Home / Browse projects / Bengaluru Urban, Karnataka / AJMERA IRIS

Registration approved No litigation declared Residential/Group Housing project

AJMERA IRIS

By AJMERA HOUSING CORPORATION BANGALORE

RG-KA-11780 · RERA PRM/KA/RERA/1251/310/PR/281024/007184 · Last updated on RERA Karnataka portal: 3 Nov 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
9 of 17Construction stages donefurthest along: Basic work of Water supply, 80%
74 of 215Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 156 documents Report an error

AJMERA IRIS is a Residential/Group Housing project by AJMERA HOUSING CORPORATION BANGALORE in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/281024/007184 on 28 Oct 2024. Possession is promised by 31 Dec 2026. 141 of the 215 units on this registration are recorded sold or booked, and 9 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAJMERA IRIS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560100
  • Pincode560100
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/281024/007184
  • ReraGenie IDRG-KA-11780

Builder

  • NameAJMERA HOUSING CORPORATION BANGALORE
  • Entity typePartnership Firm
  • GSTIN29AAKFA5286R1ZG
  • Authorized SignatoryDEEPAK S MEHTA
  • Other registrations5 more →
  • Declared earlier projects18 →

Key dates

this monthRegisteredOct 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Oct 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings11 building records
  • Documents filed156 files

Current status

66%141 of 215 units booked
82.9%Of the estimated cost spent so far

Figures as on 3 Nov 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-1(WING A)---20020
BLOCK-1(WING B)---20020
BLOCK-1(WING C)---20020
BLOCK-1(WING D)---20020
BLOCK-2(WING E)---15015
BLOCK-2(WING F)---20020
BLOCK-2(WING G)---20020
BLOCK-3(WING H)---20020
BLOCK-3(WING I)---20020
BLOCK-3(WING J)---20020
BLOCK3 (WING K)---20020

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 3 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 17 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 80%.

Building: 91% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)80%
Railing and Grill fixing80%
Electrification, Water supply and Sanitary Finishing80%
Painting80%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)80%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work80%
Internal and External work including landscapes as per sanctioned drawings80%

Progress on shared amenities40

As on 3 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Sewage and Drainage SystemYes50%
Water conservation/rain water harvesting/recharge of ground waterYes50%
Energy managementYes50%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes50%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes50%
Electricity supply transformer and substationYes50%
Storm water drainsYes50%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes50%
Parks & Tree plantingYes50%
Street LightingYes50%
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes80%
Club HouseYes80%
Community HallYes80%
Outdoor Sports facilityYes50%
Indoor Sports facilityYes50%
Swimming PoolYes50%
GymYes50%
ParksYes50%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes50%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes80%
Corridor/LobbiesYes80%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes80%
BasementYes80%
TerraceYes80%
Outer WallYes80%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesYes80%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,452 sq m
Named landowners1
LandownerVillageDistrict
SIRAJ--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 121.91 cr
Cost incurredRs 101.11 cr
Spent of the estimate82.93%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 83.55 crRs 68.09 cr
On-site expenditure-Site OverheadRs 18.18 crRs 21.44 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 11.51 crRs 1.35 cr
On-site expenditure-Salaries of workersRs 5.30 crRs 6.25 cr
On-site expenditure-Consultants FeesRs 1.92 crRs 2.26 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.45 crRs 1.71 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAMUNA CHALAM
EngineerISA STRUCTURAL STUDIO.
Chartered AccountantNV RAMANA & CO

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00661/2025-AJMERA HOUSING CORPORATION BANGALORE22/04/2025

