Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
May 2028Possession promisedno revision filed
5 of 18Construction stages donefurthest along: RCC or MS Framed structure, 98%
0 of 154Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 167 documents Report an error

ISLE OF TREES is a Residential/Group Housing project by Happiness Harmony Property Developers Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/150724/006941 on 15 Jul 2024. Possession is promised by 29 May 2028. 154 of the 154 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameISLE OF TREES
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560077
  • Pincode560077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/150724/006941
  • ReraGenie IDRG-KA-54832

Builder

  • NameHappiness Harmony Property Developers Private Limited
  • Entity typeCompany
  • CINU70200TN2018PTC121367
  • GSTIN29AAECH4663H1ZC
  • Authorized SignatoryMr. Vergum Narsing Rao
  • President & CEOMr. Sriram Subramanian Iyer
  • DirectorsMr. Sriram Subramanian Iyer, V R Karunakar Reddy
  • Project HeadMr. MAGESH

Key dates

this monthRegisteredJul 2024PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Jul 2024
  • Promised completion29 May 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed167 files

Current status

100%154 of 154 units booked
70.4%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER (AB)---1040104
TOWER (C)---50050

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 98%.

Building: 68% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure98%
Masonry Construction80%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc70%
Basic work of Water supply, Sanitary and Electrification85%
Dadoing, Skirting, Flooring, Tiles work (All types)60%
Railing and Grill fixing45%
Electrification, Water supply and Sanitary Finishing25%
Painting40%
Fire prevention and fire fighting fitting and fixture with network70%
Weather Proof work(tile,concrete)25%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work40%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities50

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes30%
Sewage and Drainage SystemYes20%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes70%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes30%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
Double height LobbyNoNot applicable
Kids poolNoNot applicable
Squash courtNoNot applicable
Kids Play areaNoNot applicable
Massage SpaceNoNot applicable
Unisex salon spaceNoNot applicable
Multi purpose HallYes0%
Outdoor AmenitiesYes0%
Other AmenitiesYes0%
StaircasesYes80%
LiftsYes60%
Corridor/LobbiesYes45%
Fire escapesYes45%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallYes60%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes60%
Common storage spacesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandah, Basement and Ground Floor LobbyYes0%

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,994 sq m
Named landowners3
LandownerVillageDistrict
M/s. Happiness Harmony Property Developers Private Limited--
M/s. Happiness Harmony Property Developers Private Limited--
M/s. Happiness Harmony Property Developers Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 184.71 cr
Cost incurredRs 130.02 cr
Spent of the estimate70.39%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 120.45 crRs 87.00 cr
Administrative CostsRs 30.68 cr-
Payment of taxesRs 29.11 crRs 14.11 cr
On-site expenditure-Consultants FeesRs 2.34 crRs 28.91 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 2.13 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Vivek V. Shankar
EngineerVishnu Kumar
Chartered AccountantGopalan Muralidharan

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00917/2026-Happiness Harmony Property Developers Private Limited29/07/2026

