Home / Browse projects / Vadodara, Gujarat / KUNJ PLAZA PHASE-2

Valid until 30 Apr 2028 Residential/Group Housing project

KUNJ PLAZA PHASE-2

By SRJ PROJECTS PRIVATE LIMITED

RG-GJ-70157 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA11971/190623 · Last updated on GujRERA portal: 8 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
5 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 93%
66 of 112Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

KUNJ PLAZA PHASE-2 is a Residential/Group Housing project by SRJ PROJECTS PRIVATE LIMITED in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA11971/190623 on 19 Jun 2023. Possession is promised by 30 Apr 2028. 46 of the 112 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.

At a glance

Project

  • NameKUNJ PLAZA PHASE-2
  • TypeResidential/Group Housing
  • Location
    • Moje Vadodara Kasba
    • Tikka No. B-17/18
    • Moje Vadodara Kasba
    • Tikka No. B-17/18
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA11971/190623
  • ReraGenie IDRG-GJ-70157

Builder

  • NameSRJ PROJECTS PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredJun 2023PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on19 Jun 2023
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed38 files

Current status

41%46 of 112 units booked
21.1%Of the estimated cost spent so far

Figures as on 8 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower I---56056
Tower J---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 8 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 93%.

Tower I47%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth90%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats71%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Tower J85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth90%
Stilt Floor93%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats68%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks86%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing68%

Progress on shared amenities23

As on 8 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes40%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,429 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 20.90 cr
Cost incurredRs 4.40 cr
Spent of the estimate21.05%
BuildingWingEstimatedIncurred
Tower INARs 12.00 crRs 1.25 cr
Tower JNARs 8.90 crRs 3.15 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARShivani Gohil & Associates
EngineerDr.VINUBHAI R. PATEL

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA11971/190623 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)8 Oct 2024
Engineer's certificate annexure8 Oct 2024
RERA registration certificate19 Jun 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

41%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep KUNJ PLAZA PHASE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmKUNJ PLAZA PHASE-2Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 122 registered projects within 2 km.

Builder: SRJ PROJECTS PRIVATE LIMITED

SRJ PROJECTS PRIVATE LIMITED has 1 registration on GujRERA, including KUNJ PLAZA PHASE-2. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if KUNJ PLAZA PHASE-2 is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KUNJ PLAZA PHASE-2?

The registered promoter entity is SRJ PROJECTS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KUNJ PLAZA PHASE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KUNJ PLAZA PHASE-2?

The professionals named in the filing: Architect: ARShivani Gohil & Associates; Engineer: Dr.VINUBHAI R. PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KUNJ PLAZA PHASE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KUNJ PLAZA PHASE-2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KUNJ PLAZA PHASE-2 to a free account