ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / KRISHNA BUNGLOWS

Valid until 31 Dec 2026 Plotted Development project

KRISHNA BUNGLOWS

By JIVRAJHARJIBHAIVASOYA AND OTHERS

RG-GJ-82587 · RERA PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/PAA15015/240325/311226 · Last updated on GujRERA portal: 24 Mar 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
52 of 52Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

KRISHNA BUNGLOWS is a Plotted Development project by JIVRAJHARJIBHAIVASOYA AND OTHERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/PAA15015/240325/311226 on 24 Mar 2025. Possession is promised by 31 Dec 2026. 0 of the 52 units on this registration are recorded sold or booked.

At a glance

Project

  • NameKRISHNA BUNGLOWS
  • TypePlotted Development
  • Location
    • MOJE:- KOSAD
    • BLOCK NO.- 774
    • T.P.S. NO.- 66 (KOSAD-VARIAV)
    • O.P. NO.- 233
    • F.P. NO.- 233
    • TA.- KATARGAM
    • DIST.- SURAT
    • KOSAD
    • Choryasi
    • Surat
    • 394107
  • Pincode394107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/PAA15015/240325/311226
  • ReraGenie IDRG-GJ-82587

Builder

  • NameJIVRAJHARJIBHAIVASOYA AND OTHERS
  • Entity typeOther

Key dates

this monthRegisteredMar 2025PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on24 Mar 2025
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

0%0 of 52 units booked

Figures as on 24 Mar 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OPEN PLOT (TOTAL 52 UNIT)---0052

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 24 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

OPEN PLOT (TOTAL 52 UNIT):

ActivityProgress
Excavation-
Podiums (if any)Not applicable
Plinth-
Stilt Floor-
Slabs of Super Structure-
Internal walls, internal plaster, floorings, doors and windows within flats-
Sanitary fittings within the flats-
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks-
External plumbing and external plaster, elevation, completion of terraces with waterproofing-
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing-

Progress on shared amenities23

As on 24 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes25%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes25%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,161 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParth Jivrajbhai Gabani
EngineerKANTILAL GOPALBHAI PATEL

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORYASI/Surat Municipal Corporation/PAA15015/240325/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate24 Mar 2025
Engineer's certificate (Form 2)4 Mar 2025
Engineer's certificate annexure4 Mar 2025
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

0%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep KRISHNA BUNGLOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KOSAD2,600+ in Surat

2 kmKRISHNA BUNGLOWSOther 96Dot size: filed unitsN

Filed coordinates, straight-line distance. 96 registered projects within 2 km.

Builder: JIVRAJHARJIBHAIVASOYA AND OTHERS

JIVRAJHARJIBHAIVASOYA AND OTHERS has 1 registration on GujRERA, including KRISHNA BUNGLOWS. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if KRISHNA BUNGLOWS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KRISHNA BUNGLOWS?

The registered promoter entity is JIVRAJHARJIBHAIVASOYA AND OTHERS. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KRISHNA BUNGLOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KRISHNA BUNGLOWS?

The professionals named in the filing: Architect: Parth Jivrajbhai Gabani; Engineer: KANTILAL GOPALBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA BUNGLOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA BUNGLOWS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA BUNGLOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.