Registration approved No litigation declared Plotted Development project

Krishi Dhama Layout Phase-3

By KARIYAPPA

RG-KA-34436 · RERA PRM/KA/RERA/1250/301/PR/060923/006243 · Last updated on RERA Karnataka portal: 1 Sep 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2022Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 129 documents Report an error

Krishi Dhama Layout Phase-3 is a Plotted Development project by KARIYAPPA in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/301/PR/060923/006243 on 6 Sep 2023. Possession is promised by 29 Jun 2022.

At a glance

Project

  • NameKrishi Dhama Layout Phase-3
  • TypePlotted Development
  • Location
    • Doddaballapura
    • Bengaluru Rural
    • 561203
  • Pincode561203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/301/PR/060923/006243
  • ReraGenie IDRG-KA-34436

Builder

  • NameKARIYAPPA
  • Entity typeProprietorship
  • Authorized SignatoryKARIYAPPA
  • Other registrations1 more →

Key dates

Registered
6 Sep 2023
Promised
29 Jun 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Sep 2023
  • Promised completion29 Jun 2022
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed129 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
Kariyappa S/o.Late.Chikkanna--
Kariyappa S/o.Late.Chikkanna--
Kariyappa S/o.Late.Chikkanna--
Kariyappa S/o.Late.Chikkanna--
Kariyappa S/o.Late.Chikkanna--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.80 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 2.80 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerVishnu Kumar
Chartered AccountantVikas Y

