Home / Browse projects / Bengaluru Urban, Karnataka / Mahendra Arto Helix
Mahendra Arto Helix
RG-KA-27299 · RERA PRM/KA/RERA/1251/308/PR/270723/006099 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
Saved.
Mahendra Arto Helix is a Residential/Group Housing project by MAHENDRA ARTO LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/270723/006099 on 27 Jul 2023. Possession is promised by 30 Jun 2028. 163 of the 273 units on this registration are recorded sold or booked, and 5 of 15 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameMahendra Arto Helix
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 560100
- Pincode560100
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/270723/006099
- ReraGenie IDRG-KA-27299
Builder
- NameMAHENDRA ARTO LLP
- Entity typePartnership Firm
- LLPINABA-1309
- GSTIN29ABTFM1617P1ZF
- Authorized SignatoryMAHENDRA B N
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on27 Jul 2023
- Promised completion30 Jun 2028
- Revised completionNone
- Buildings2 building records
- Documents filed197 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Towe-A | - | - | - | 196 | 0 | 196 |
| Tower -B | - | - | - | 198 | 0 | 198 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 15 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 83%.
Building: 57% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Retaining wall (All types) | 100% |
| Plinth level Beam | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| RCC or MS Framed structure | 83% |
| Masonry construction: Bricks, Concrete blocks etc | Not applicable |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | 25% |
| Basic work of Water supply, Sanitary and Electrification | 33% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 55% |
| Railing and Grill fixing | 33% |
| Electrification, Water supply and Sanitary Finishing | 33% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | 54% |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | 46% |
| Elevation work | 0% |
| Internal and External work including landscapes as per santioned drawings | 0% |
Progress on shared amenities41
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 27% |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | 27% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 55% |
| Water conservation | Yes | 55% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 30% |
| Education/Health/Other public amenities | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Gas | Yes | 0% |
| Water and Sanitation | Yes | 0% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 87% |
| Lifts | Yes | 0% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 87% |
| Fire escapes | Yes | 85% |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 85% |
| Basement | Yes | 75% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas and common storage spaces | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| B T Nagaraj Reddy | - | - |
| HARI PRASAD, | - | - |
| GURUPRASAD | - | - |
| RAM PRASAD | - | - |
| RAJENDRA PRASAAD | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 260.00 cr | Rs 130.23 cr |
| Total on site overheads | Rs 63.97 cr | Rs 24.35 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 15.02 cr | Rs 5.07 cr |
| Payment of fees | Rs 6.00 cr | Rs 5.63 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Surendran R |
| Engineer | Nagesh BV |
| Chartered Accountant | MALLIKARJUNAIAH B |
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00994/2026 | - | MAHENDRA ARTO LLP | 12/08/2026 |
Documents filed197
As listed on the registration, under the names the promoter filed them with; the newest 80 of 197 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/270723/006099 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4- Q2 Letterhead.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Final Q-2 ARCHITECT'S CERTIFICATE.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers Certificate Mahendra Arto.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Signed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Final Q-1 ARCHITECT'S CERTIFICATE.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers Certificate Mahendra Arto Llp (1) - converted.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Modification_of_Project-MALLP.pdf | 16 Apr 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECT'S CERTIFICATE.pdf | 16 Apr 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers Certifcate (1).pdf | 16 Apr 2026 |
| Q3 2025-26 Water supply and sewage board | 16 Apr 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 16 Apr 2026 |
| Q3 2025-26 KPTCL- BESCOM | 16 Apr 2026 |
| Q3 2025-26 Fire and Safety | 16 Apr 2026 |
| Q3 2025-26 Airport Authority of India | 16 Apr 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 16 Apr 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4- MALLP Q4 Certified CONVERTED.pdf | 16 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Final Q-3 ARCHITECT'S CERTIFICATE Q4.pdf | 16 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEER’S CERTIFCATE Q4.pdf | 16 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 16 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 16 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 16 Apr 2026 |
