Home / Browse projects / Surat, Gujarat / OPERA CRYTSAL

Valid until 29 Jun 2026 Mixed Development project

OPERA CRYTSAL

By VISHWAS HITECH INFRAPROJECTS PRIVATE LIMITED

RG-GJ-40613 · RERA PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX3/040825/290626 · Last updated on GujRERA portal: 29 Jul 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Jun 2026Possession promisedmoved 36 months from the original
120 of 126Construction stages doneacross 14 buildings; furthest along: Sanitary fittings within the flats, 14%
172 of 532Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

OPERA CRYTSAL is a Mixed Development project by VISHWAS HITECH INFRAPROJECTS PRIVATE LIMITED in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX3/040825/290626 on 8 Sep 2017. Possession is promised by 29 Jun 2026. The completion date has moved by 36 months from the original filing. 360 of the 532 units on this registration are recorded sold or booked, and 120 of 126 construction stages are filed complete.

At a glance

Project

  • NameOPERA CRYTSAL
  • TypeMixed Development
  • Location
    • TP-36 (VARIAV)
    • B.NO. 1244
    • FP-3/A
    • OP-3
    • VARIAV ROAD
    • SURAT
    • Variav
    • Olpad
    • Surat
    • 394107
  • Pincode394107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX3/040825/290626
  • ReraGenie IDRG-GJ-40613

Builder

  • NameVISHWAS HITECH INFRAPROJECTS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations4 more →

Key dates

this monthRegisteredSep 2017First promiseJun 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusValid until 29 Jun 2026
  • Registered on8 Sep 2017
  • Promised completion29 Jun 2026
  • Revised completionRevised to 29 Jun 2026 (originally 30 Jun 2023)
  • Buildings14 building records
  • Documents filed37 files

Current status

68%360 of 532 units booked
96.0%Of the estimated cost spent so far

Figures as on 29 Jul 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
F1+F2---40040
G1+G2---40040
H1+H2---40040
I1+I2---40040
J1+J2---30030
K1+K2---30030
L1+L2---40040
M1+M2---40040
N1+N2---40040
A1+A2---27936
B1+B2---27936
C1+C2---40040
D1+D2---40040
E1+E2---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building14

As on 29 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

120 of 126 construction stages are filed complete across 14 buildings. The stage furthest along is Sanitary fittings within the flats, at 14%.

F1+F2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G1+G2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
H1+H2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
I1+I2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
J1+J2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
K1+K2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
L1+L2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
M1+M2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
N1+N2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A1+A2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B1+B268%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats14%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C1+C268%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats13%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D1+D2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E1+E2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 29 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes75%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes75%
Storm water drainsYes75%
Landscaping and tree plantingYes75%
Street lightingYes75%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes75%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes75%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,768 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 34.90 cr
Cost incurredRs 33.51 cr
Spent of the estimate96.02%
BuildingWingEstimatedIncurred
I1+I2NARs 3.02 crRs 3.02 cr
D1+D2NARs 2.92 crRs 2.92 cr
C1+C2NARs 2.78 crRs 2.00 cr
F1+F2NARs 2.69 crRs 2.69 cr
G1+G2NARs 2.69 crRs 2.69 cr
H1+H2NARs 2.69 crRs 2.69 cr
K1+K2NARs 2.49 crRs 2.49 cr
L1+L2NARs 2.37 crRs 2.37 cr
M1+M2NARs 2.37 crRs 2.37 cr
N1+N2NARs 2.37 crRs 2.37 cr
J1+J2NARs 2.30 crRs 2.30 cr
A1+A2NARs 2.11 crRs 2.11 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYAGNIK R JETANI
EngineerJALIL SHEIKH

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX1/021123Applied Jun 2023; approved Nov 2023
PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX2/290824/290625Applied Jun 2024; approved Aug 2024
PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX3/040825/290626Applied Jun 2025; approved Aug 2025

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/OLPAD/SUDA/MAA00107/A1M/EX3/040825/290626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)29 Jul 2025
Architect's certificate (Form 1)14 Jul 2025
Engineer's certificate (Form 2)14 Jul 2025
Engineer's certificate annexure14 Jul 2025
RERA registration certificate8 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

68%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 36 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep OPERA CRYTSAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Variav2,600+ in Surat

2 kmOPERA CRYTSALOther 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 98 registered projects within 2 km.

Builder: VISHWAS HITECH INFRAPROJECTS PRIVATE LIMITED

VISHWAS HITECH INFRAPROJECTS PRIVATE LIMITED has 5 registrations on GujRERA, including OPERA CRYTSAL and OPERA PRINCE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if OPERA CRYTSAL is delayed beyond 29 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OPERA CRYTSAL?

The registered promoter entity is VISHWAS HITECH INFRAPROJECTS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OPERA CRYTSAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OPERA CRYTSAL?

The professionals named in the filing: Architect: YAGNIK R JETANI; Engineer: JALIL SHEIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OPERA CRYTSAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OPERA CRYTSAL. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OPERA CRYTSAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.