Valid until 28 Sep 2026 Residential/Group Housing project

Lilleria Signature

By LILLERIA DEVELOPERS LLP

RG-GJ-95857 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926 · Last updated on GujRERA portal: 19 Oct 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Sep 2026Possession promisedmoved 24 months from the original
53 of 63Construction stages doneacross 7 buildings; furthest along: External plumbing and external plaster, 99%
5 of 224Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

Lilleria Signature is a Residential/Group Housing project by LILLERIA DEVELOPERS LLP in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926 on 21 Oct 2019. Possession is promised by 28 Sep 2026. The completion date has moved by 24 months from the original filing. 219 of the 224 units on this registration are recorded sold or booked, and 53 of 63 construction stages are filed complete.

At a glance

Project

  • NameLilleria Signature
  • TypeResidential/Group Housing
  • Location
    • RS NO 973
    • 974 & 975 TP Scheme 60
    • FP NO 86
    • Gotri
    • Gotri
    • Vadodara
    • 391101
  • Pincode391101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926
  • ReraGenie IDRG-GJ-95857

Builder

  • NameLILLERIA DEVELOPERS LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations3 more →

Key dates

this monthRegisteredOct 2019First promiseSep 2024Revised toSep 2026

Key facts

Registration and timeline

  • StatusValid until 28 Sep 2026
  • Registered on21 Oct 2019
  • Promised completion28 Sep 2026
  • Revised completionRevised to 28 Sep 2026 (originally 30 Sep 2024)
  • Buildings7 building records
  • Documents filed48 files

Current status

98%219 of 224 units booked
100.0%Of the estimated cost spent so far

Figures as on 19 Oct 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower D---56056
Tower E---28028
Tower F---28028
Tower A---28028
Tower B---28028
Tower B 1---28028
Tower C---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 19 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

53 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is External plumbing and external plaster, at 99%.

Tower D99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
Tower E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower B99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing96%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing94%
Tower B 199%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
Tower C99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing99%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%

Progress on shared amenities19

As on 19 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes70%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes80%
Fire fightingYes80%
Drinking water facilitiesYes96%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,200 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 24.35 cr
Cost incurredRs 24.35 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Tower B 1NARs 4.05 crRs 4.05 cr
Tower CNARs 4.05 crRs 4.05 cr
Tower DNARs 4.05 crRs 4.05 cr
Tower ANARs 3.05 crRs 3.05 cr
Tower BNARs 3.05 crRs 3.05 cr
Tower ENARs 3.05 crRs 3.05 cr
Tower FNARs 3.05 crRs 3.05 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRuchir Sheth
EngineerVinubhai Patel

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX1/110924/290925Applied Aug 2024; approved Sep 2024
PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926Applied Sep 2025; approved Nov 2025

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA06202/A1R/EX2/101125/280926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)19 Oct 2026
Engineer's certificate (Form 2)19 Oct 2026
Engineer's certificate annexure19 Oct 2026
Accountant's certificate (Form 3)19 Oct 2026
Site photograph, Tower D17 Oct 2026
Site photograph, Tower E17 Oct 2026
Site photograph, Tower F17 Oct 2026
Site photograph, Tower A17 Oct 2026
Site photograph, Tower B17 Oct 2026
Site photograph, Tower B 117 Oct 2026
Site photograph, Tower C17 Oct 2026
RERA registration certificate21 Oct 2019
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

98%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 24 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Lilleria Signature on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gotri2,900+ in Vadodara

2 kmLilleria SignatureOther 303Dot size: filed unitsN

Filed coordinates, straight-line distance. 303 registered projects within 2 km.

Builder: LILLERIA DEVELOPERS LLP

LILLERIA DEVELOPERS LLP has 4 registrations on GujRERA, including Lilleria Aashiana and Lilleria 1038. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Lilleria Signature is delayed beyond 28 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Lilleria Signature?

The registered promoter entity is LILLERIA DEVELOPERS LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Lilleria Signature?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Lilleria Signature?

The professionals named in the filing: Architect: Ruchir Sheth; Engineer: Vinubhai Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Lilleria Signature?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Lilleria Signature. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Lilleria Signature to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.