredRs 39.47 cr
Spent of the estimate44.91%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 56.30 crRs 23.66 cr
On-site expenditure-Site OverheadRs 22.25 crRs 7.59 cr
On-site expenditure-Salaries of workersRs 6.76 crRs 6.38 cr
On-site expenditure-Consultants FeesRs 1.06 crRs 1.43 cr
Payment of feesRs 82.91 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 67.46 lakhRs 40.82 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVernekar Associates Pvt. Ltd.
EngineerS N Arun Kumar
Chartered AccountantP Mohan Raju

Litigation declared2

CaseCourtStatus
O.S.No.384/2024/2024Senior Civil Judge, Bangalore Rural District-
COM O.S.No.122Commercial Court, Bangalore Rural District-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed86

As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/300125/007457 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-04 CA Retreat Sep 2026.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-05 Architect Sep-2026 Retreat.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-06 Engg Sep-2026 Retreat.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-04 CA Certificate june 26 Retreat.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-05 Architect Certificate June 2026 Retreat.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-06 Engg Certificate June 2026 Retreat.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 04 CA Certificate Retreat.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 05 Architect Mar 2026 Retreat.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-06 Engg Mar-2026 Retreat.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-04 CA Retreat Dec-2025.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-05 Architect Certificate Retreat Dec 2025.pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-06 Engg Retreat Dec 2025.pdf19 Feb 2026
Q3 2025-26 Water supply and sewage board19 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)19 Feb 2026
Q3 2025-26 KPTCL- BESCOM19 Feb 2026
Cash flow statement for 2023-24File: Cash Flow Statement 2023-24.pdf28 Jan 2025
MR showing flow of titles in favor of landowner SMT.KAMALA RAMANFile: MUTATIONS-2.pdf28 Jan 2025
Defect free EC from 1-4-2004 to till dateFile: EC 01 04 2004 to 27 01 2025.pdf28 Jan 2025
Title deed of the current land ownerFile: Release Deed - 2143.pdf28 Jan 2025
Undertaking affidavit to permanently preserve 0-07 guntas of B-karab landFile: Affidavit Retreat Kharabh.pdf28 Jan 2025
Notarized affidavit regarding all pending or cleared litigations /non-litigationFile: Affidavit Retreat pending Litigations.pdf28 Jan 2025
RTC, survey Old Sy No.11 New Sy No.92-
Mutation, survey Old Sy No.11 New Sy No.92-
Encumbrance Certificate, survey Old Sy No.11 New Sy No.92-
Conversion/Alienation Order, survey Old Sy No.11 New Sy No.92-
JDA, survey Old Sy No.11 New Sy No.92-
Khatha, survey Old Sy No.11 New Sy No.92-
Registration CertificateFile: ROC.pdf-
Memorandum of AssociationFile: NCCUIL MOA.pdf-
Article of AssociationFile: NCCUIL AOA.pdf-
GST CertificateFile: GST Certificate NCCUIL.pdf-
Organization StructureFile: Orgnaization Structure.pdf-
Certificate issued by CA Form 1File: FORM-1 CA CERTIFICATE.PDF-
Certificate issued by Architect Form 2File: Form 2 Architecht Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-03 Engg Certificate Retreat.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
Land Litigation Details-
Land Litigation Details-
Land Litigation Details-
Land Litigation Details-
Balance Sheet 2023 - 2024File: Balance Sheet 2023-24.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet 2022-23.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet 2021-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: P & L STMNT 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P & L STMNT 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P & L STMNT 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR A 23-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR A 22-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR A 21-22.pdf-
Director's Report 2023 - 2024File: Notice and Directors Report 23-24 (NCC Urban).pdf-
Director's Report 2022 - 2023File: Notice and Directors Report NCC Urban 2022-23.pdf-
Director's Report 2021 - 2022File: Notice and Directors Report 2021-22 (NCC Urban).pdf-
Cash Flow Statement 2023 - 2024File: Cash Flow Stmnt 2022-23.pdf-
Cash Flow Statement 2022 - 2023File: Cash Flow Stmnt 2022-23.pdf-
Auditor's Report 2023 - 2024File: Auditors Report 2023-24.pdf-
Auditor's Report 2022 - 2023File: Auditors Report 2022-23.pdf-
Auditor's Report 2021 - 2022File: Auditors Report 2021-22.pdf-
License-
Approved PDF-
Approved PDF-
Structural Stability Certificate-
Project specifications- Retreat-
Retreat Brochure-
Proforma agreement of sale - Retreat-
Allotment letter Retreat-
FORMB NCCUIL AFFIDAVIT-
Affidavit Non Violation-
JD Affidavit RERA Retreat-
Legal Opinion Sy No 92 compressed-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
NCC Urban Park ViewSy No 5/2, Old Sy No 5, Mandalakunte Village Yelahanka Hobli Bangalore North TalukCompleted-No date filed
NCC URBAN MAYFAIR LitigationSy No 83, Old Sy No 41, Puttenahalli village, Yelahanka Hobli Bengaluru North TalukCompleted-No date filed

How this compares with Bengaluru Urban

16%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep NCC URBAN RETREAT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNCC URBAN RETREATOther 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 41 registered projects within 2 km.

Builder: NCC URBAN INFRASTRUCTURE LIMITED

NCC URBAN INFRASTRUCTURE LIMITED has 5 registrations on RERA Karnataka, including NCC URBAN GREEN PROVINCE PHASE 2 and NCC Urban Green Province One. Its filings declare 5 earlier projects, 2 of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if NCC URBAN RETREAT is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NCC URBAN RETREAT?

The registered promoter entity is NCC URBAN INFRASTRUCTURE LIMITED, a company as per the filing. Its GSTIN 29AACCN2301G1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NCC URBAN RETREAT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NCC URBAN RETREAT?

The professionals named in the filing: Architect: Vernekar Associates Pvt. Ltd.; Engineer: S N Arun Kumar; Chartered Accountant: P Mohan Raju. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NCC URBAN RETREAT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NCC URBAN RETREAT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NCC URBAN RETREAT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.