Documents filed156

As listed on the registration, under the names the promoter filed them with; the newest 80 of 156 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/281024/007184 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: AJMERA IRIS Form -4 Chartered Accountant.pdf3 Nov 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Ajmera Iris ARCH CERT.pdf3 Nov 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Ajmira Iris ENGINEERS CERT 30092026.pdf3 Nov 2026
Q2 2026-27 Water supply and sewage board3 Nov 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)3 Nov 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)3 Nov 2026
Q2 2026-27 KPTCL- BESCOM3 Nov 2026
Q2 2026-27 Labour and Education Department3 Nov 2026
Q2 2026-27 Airport Authority of India3 Nov 2026
Q2 2026-27 BSNL/Telecommunication Department3 Nov 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: AJMERA IRIS Form -4 Chartered Accountant.pdf3 Aug 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate-IRIS-300626.pdf3 Aug 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Ajmera IRIS ENGINEERING As on 30062026.pdf3 Aug 2026
Q1 2026-27 Water supply and sewage board3 Aug 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)3 Aug 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)3 Aug 2026
Q1 2026-27 KPTCL- BESCOM3 Aug 2026
Q1 2026-27 Labour and Education Department3 Aug 2026
Q1 2026-27 Airport Authority of India3 Aug 2026
Q1 2026-27 BSNL/Telecommunication Department3 Aug 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: AJMERA IRIS Form -4 Chartered Accountant_compressed.pdf7 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Iris Architecth certificate-Form-06 as on 31032026.pdf7 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Iris CE certificate-Form-06 as on 31032026.pdf7 May 2026
Q4 2025-26 Water supply and sewage board7 May 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)7 May 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)7 May 2026
Q4 2025-26 KPTCL- BESCOM7 May 2026
Q4 2025-26 Labour and Education Department7 May 2026
Q4 2025-26 Airport Authority of India7 May 2026
Q4 2025-26 BSNL/Telecommunication Department7 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: AJMERA IRIS Form -4 Chartered Accountant_compressed.pdf26 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architects Certificate IRIS.pdf26 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Ajmera Iris CE CERTIFICATE.pdf26 Jan 2026
Q3 2025-26 Water supply and sewage board26 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)26 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)26 Jan 2026
Q3 2025-26 KPTCL- BESCOM26 Jan 2026
Q3 2025-26 Labour and Education Department26 Jan 2026
Q3 2025-26 Airport Authority of India26 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department26 Jan 2026
Chartered accountant certificate form-1 with UDINFile: CA Form No1.pdf20 Oct 2024
Upload bank 100%, 70%, and 30% account pass sheets or statementsFile: Bank Account confirmation.pdf20 Oct 2024
The total estimated project cost mentioned in the bank affidavit needs to be correctedFile: Bank affidavit.pdf20 Oct 2024
Sources of funds to complete the projectFile: Source of funds required to complete the project.pdf20 Oct 2024
As per financial statements, borrowing details not mentioned in sources of funds, please update wFile: RBL-Sanction Letter-Iris.pdf20 Oct 2024
Quarterly update of previous project - Ajmera LugaanoFile: Quarterly Update Details Lugaano.pdf20 Oct 2024
Quarterly update of previous project - Ajmera florenzaFile: Quarterly Update Details Florenza.pdf20 Oct 2024
Self Attested KYC of PartnersFile: Partners KYC.pdf20 Oct 2024
Connected MR in favor of landowner before conversion showing flow of titlesFile: MR36-2000-01.jpeg20 Oct 2024
EC from 1-7/2/2024 to till dateFile: ECC-17102024-5695223 (1).pdf20 Oct 2024
Mother conversion order issued by the deputy commissionerFile: Conversion -Hi-Tech-NO S R 6--20101-12.pdf20 Oct 2024
Title deed of the current landowner as per latest transaction - Sale Deed (Doc. No.1840)File: Sale Deed (Doc No1840)_1.pdf20 Oct 2024
Title deed of the current landowner as per latest transaction - SALEDEED NUMBER 1847-YEAR 1997-1998File: SALEDEED NUMBER 1847-YEAR 1997-1998_1.pdf20 Oct 2024
Title deed of the current landowner as per latest transaction - Sale Deed1859-1997-98File: SD-Siraj 1859-1997-98_1.pdf20 Oct 2024
Title deed of the current landowner as per latest transaction - Sale Deed-2705-2001-02File: SD-Siraj-2705-2001-02_1.pdf20 Oct 2024
Structural safety adopted for the proposed building - Certificated by Registered EngineerFile: Ajmera Iris Structural.pdf20 Oct 2024
STP design drawing as per the Guidelines of KSPCB NOCFile: SITE PLAN MOEF SANCTION-Model.pdf20 Oct 2024
Self-attested copy of the NOC issued by BESCOM and BWSSB along with the copy of the fee receipt paidFile: attested BESCOM & BWSSB NOC.pdf20 Oct 2024
Land cost calculation sheet as per the guidance valueFile: land cost calculation.pdf20 Oct 2024
Allotment letter in the prescribed formatFile: DRAFT ALLOTMENT LETTER NEW FORMAT by RERA govt of Karnataka-.pdf20 Oct 2024
Proforma of Agreement for Sale (AFS)File: Final draft- ATS-RERA.pdf20 Oct 2024
Estimated cost of construction certified by the EngineerFile: Estimated cost.pdf20 Oct 2024
Project specification certified by the EngineerFile: Project Specification.pdf20 Oct 2024
Section 3(1) notarized affidavitFile: AFFIDAT 4682W.pdf20 Oct 2024
Self-attested copy of the Engineer license certificateFile: Certificate-CE.pdf20 Oct 2024
Amenities and Common area detailsFile: Amenities and Common area details .pdf20 Oct 2024
RTC, survey 30/25-
Mutation, survey 30/25-
Encumbrance Certificate, survey 30/25-
Conversion/Alienation Order, survey 30/25-
JDA, survey 30/25-
Khatha, survey 30/25-
Registration CertificateFile: Registration Certificate0000.jpg-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
AJMERA FLORENZAAJMERA FLORENZA, SY NO 7/1,9/1 KEMPANAHALI VILLAGE,YELAHANKA HOBLI, BANGALORE NORTH TALUK, YELAHANKA, BENGALURU URBAN, KARNATAKAOngoingSep 2025Not delivered
AJMERA NUCLEUS RESIDENTIAL AB WINGSY NO 13/5, ELECTRONIC CITY PHASE 2, DODDANAGAMANGALA MAIN ROAD,Completed-No date filed
AJMERA NUCLEUS C WINGSY NO 13/5, ELECTRONIC CITY PHASE 2, DODDANAGAMANGALA MAIN ROAD,Completed-No date filed

How this compares with Bengaluru Urban

66%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AJMERA IRIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAJMERA IRISOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: AJMERA HOUSING CORPORATION BANGALORE

AJMERA HOUSING CORPORATION BANGALORE has 6 registrations on RERA Karnataka, including AJMERA NUCLEUS PHASE 2 (RESIDENTIAL -C WING) and AJMERA MARINA. Its filings declare 18 earlier projects, 17 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AJMERA IRIS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AJMERA IRIS?

The registered promoter entity is AJMERA HOUSING CORPORATION BANGALORE, a partnership firm as per the filing. Its GSTIN 29AAKFA5286R1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AJMERA IRIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AJMERA IRIS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at AJMERA IRIS?

The professionals named in the filing: Architect: JAMUNA CHALAM; Engineer: ISA STRUCTURAL STUDIO.; Chartered Accountant: NV RAMANA & CO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AJMERA IRIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AJMERA IRIS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AJMERA IRIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.