Documents filed167

As listed on the registration, under the names the promoter filed them with; the newest 80 of 167 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/150724/006941 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate IOT- Karn RERA Form - 4 - Q2 FY26-27.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 30-09-2026.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 30-09-2026.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 IOT - CA Certificate.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 13-07-2026.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 30-06-2026.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 RERA - Q-4 25-26 Isle of Trees.pdf5 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 17-04-2026.pdf5 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 31-03-2026.pdf5 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: IOT - RERA Form 4 - Q3 FY26.pdf26 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 31-12-2025.pdf26 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 31-12-2025.pdf26 Jan 2026
Auditor Report FY 2022-23File: 1 Auditor Report FY 2022-23.pdf26 Jun 2024
Auditor Report FY 2021-22File: 2 Auditor Report FY 2021-22.pdf26 Jun 2024
Auditor Report FY 2020-21File: 3 Auditor Report FY 2020-21.pdf26 Jun 2024
Clarification on CapitalFile: 4 Clarification on Capital.pdf26 Jun 2024
Balance sheet FY 2022-23File: 5 Balance sheet FY 2022-23.pdf26 Jun 2024
Profit and Loss FY 2022-23File: 6 Profit and Loss FY 2022-23.pdf26 Jun 2024
Balance sheet FY 2021-22File: 7 Balance sheet FY 2021-22.pdf26 Jun 2024
Profit and loss FY 2021-22File: 8 Profit and loss FY 2021-22.pdf26 Jun 2024
Financials BL P&L and Audit Report with UDIN FY 2020-21File: 9 Financials BL P&L and Audit Report with UDIN FY 2020-21.pdf26 Jun 2024
Happiness Clarification on Single Plot and OrderFile: 1 Happiness Clarification on Single Plot and Order.pdf26 Jun 2024
Happiness Clarification on CCFile: 2 Happiness Clarification on CC.pdf26 Jun 2024
Happiness Clarification on Relnq DeedFile: 3 Happiness Clarification on Relnq Deed.pdf26 Jun 2024
Zonal Regulation 2015File: 4 Zonal Regulation 2015.pdf26 Jun 2024
Ranchenahalli Guidelines valueFile: 5 Ranchenahalli Guidelines value.pdf26 Jun 2024
Amenities and Common Area detailsFile: 6 Amenities and Common Area details.pdf26 Jun 2024
Proforma Agreement of SaleFile: 7 Proforma Agreement of Sale.pdf26 Jun 2024
Legal OpinionFile: 8 Legal Opinion.pdf26 Jun 2024
HHPDPL Source of funds letter with supporting docsFile: 10 HHPDPL Source of funds letter with supporting docs.pdf26 Jun 2024
RTC, survey 85/2-
Mutation, survey 85/2-
Encumbrance Certificate, survey 85/2-
Conversion/Alienation Order, survey 85/2-
Sale/Title/Gift Deed, survey 85/2-
Khatha, survey 85/2-
RTC, survey 85/3B-
Mutation, survey 85/3B-
Encumbrance Certificate, survey 85/3B-
Conversion/Alienation Order, survey 85/3B-
Sale/Title/Gift Deed, survey 85/3B-
Khatha, survey 85/3B-
RTC, survey 85/4-
Mutation, survey 85/4-
Encumbrance Certificate, survey 85/4-
Conversion/Alienation Order, survey 85/4-
Sale/Title/Gift Deed, survey 85/4-
Khatha, survey 85/4-
Registration CertificateFile: Certificate of Incorporation_HHPDPL.pdf-
Memorandum of AssociationFile: MOA.pdf-
Article of AssociationFile: AOA.pdf-
Organization StructureFile: Org chart.pdf-
Certificate issued by CA Form 1File: Form - 1 CA Certificate RAC.pdf-
Certificate issued by Architect Form 2File: FORM-2 ARCHITECT CERTIFICATE.pdf-
Certificate issued by Engineer Form 3File: FORM-3 ENGINEER CERTIFICATE.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation affidavit.pdf-
Certificate from Chartered AccountFile: Form - 1 CA Certificate RAC.pdf-
Balance Sheet 2022 - 2023File: Balance sheet FY 2022-23.pdf-
Balance Sheet 2021 - 2022File: Balance sheet FY 2021-22.pdf-
Balance Sheet 2020 - 2021File: Happiness FY 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss FY 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and loss FY 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Happiness FY 2020-21.pdf-
Director's Report 2022 - 2023File: Directors Report FY 2022-23.pdf-
Director's Report 2021 - 2022File: Directors Report FY 2021-22.pdf-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ISLE OF TREES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmISLE OF TREESOther 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: Happiness Harmony Property Developers Private Limited

Happiness Harmony Property Developers Private Limited has 1 registration on RERA Karnataka, including ISLE OF TREES. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ISLE OF TREES is delayed beyond 29 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ISLE OF TREES?

The registered promoter entity is Happiness Harmony Property Developers Private Limited, a company as per the filing. Its CIN U70200TN2018PTC121367 and GSTIN 29AAECH4663H1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ISLE OF TREES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ISLE OF TREES?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ISLE OF TREES?

The professionals named in the filing: Architect: Mr. Vivek V. Shankar; Engineer: Vishnu Kumar; Chartered Accountant: Gopalan Muralidharan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ISLE OF TREES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ISLE OF TREES. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ISLE OF TREES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.