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed129

As listed on the registration, under the names the promoter filed them with; the newest 80 of 129 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/301/PR/060923/006243 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA_Reliquement Deed_KDL-3File: 2 CA_Reliquement Deed_KDL-3.pdf1 Sep 2023
CLARIFICATION ON CDP MASTER EXTRACTFile: 3 CLARIFICATION ON CDP MASTER EXTRACT.pdf1 Sep 2023
CLARIFICATION ON WATER NOCFile: 4 CLARIFICATION ON WATER NOC.pdf1 Sep 2023
BESCOM_NOC_KDL-3File: 5 BESCOM_NOC_KDL-3.pdf1 Sep 2023
Local gram Panchayat_NOC_KDL-3File: 6 Local gram Panchayat_NOC_KDL-3.pdf1 Sep 2023
Civil Work Completion Certificate_KDL-3File: 7 Civil Work Completion Certificate_KDL-3.pdf1 Sep 2023
CLARIFICATION ON Sy No 16-6File: 1 CLARIFICATION ON Sy No 16-6.pdf1 Sep 2023
chartered accountant certificate _Form-1File: CA Certificate_Form-1_KDL-3.pdf11 Aug 2023
Bank account Details & name ClarificationFile: RERA Bank Account Bassbook & Clarification_KDL_3.pdf11 Aug 2023
sources of funds_Supporting DocumentsFile: KDL-3_Source of Funds_Supporting Documents.pdf11 Aug 2023
NOC from UASE SocietyFile: KDL_3_UEHCS_NOC.pdf11 Aug 2023
Relinquishment deedFile: Relinqueshment Deed_KDL_Phase 3.pdf11 Aug 2023
horticulture department NOC for park developmentFile: Park_NOC_KDL-3.pdf11 Aug 2023
Civil Work Completion certificate by AuthorityFile: Civil Work Completion Certificate_KDL-3.pdf11 Aug 2023
CDP map showing the proposed site.File: CDP & Google map_Demarked_KDL_3.pdf11 Aug 2023
Google map showing the proposed site.File: Google Map_KDL-3_Demarked.pdf11 Aug 2023
village map showing the proposed site.File: Village Map_KDL-3_Demarked.pdf11 Aug 2023
BESCOM_NOCFile: BESCOM_NOC & Service Certificate_KDL-3.pdf11 Aug 2023
Local Gram Panchatchty_Water Supply_NOCFile: Local gram Panchayat_NOC_KDL-3.pdf11 Aug 2023
Sold & unsold Units_Self DeclearationFile: SOLD & UNSOLD UNITS Self Declaration_KDL-3.pdf11 Aug 2023
STP DrawingFile: STP Drawing.pdf11 Aug 2023
KSPCB_NOCFile: KSPCB_NOC.pdf11 Aug 2023
100% Final Approved Layout PlanFile: 100% Final Release Layout Plan.jpg11 Aug 2023
100% Released Approval LetterFile: Layout Plan Final Approval Letter_KDL_Phase 3.pdf11 Aug 2023
Hissa & Podi DocumentsFile: Hissa podi_KDL-3.pdf11 Aug 2023
RTC & MR of All Sy noFile: RTC & MR_All Sy_KDL-3.pdf11 Aug 2023
Title Deed & Documents of all Sy noFile: Title Deed_All Sy_KDL-3.pdf11 Aug 2023
Form 2_Architect CertificateFile: Form 2_Krishi Dhama Layout-Phase3_Architect.pdf11 Aug 2023
Form 5_Architect CertificateFile: Form 5_Krishi Dhama Layout-Phase 3_Architect.pdf11 Aug 2023
Form 3_Engineer CertificateFile: Form 3_KDL-3_Engineer.pdf11 Aug 2023
Form 6_Engineer CertificateFile: Form 6_KDL-3_Engineer.pdf11 Aug 2023
Clarification on KSPCB NOCFile: Clarification on KSPCB NOC.pdf11 Aug 2023
NPA_ZONING_REGULATION_2031File: NPA_ZONING_REGULATION_2031.pdf11 Aug 2023
Engineer Cost Estimation BreakupFile: Engineer Cost Estimation Breakup.pdf11 Aug 2023
KDL-3_Query ResponseFile: KDL-3_Query Response.pdf11 Aug 2023
RTC, survey 15/4-
Mutation, survey 15/4-
Encumbrance Certificate, survey 15/4-
Conversion/Alienation Order, survey 15/4-
Sale/Title/Gift Deed, survey 15/4-
Khatha, survey 15/4-
RTC, survey 16/1-
Mutation, survey 16/1-
Encumbrance Certificate, survey 16/1-
Conversion/Alienation Order, survey 16/1-
Sale/Title/Gift Deed, survey 16/1-
Khatha, survey 16/1-
RTC, survey 16/5-
Mutation, survey 16/5-
Encumbrance Certificate, survey 16/5-
Conversion/Alienation Order, survey 16/5-
Sale/Title/Gift Deed, survey 16/5-
Khatha, survey 16/5-
RTC, survey 17/5-
Mutation, survey 17/5-
Encumbrance Certificate, survey 17/5-
Conversion/Alienation Order, survey 17/5-
Sale/Title/Gift Deed, survey 17/5-
Khatha, survey 17/5-
RTC, survey 18/1-
Mutation, survey 18/1-
Encumbrance Certificate, survey 18/1-
Conversion/Alienation Order, survey 18/1-
Sale/Title/Gift Deed, survey 18/1-
Khatha, survey 18/1-
Certificate issued by CA Form 1File: CA Certificate_Form-1_KDL-3.pdf-
Certificate issued by Engineer Form 3File: Form 3_KDL-3_Engineer.pdf-
Project Chartered Accountant-
Project Engineer-
AffidavitFile: Non_Litigation_Affidivat_KDL_3.pdf-
Certificate from Chartered AccountFile: CA Certificate_Form-1_KDL-3.pdf-
Certificate issued by ArchitectFile: Form 2_Krishi Dhama Layout-Phase3_Architect.pdf-
Balance Sheet 2021 - 2022File: Kariyappa_ITR_22-23.pdf-
Balance Sheet 2020 - 2021File: Kariyappa_ITR_21-22.pdf-
Balance Sheet 2019 - 2020File: Kariyappa_ITR_20-21.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Kariyappa_ITR_22-23.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Kariyappa_ITR_21-22.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Kariyappa_ITR_20-21.pdf-
Director's Report 2021 - 2022File: Kariyappa_ITR_22-23.pdf-
Director's Report 2020 - 2021File: Kariyappa_ITR_21-22.pdf-

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Krishi Dhama Layout Phase-3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmKrishi Dhama Layout PhasOther 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: KARIYAPPA

KARIYAPPA has 2 registrations on RERA Karnataka, including Krishi Dhama Layout Phase-3 and SHEK RAHIMAN NAGAR. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Krishi Dhama Layout Phase-3 is delayed beyond 29 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Krishi Dhama Layout Phase-3?

The registered promoter entity is KARIYAPPA, a proprietorship as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Krishi Dhama Layout Phase-3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Krishi Dhama Layout Phase-3?

The professionals named in the filing: Engineer: Vishnu Kumar; Chartered Accountant: Vikas Y. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Krishi Dhama Layout Phase-3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Krishi Dhama Layout Phase-3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Krishi Dhama Layout Phase-3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.