Valid until 31 Dec 2026 Mixed Development project

Narayan Vandan

By JP BUILD_TECH

RG-GJ-04500 · RERA PR/GJ/ANAND/ANAND/Others/MAA07933/EX1/EX2/260526/311226 · Last updated on GujRERA portal: 7 May 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 24 months from the original
9 of 18Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 97%
11 of 26Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

Narayan Vandan is a Mixed Development project by JP BUILD_TECH in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Others/MAA07933/EX1/EX2/260526/311226 on 18 Jan 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 15 of the 26 units on this registration are recorded sold or booked, and 9 of 18 construction stages are filed complete.

At a glance

Project

  • NameNarayan Vandan
  • TypeMixed Development
  • Location
    • NARAYAN VANDAN
    • OPP KESAR VATIKA
    • NR RAJ SHIVALAY
    • ANAND
    • Anand
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Others/MAA07933/EX1/EX2/260526/311226
  • ReraGenie IDRG-GJ-04500

Builder

  • NameJP BUILD_TECH
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on18 Jan 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed43 files

Current status

58%15 of 26 units booked
80.2%Of the estimated cost spent so far

Figures as on 7 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
COMMERCIAL---01818
RESIDENTIAL---808

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 7 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

COMMERCIAL86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
RESIDENTIAL69%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats87%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks89%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing12%

Progress on shared amenities19

As on 7 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingNoNot applicable
Street lightingYes12%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes20%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,207 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.85 cr
Cost incurredRs 2.28 cr
Spent of the estimate80.15%
BuildingWingEstimatedIncurred
RESIDENTIALNARs 1.88 crRs 1.37 cr
COMMERCIALNARs 96.90 lakhRs 91.09 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFALGUNI KSHATRIYA
EngineerMITESH DAVE

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/ANAND/ANAND/Others/MAA07933/EX1/210125/311225Applied Dec 2024; approved Jan 2025
PR/GJ/ANAND/ANAND/Others/MAA07933/EX1/EX2/260526/311226Applied Dec 2025; approved May 2026

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Others/MAA07933/EX1/EX2/260526/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 May 2026
Architect's certificate (Form 1)6 May 2026
Engineer's certificate (Form 2)6 May 2026
Engineer's certificate annexure6 May 2026
Site photograph, COMMERCIAL6 May 2026
Site photograph, RESIDENTIAL6 May 2026
RERA registration certificate18 Jan 2021
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

58%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one moved by 24 months

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep Narayan Vandan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Anand310+ in Anand

2 kmNarayan VandanOther 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 74 registered projects within 2 km.

Builder: JP BUILD_TECH

JP BUILD_TECH has 1 registration on GujRERA, including Narayan Vandan. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if Narayan Vandan is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Narayan Vandan?

The registered promoter entity is JP BUILD_TECH, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Narayan Vandan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Narayan Vandan?

The professionals named in the filing: Architect: FALGUNI KSHATRIYA; Engineer: MITESH DAVE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Narayan Vandan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Narayan Vandan. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Narayan Vandan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.