Keshav Park
RG-GJ-61156 · RERA PR/GJ/VADODARA/KARJAN/Others/RAA07243/020720 · Last updated on GujRERA portal: 24 Oct 2024
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
Keshav Park is a Residential/Group Housing project by KESHAV ENTERPRISE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/KARJAN/Others/RAA07243/020720 on 2 Jul 2020. Possession is promised by 31 Dec 2025. 110 of the 112 units on this registration are recorded sold or booked, and 56 of 72 construction stages are filed complete.
At a glance
Project
- NameKeshav Park
- TypeResidential/Group Housing
- Location
- Keshav Park
- Opp. APMA
- Nr. Essar Petrol Pump
- Nava Bazar
- Karjan
- Karjan
- Vadodara
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/KARJAN/Others/RAA07243/020720
- ReraGenie IDRG-GJ-61156
Builder
- NameKESHAV ENTERPRISE
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Dec 2025
- Registered on2 Jul 2020
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings8 building records
- Documents filed48 files
Current status
Figures as on 24 Oct 2024, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Unit 55 to 68 | - | - | - | 14 | 0 | 14 |
| Unit 69 and 70 | - | - | - | 2 | 0 | 2 |
| Unit 71 to 84 | - | - | - | 14 | 0 | 14 |
| Unit 85 and 86 | - | - | - | 2 | 0 | 2 |
| Unit 87 to 112 | - | - | - | 26 | 0 | 26 |
| Unit 1 to 24 | - | - | - | 25 | 0 | 25 |
| Unit 25 to 53 | - | - | - | 28 | 0 | 28 |
| Unit 54 | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building8
As on 24 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
56 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is Plinth, at 0%.
Unit 55 to 6878%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 69 and 7078%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 71 to 8478%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 85 and 8678%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 87 to 11278%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 1 to 2478%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 25 to 5378%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Unit 5478%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 24 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | No | Not applicable |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 100% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Unit 25 to 53 | NA | Rs 1.27 cr | Rs 1.27 cr |
| Unit 1 to 24 | NA | Rs 1.17 cr | Rs 1.17 cr |
| Unit 55 to 68 | NA | Rs 52.38 lakh | Rs 52.38 lakh |
| Unit 71 to 84 | NA | Rs 52.38 lakh | Rs 52.38 lakh |
| Unit 85 and 86 | NA | Rs 10.18 lakh | Rs 10.18 lakh |
| Unit 69 and 70 | NA | Rs 10.00 lakh | Rs 10.00 lakh |
| Unit 87 to 112 | NA | Rs 9.43 lakh | Rs 9.43 lakh |
| Unit 54 | NA | Rs 5.46 lakh | Rs 5.46 lakh |
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/KARJAN/Others/RAA07243/020720 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 24 Oct 2024 |
| Engineer's certificate (Form 2) | 24 Oct 2024 |
| Engineer's certificate annexure | 24 Oct 2024 |
| Accountant's certificate (Form 3) | 24 Oct 2024 |
| Site photograph, Unit 55 to 68 | 23 Oct 2024 |
| Site photograph, Unit 69 and 70 | 23 Oct 2024 |
| Site photograph, Unit 71 to 84 | 23 Oct 2024 |
| Site photograph, Unit 85 and 86 | 23 Oct 2024 |
| Site photograph, Unit 87 to 112 | 23 Oct 2024 |
| Site photograph, Unit 1 to 24 | 23 Oct 2024 |
| Site photograph, Unit 25 to 53 | 23 Oct 2024 |
| Site photograph, Unit 54 | 23 Oct 2024 |
| RERA registration certificate | 2 Jul 2020 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep Keshav Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Karjan2,900+ in Vadodara
Filed coordinates, straight-line distance. 38 registered projects within 2 km.
PMAY, EWS, TP 28, FP 152/1+152/2, R.S.no.585/1
VADODARA MUNICIPAL CORPORATION
AGORA CITY CENTER
MANAV INFRASTRUCTURE PRIVATE LIMITED
49 shops + 1560 EWS - II at Gorwa, Phase 5
GUJARAT HOUSING BOARD
PMAY-KHATAMBA
VADODARA URBAN DEVELOPMENT AUTHORITY
Akshar Pavilion
AKSHAR PHC REALCON
NAZARBAUG PALACE PHASE-1
ONS BUILDTECH LLP
See every Vadodara project, with the district possession charts
Builder: KESHAV ENTERPRISE
KESHAV ENTERPRISE has 1 registration on GujRERA, including Keshav Park. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if Keshav Park is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Keshav Park?
The registered promoter entity is KESHAV ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Keshav Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Keshav Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback