NAND UPVAN

By DEV DEVELOPERS

RG-GJ-70755 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA11876/310523 · Last updated on GujRERA portal: 10 Sep 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Apr 2027Possession promisedmoved 16 months from the original
3 of 54Construction stages doneacross 6 buildings; furthest along: Plinth, 80%
20 of 22Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

NAND UPVAN is a Residential/Group Housing project by DEV DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA11876/310523 on 31 May 2023. Possession is promised by 30 Apr 2027. The completion date has moved by 16 months from the original filing. 2 of the 22 units on this registration are recorded sold or booked, and 3 of 54 construction stages are filed complete.

At a glance

Project

  • NameNAND UPVAN
  • TypeResidential/Group Housing
  • Location
    • LAND BEARING BLOCK NO 423
    • OP NO 5/8
    • FP NO 5/8
    • TP NO 40
    • VILLAGE- KAPURAI
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA11876/310523
  • ReraGenie IDRG-GJ-70755

Builder

  • NameDEV DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations9 more →

Key dates

this monthRegisteredMay 2023First promiseDec 2025Revised toApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on31 May 2023
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2025)
  • Buildings6 building records
  • Documents filed38 files

Current status

9%2 of 22 units booked
10.3%Of the estimated cost spent so far

Figures as on 10 Sep 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A---505
TYPE C---404
TYPE B---505
TYPE E---202
TYPE D---404
TYPE F---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 10 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Plinth, at 80%.

TYPE A33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE C0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE B31%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth80%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE E0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE D0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE F0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 10 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,703 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.25 cr
Cost incurredRs 75.00 lakh
Spent of the estimate10.34%
BuildingWingEstimatedIncurred
TYPE ANARs 1.64 crRs 41.00 lakh
TYPE BNARs 1.64 crRs 34.00 lakh
TYPE CNARs 1.31 cr-
TYPE DNARs 1.31 cr-
TYPE ENARs 67.00 lakh-
TYPE FNARs 67.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARYA ASSOCIATES
EngineerSHRI KISHORBHAI L PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Dec 2025; no approval date filed

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA11876/310523 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)10 Sep 2024
Engineer's certificate annexure10 Sep 2024
RERA registration certificate31 May 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

9%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 16 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep NAND UPVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmNAND UPVANOther 203Dot size: filed unitsN

Filed coordinates, straight-line distance. 203 registered projects within 2 km.

Builder: DEV DEVELOPERS

DEV DEVELOPERS has 10 registrations on GujRERA, including Dev Shikhar and Dwarika Bhoomi. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if NAND UPVAN is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of NAND UPVAN?

The registered promoter entity is DEV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in NAND UPVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NAND UPVAN?

The professionals named in the filing: Architect: ARYA ASSOCIATES; Engineer: SHRI KISHORBHAI L PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAND UPVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAND UPVAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAND UPVAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.