Lilleria Signature
RG-GJ-95857 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926 · Last updated on GujRERA portal: 19 Oct 2026
Source: official GujRERA filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- Nothing verified clear yet
Saved.
Lilleria Signature is a Residential/Group Housing project by LILLERIA DEVELOPERS LLP in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926 on 21 Oct 2019. Possession is promised by 28 Sep 2026. The completion date has moved by 24 months from the original filing. 219 of the 224 units on this registration are recorded sold or booked, and 53 of 63 construction stages are filed complete.
At a glance
Project
- NameLilleria Signature
- TypeResidential/Group Housing
- Location
- RS NO 973
- 974 & 975 TP Scheme 60
- FP NO 86
- Gotri
- Gotri
- Vadodara
- 391101
- Pincode391101
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926
- ReraGenie IDRG-GJ-95857
Builder
- NameLILLERIA DEVELOPERS LLP
- Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
- Other registrations3 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 28 Sep 2026
- Registered on21 Oct 2019
- Promised completion28 Sep 2026
- Revised completionRevised to 28 Sep 2026 (originally 30 Sep 2024)
- Buildings7 building records
- Documents filed48 files
Current status
Figures as on 19 Oct 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower D | - | - | - | 56 | 0 | 56 |
| Tower E | - | - | - | 28 | 0 | 28 |
| Tower F | - | - | - | 28 | 0 | 28 |
| Tower A | - | - | - | 28 | 0 | 28 |
| Tower B | - | - | - | 28 | 0 | 28 |
| Tower B 1 | - | - | - | 28 | 0 | 28 |
| Tower C | - | - | - | 28 | 0 | 28 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building7
As on 19 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
53 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is External plumbing and external plaster, at 99%.
Tower D99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 98% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 95% |
Tower E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 98% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 98% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower B99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 96% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 94% |
Tower B 199%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 95% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 95% |
Tower C99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 99% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 90% |
Progress on shared amenities19
As on 19 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 70% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Fire fighting | Yes | 80% |
| Drinking water facilities | Yes | 96% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 100% |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower B 1 | NA | Rs 4.05 cr | Rs 4.05 cr |
| Tower C | NA | Rs 4.05 cr | Rs 4.05 cr |
| Tower D | NA | Rs 4.05 cr | Rs 4.05 cr |
| Tower A | NA | Rs 3.05 cr | Rs 3.05 cr |
| Tower B | NA | Rs 3.05 cr | Rs 3.05 cr |
| Tower E | NA | Rs 3.05 cr | Rs 3.05 cr |
| Tower F | NA | Rs 3.05 cr | Rs 3.05 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ruchir Sheth |
| Engineer | Vinubhai Patel |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 19 Oct 2026 |
| Engineer's certificate (Form 2) | 19 Oct 2026 |
| Engineer's certificate annexure | 19 Oct 2026 |
| Accountant's certificate (Form 3) | 19 Oct 2026 |
| Site photograph, Tower D | 17 Oct 2026 |
| Site photograph, Tower E | 17 Oct 2026 |
| Site photograph, Tower F | 17 Oct 2026 |
| Site photograph, Tower A | 17 Oct 2026 |
| Site photograph, Tower B | 17 Oct 2026 |
| Site photograph, Tower B 1 | 17 Oct 2026 |
| Site photograph, Tower C | 17 Oct 2026 |
| RERA registration certificate | 21 Oct 2019 |
| Extension certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep Lilleria Signature on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gotri2,900+ in Vadodara
Filed coordinates, straight-line distance. 303 registered projects within 2 km.
Akshar Pavilion
AKSHAR PHC REALCON
LIG SCHEME AT TP 60 FP 127 MMGY
VADODARA MUNICIPAL CORPORATION
PMAY-SEWASI-F.P.75
VADODARA URBAN DEVELOPMENT AUTHORITY
Broadway Pride
ARIHANT INFRASTRUCTURE
Broadway Signature
ARIHANT INFRASTRUCTURE
PAVILION HEIGHTS
PAVILION HEIGHTS
See every Vadodara project, with the district possession charts
Builder: LILLERIA DEVELOPERS LLP
LILLERIA DEVELOPERS LLP has 4 registrations on GujRERA, including Lilleria Aashiana and Lilleria 1038. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if Lilleria Signature is delayed beyond 28 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Lilleria Signature?
The registered promoter entity is LILLERIA DEVELOPERS LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Lilleria Signature?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Lilleria Signature?
The professionals named in the filing: Architect: Ruchir Sheth; Engineer: Vinubhai Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Lilleria Signature?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.