Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
JAY PARSHWA SIGNATURE is a Residential/Group Housing project by RAJESH KUMAR GHORAWATH in Chikkamagaluru, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1255/323/PR/180521/001770 on 21 May 2018. Possession is promised by 31 Dec 2022. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameJAY PARSHWA SIGNATURE
- TypeResidential/Group Housing
- Location
- Chikkamagaluru
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1255/323/PR/180521/001770
- ReraGenie IDRG-KA-17203
Builder
- NameRAJESH KUMAR GHORAWATH
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 May 2018
- Promised completion31 Dec 2022
- Revised completionRevised to 31 Dec 2022 (originally 31 Mar 2022)
- Buildings1 building record
- Documents filed45 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ARYADEEP SIGNATURE 1 | - | - | - | 35 | 0 | 35 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | No | Not applicable |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | No | Not applicable |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARVIND LALWANI |
| Engineer | ARVIND LALWANI |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed45
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1255/323/PR/180521/001770 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| scan0129 | - |
| CHIKKAMAGALORE BLUE PRINT | - |
| CHIKKAMAGALORE BLUE PRINT | - |
| Document1 | - |
| Document1 | - |
| Sale Deed | - |
| CHIKKAMAGALORE BLUE PRINT | - |
| CHIKKAMAGALORE BLUE PRINT | - |
| Document1 | - |
| aryadeep (1) | - |
| Untitled | - |
| scan0131 | - |
| scan0130 | - |
| Document1 | - |
| CHIKKAMAGALORE BLUE PRINT | - |
| CHIKKAMAGALORE BLUE PRINT | - |
| Document1 | - |
| Balance Sheet 2016 - 2017File: A 170_Balance Sheet_AY 17-18.pdf | - |
| Balance Sheet 2015 - 2016File: A170Scan01.pdf | - |
| Balance Sheet 2014 - 2015File: bs.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: A 170_Prpofit and Loss Account_AY 17-18.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: A170Scan01.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: bs.pdf | - |
| Director's Report 2016 - 2017File: A 170_Audit Report_AY 17-18.pdf | - |
| Director's Report 2015 - 2016File: A170Scan01.pdf | - |
| Director's Report 2014 - 2015File: bs.pdf | - |
| Cash Flow Statement 2016 - 2017File: A 170_Balance Sheet_AY 17-18.pdf | - |
| Cash Flow Statement 2015 - 2016File: A170Scan01.pdf | - |
| Auditor's Report 2016 - 2017File: A 170_Audit Report_AY 17-18.pdf | - |
| Auditor's Report 2015 - 2016File: A170Scan01.pdf | - |
| Auditor's Report 2014 - 2015File: bs.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ARYADEEP INFRASTRUCTURE PRIVATE LIMITED_05-Nov-2017_289611741.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ARYADEEP INFRASTRUCTURE PRIVATE LIMITED_11-Mar-2017_657111961.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ARYADEEP INFRASTRUCTURE PRIVATE LIMITED_11-Mar-2017_656788381.pdf | - |
| scan0133 | - |
| Prospectus/BrochureFile: Brochur_ARYADEEP SIGNATURE.pdf | - |
| Advertisement Copy 1File: Advertisement_ARYADEEP SIGNATURE.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1255_323_PR_180521_001770.xlsx | - |
| Loan raised documentFile: Form-4 CC.pdf | - |
| Stability CertificateFile: Stability Certificate.jpg | - |
| Occupancy CertificateFile: Completion Certificate.jpg | - |
| Architect certificate for having completed the work(in format no 5)File: Form 5 Architect Certificate Closure.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form-4 CC.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Closure Affidavit.pdf | - |
| Form 6 Engineer Certificate ClosureFile: Form 6 Engineer Certificate Closure.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Chikkamagaluru
Computed across the 36 Chikkamagaluru projects on ReraGenie, from their own filings.
Keep JAY PARSHWA SIGNATURE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chikkamagaluru36 in Chikkamagaluru
VANI VILASA
TUNGABHADRA DEVELOPERS
SUDHARMA APARTMENTS
NATESH H.S & K.M CHANDRAMOHAN
The Grand Retreat
Manjunath Balakrishna
Sharada Enclave
Injith Developers
Construction of PKGBY - AHP 15 Dus
RGHCL
BANYAN BOULEVARD
M/s. BANYAN ENTERPRISES
See every Chikkamagaluru project, with the district possession charts
Builder: RAJESH KUMAR GHORAWATH
RAJESH KUMAR GHORAWATH has 1 registration on RERA Karnataka, including JAY PARSHWA SIGNATURE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Chikkamagaluru district page.
Frequently asked questions
What are my rights if JAY PARSHWA SIGNATURE is delayed beyond 31 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of JAY PARSHWA SIGNATURE?
The registered promoter entity is RAJESH KUMAR GHORAWATH. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in JAY PARSHWA SIGNATURE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at JAY PARSHWA SIGNATURE?
The professionals named in the filing: Architect: ARVIND LALWANI; Engineer: ARVIND LALWANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JAY PARSHWA SIGNATURE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.