| Q4 2025-26 Fire and Safety | 16 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 16 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 16 Apr 2026 |
| Reply to QueryFile: Reply to Query.pdf | 6 Feb 2026 |
| & 2 Affidavit-Renewed Building Plan and LetterFile: 1 & 2 Affidavit-Renewed Building Plan and Letter.pdf | 6 Feb 2026 |
| Structural Stability CertificateFile: 3 Structural Stability Certificate.pdf | 6 Feb 2026 |
| Sold and Unsold DetailsFile: 4 Sold and Unsold Details.pdf | 6 Feb 2026 |
| Modified-Lower and Upper Basement Floor PlanFile: 5 Modified-Lower and Upper Basement Floor Plan.pdf | 6 Feb 2026 |
| Modified-Ground Floor Plan and Site PlanFile: 5 Modified-Ground Floor Plan and Site Plan.pdf | 6 Feb 2026 |
| Modified-1st to 34th Floor Plan and Terrace Floor PlanFile: 5 Modified-1st to 34th Floor Plan and Terrace Floor Plan.pdf | 6 Feb 2026 |
| Modified-Elevation and Section PlanFile: 5 Modified-Elevation and Section Plan.pdf | 6 Feb 2026 |
| Modified-Tower B and Amenity BlockFile: 5 Modified-Tower B and Amenity Block.pdf | 6 Feb 2026 |
| Previous-Elevation and Section PlanFile: 5 Previous-Elevation and Section Plan.pdf | 6 Feb 2026 |
| Previous-Ground Floor Plan and Site PlanFile: 5 Previous-Ground Floor Plan and Site Plan.pdf | 6 Feb 2026 |
| Previous-Lower & Upper Basement Floor PlanFile: 5 Previous-Lower & Upper Basement Floor Plan.pdf | 6 Feb 2026 |
| Previous-Tower A 1 -24th Floor Plan and Terrace Floor PlanFile: 5 Previous-Tower A 1 -24th Floor Plan and Terrace Floor Plan.pdf | 6 Feb 2026 |
| Previous-Tower B & Amenity Block 1 -23rd Floor Plan and Terrace Floor PlanFile: 5 Previous-Tower B & Amenity Block 1 -23rd Floor Plan and Terrace Floor Plan.pdf | 6 Feb 2026 |
| Sold and Unsold DetailsFile: 6 Sold and Unsold Details.pdf | 6 Feb 2026 |
| Structural Stability CertificateFile: 8 Structural Stability Certificate.pdf | 6 Feb 2026 |
| Self-Attested Engineer LicenseFile: 9 Self-Attested Engineer License.pdf | 6 Feb 2026 |
| Airport Authority of India NOCFile: 10 Airport Authority of India NOC.pdf | 6 Feb 2026 |
| BESCOM NOCFile: 10 BESCOM NOC.pdf | 6 Feb 2026 |
| BSNL NOCFile: 10 BSNL NOC.pdf | 6 Feb 2026 |
| BWSSB Water NOCFile: 10 BWSSB Water NOC.pdf | 6 Feb 2026 |
| Fire NOCFile: 10 Fire NOC.pdf | 6 Feb 2026 |
| KSPCB NOCFile: 10 KSPCB NOC.pdf | 6 Feb 2026 |
| SEIAA NOCFile: 10 SEIAA NOC.pdf | 6 Feb 2026 |
| GUIDENCE VALUEFile: GUIDENCE VALUE.pdf | 19 Jul 2023 |
| Single plot layoutFile: Upload Single plot layout.pdf | 19 Jul 2023 |
| Single plot layout OrderFile: Upload Single plot layout Order.pdf | 19 Jul 2023 |
| Carpet area calculationFile: Certified Carpet area calculation.pdf | 19 Jul 2023 |
| CDPFile: CDP.pdf | 19 Jul 2023 |
| Village mapFile: Village map.pdf | 19 Jul 2023 |
| Relinquishment deedFile: Relinquishment deed-Road widening area.pdf | 19 Jul 2023 |
| Building LicenseFile: Building License.pdf | 19 Jul 2023 |
| Tower A PlanFile: Tower A Plan.pdf | 19 Jul 2023 |
| Tower B PlanFile: Tower B Plan.pdf | 19 Jul 2023 |
| Tower A B and Amenity_Ground and Basement PlanFile: Tower A B and Amenity_Ground and Basement Plan.pdf | 19 Jul 2023 |
| Tower A B Elevation and Section PlanFile: Tower A B Elevation and Section Plan.pdf | 19 Jul 2023 |
| Upper and Lower Floor PlanFile: Upper and Lower Floor Plan.pdf | 19 Jul 2023 |
| Engineer license certificateFile: Engineer license certificate.pdf | 19 Jul 2023 |
| Project specificationFile: Project specification certified by the Engineer.pdf | 19 Jul 2023 |
| Water NOCFile: Water NOC.pdf | 19 Jul 2023 |
| Structural safety certificateFile: Structural safety.pdf | 19 Jul 2023 |
| Estimated cost of constructionFile: Estimated cost of construction.pdf | 19 Jul 2023 |
| STPFile: STP.pdf | 19 Jul 2023 |
| AOSFile: Mahendra_Helix_AOS.pdf | 19 Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Mahendra Arto Helix on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 12 registered projects within 2 km.
AJMERA IRIS
AJMERA HOUSING CORPORATION BANGALORE
INSPIRA TROPICAL GARDEN
IINSPIRA TROPICAL GARDEN LLP
Shravanthi Prakruti
BKN Developers Pvt Ltd
Ayatana Residences E-City
ARATT ONE WORLD PRIVATE LIMITED
SPLENDID EVORA
SPLENDID PROPERTIES
VARAD
SATYAM BUILDERS & DEVELOPERS
See every Bengaluru Urban project, with the district possession charts
Builder: MAHENDRA ARTO LLP
MAHENDRA ARTO LLP has 1 registration on RERA Karnataka, including Mahendra Arto Helix. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Mahendra Arto Helix is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Mahendra Arto Helix?
The registered promoter entity is MAHENDRA ARTO LLP, a partnership firm as per the filing. Its LLPIN ABA-1309 and GSTIN 29ABTFM1617P1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Mahendra Arto Helix?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mahendra Arto Helix?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Mahendra Arto Helix?
The professionals named in the filing: Architect: Surendran R; Engineer: Nagesh BV; Chartered Accountant: MALLIKARJUNAIAH B. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mahendra Arto Helix?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback