Home / Browse projects / Vadodara, Gujarat / Madhav Resi Cum Plaza Phase 2

Valid until 25 Jun 2026 Mixed Development project

Madhav Resi Cum Plaza Phase 2

By NIRAV ASSOCIATES

RG-GJ-65364 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA04167/A1M/210919 · Last updated on GujRERA portal: 25 Jul 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
48 of 54Construction stages doneacross 6 buildings; furthest along: Stilt Floor, 0%
78 of 182Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

Madhav Resi Cum Plaza Phase 2 is a Mixed Development project by NIRAV ASSOCIATES in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA04167/A1M/210919 on 29 Nov 2018. Possession is promised by 25 Jun 2026. 104 of the 182 units on this registration are recorded sold or booked, and 48 of 54 construction stages are filed complete.

At a glance

Project

  • NameMadhav Resi Cum Plaza Phase 2
  • TypeMixed Development
  • Location
    • NR KHODIYAR NAGAR
    • OPP MY SHANNEN SCHOOL
    • Vadodara
    • 390006
  • Pincode390006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA04167/A1M/210919
  • ReraGenie IDRG-GJ-65364

Builder

  • NameNIRAV ASSOCIATES
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredNov 2018PromisedJun 2026

Key facts

Registration and timeline

  • StatusValid until 25 Jun 2026
  • Registered on29 Nov 2018
  • Promised completion25 Jun 2026
  • Revised completionNone
  • Buildings6 building records
  • Documents filed43 files

Current status

57%104 of 182 units booked
100.0%Of the estimated cost spent so far

Figures as on 25 Jul 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER I---20020
TOWER J---20020
TOWER K---30030
TOWER L---161834
TOWER C D---322658
TOWER E---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 25 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

48 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Stilt Floor, at 0%.

TOWER I89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER J89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER K89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER L89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER C D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER E89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 25 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyNoNot applicable
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,448 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.35 cr
Cost incurredRs 15.35 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TOWER C DNARs 2.56 crRs 2.56 cr
TOWER ENARs 2.56 crRs 2.56 cr
TOWER INARs 2.56 crRs 2.56 cr
TOWER JNARs 2.56 crRs 2.56 cr
TOWER KNARs 2.56 crRs 2.56 cr
TOWER LNARs 2.56 crRs 2.56 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN PATEL
EngineerNARENDRA PATEL

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA04167/A1M/210919 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)25 Jul 2022
Architect's certificate (Form 1)14 Jul 2022
Engineer's certificate (Form 2)14 Jul 2022
Engineer's certificate annexure14 Jul 2022
Site photograph, TOWER I14 Jul 2022
Site photograph, TOWER J14 Jul 2022
Site photograph, TOWER K14 Jul 2022
Site photograph, TOWER L14 Jul 2022
Site photograph, TOWER C D14 Jul 2022
Site photograph, TOWER E14 Jul 2022
RERA registration certificate29 Nov 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

57%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Madhav Resi Cum Plaza Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmMadhav Resi Cum Plaza PhOther 117Dot size: filed unitsN

Filed coordinates, straight-line distance. 117 registered projects within 2 km.

Builder: NIRAV ASSOCIATES

NIRAV ASSOCIATES has 2 registrations on GujRERA, including MADHAV RESI CUM PLAZA - PHASE 1 and Madhav Resi Cum Plaza Phase 2. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Madhav Resi Cum Plaza Phase 2 is delayed beyond 25 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Madhav Resi Cum Plaza Phase 2?

The registered promoter entity is NIRAV ASSOCIATES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Madhav Resi Cum Plaza Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Madhav Resi Cum Plaza Phase 2?

The professionals named in the filing: Architect: KIRAN PATEL; Engineer: NARENDRA PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Madhav Resi Cum Plaza Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Madhav Resi Cum Plaza Phase 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Madhav Resi Cum Plaza Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.