Home / Browse projects / Vadodara, Gujarat / MADHUBAN SQUARE II

Valid until 31 Mar 2024 Residential/Group Housing project

MADHUBAN SQUARE II

By DISHA DEVELOPERS

RG-GJ-51540 · RERA PR/GJ/VADODARA/KARJAN/Others/RAA07491/230920 · Last updated on GujRERA portal: 28 Mar 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2024Possession promisedno revision filed
90 of 90Construction stages doneacross 10 buildings; every applicable stage filed complete
2 of 66Units unsoldnot recorded sold or booked
Jump to the 50 documents Report an error

MADHUBAN SQUARE II is a Residential/Group Housing project by DISHA DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/KARJAN/Others/RAA07491/230920 on 23 Sep 2020. Possession is promised by 31 Mar 2024. 64 of the 66 units on this registration are recorded sold or booked, and 90 of 90 construction stages are filed complete.

At a glance

Project

  • NameMADHUBAN SQUARE II
  • TypeResidential/Group Housing
  • Location
    • MADHUBAN SQUARE II
    • OPP. KARJAN PUBLIC SCHOOL
    • MIYAGAM CHOKDI
    • Karjan
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/KARJAN/Others/RAA07491/230920
  • ReraGenie IDRG-GJ-51540

Builder

  • NameDISHA DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2020PromisedMar 2024

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2024
  • Registered on23 Sep 2020
  • Promised completion31 Mar 2024
  • Revised completionNone
  • Buildings10 building records
  • Documents filed50 files

Current status

97%64 of 66 units booked
100.0%Of the estimated cost spent so far

Figures as on 28 Mar 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A3---101
TYPE A4---202
TYPE A5---101
TYPE A6---101
TYPE B1---606
TYPE B2---606
TYPE B3---202
TYPE B4---202
TYPE A1---23023
TYPE A2---22022

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building10

As on 28 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

90 of 90 construction stages are filed complete across 10 buildings.

TYPE A3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE A4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE A5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE A6100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE B1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE B2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE B3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE B4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE A1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE A2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,600 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.10 cr
Cost incurredRs 6.10 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TYPE A1NARs 2.21 crRs 2.21 cr
TYPE A2NARs 2.11 crRs 2.11 cr
TYPE B1NARs 50.44 lakhRs 50.44 lakh
TYPE B2NARs 50.44 lakhRs 50.44 lakh
TYPE A4NARs 18.67 lakhRs 18.67 lakh
TYPE B4NARs 16.09 lakhRs 16.09 lakh
TYPE B3NARs 16.05 lakhRs 16.05 lakh
TYPE A3NARs 9.38 lakhRs 9.38 lakh
TYPE A5NARs 8.46 lakhRs 8.46 lakh
TYPE A6NARs 8.30 lakhRs 8.30 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAditya Ajit Umrajkar
EngineerANIL MISTRY

Documents filed50

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/KARJAN/Others/RAA07491/230920 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)28 Mar 2024
Engineer's certificate (Form 2)28 Mar 2024
Engineer's certificate annexure28 Mar 2024
Accountant's certificate (Form 3)28 Mar 2024
Site photograph, TYPE A318 Mar 2024
Site photograph, TYPE A418 Mar 2024
Site photograph, TYPE A518 Mar 2024
Site photograph, TYPE A618 Mar 2024
Site photograph, TYPE B118 Mar 2024
Site photograph, TYPE B218 Mar 2024
Site photograph, TYPE B318 Mar 2024
Site photograph, TYPE B418 Mar 2024
Site photograph, TYPE A118 Mar 2024
Site photograph, TYPE A218 Mar 2024
RERA registration certificate23 Sep 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

97%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep MADHUBAN SQUARE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Karjan2,900+ in Vadodara

2 kmMADHUBAN SQUARE IIOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: DISHA DEVELOPERS

DISHA DEVELOPERS has 2 registrations on GujRERA, including MADHUBAN RESIDENCY and MADHUBAN SQUARE II. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if MADHUBAN SQUARE II is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of MADHUBAN SQUARE II?

The registered promoter entity is DISHA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in MADHUBAN SQUARE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MADHUBAN SQUARE II?

The professionals named in the filing: Architect: Aditya Ajit Umrajkar; Engineer: ANIL MISTRY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MADHUBAN SQUARE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MADHUBAN SQUARE II. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MADHUBAN SQUARE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.