Red flags
- 1 complaint at RERA Karnataka
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
Saved.
ISLE OF TREES is a Residential/Group Housing project by Happiness Harmony Property Developers Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/150724/006941 on 15 Jul 2024. Possession is promised by 29 May 2028. 154 of the 154 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameISLE OF TREES
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560077
- Pincode560077
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/150724/006941
- ReraGenie IDRG-KA-54832
Builder
- NameHappiness Harmony Property Developers Private Limited
- Entity typeCompany
- CINU70200TN2018PTC121367
- GSTIN29AAECH4663H1ZC
- Authorized SignatoryMr. Vergum Narsing Rao
- President & CEOMr. Sriram Subramanian Iyer
- DirectorsMr. Sriram Subramanian Iyer, V R Karunakar Reddy
- Project HeadMr. MAGESH
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Jul 2024
- Promised completion29 May 2028
- Revised completionNone
- Buildings2 building records
- Documents filed167 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER (AB) | - | - | - | 104 | 0 | 104 |
| TOWER (C) | - | - | - | 50 | 0 | 50 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 98%.
Building: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 98% |
| Masonry Construction | 80% |
| Plastering inside , outside & Ceiling | 80% |
| Joinery: Doors, Windows, Ventilators etc | 70% |
| Basic work of Water supply, Sanitary and Electrification | 85% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 60% |
| Railing and Grill fixing | 45% |
| Electrification, Water supply and Sanitary Finishing | 25% |
| Painting | 40% |
| Fire prevention and fire fighting fitting and fixture with network | 70% |
| Weather Proof work(tile,concrete) | 25% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 40% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities50
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 30% |
| Sewage and Drainage System | Yes | 20% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 70% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 30% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Double height Lobby | No | Not applicable |
| Kids pool | No | Not applicable |
| Squash court | No | Not applicable |
| Kids Play area | No | Not applicable |
| Massage Space | No | Not applicable |
| Unisex salon space | No | Not applicable |
| Multi purpose Hall | Yes | 0% |
| Outdoor Amenities | Yes | 0% |
| Other Amenities | Yes | 0% |
| Staircases | Yes | 80% |
| Lifts | Yes | 60% |
| Corridor/Lobbies | Yes | 45% |
| Fire escapes | Yes | 45% |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 60% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 60% |
| Common storage spaces | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah, Basement and Ground Floor Lobby | Yes | 0% |
Land and ownership3
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/s. Happiness Harmony Property Developers Private Limited | - | - |
| M/s. Happiness Harmony Property Developers Private Limited | - | - |
| M/s. Happiness Harmony Property Developers Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 120.45 cr | Rs 87.00 cr |
| Administrative Costs | Rs 30.68 cr | - |
| Payment of taxes | Rs 29.11 cr | Rs 14.11 cr |
| On-site expenditure-Consultants Fees | Rs 2.34 cr | Rs 28.91 cr |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 2.13 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. Vivek V. Shankar |
| Engineer | Vishnu Kumar |
| Chartered Accountant | Gopalan Muralidharan |
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00917/2026 | - | Happiness Harmony Property Developers Private Limited | 29/07/2026 |
Documents filed167
As listed on the registration, under the names the promoter filed them with; the newest 80 of 167 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/150724/006941 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate IOT- Karn RERA Form - 4 - Q2 FY26-27.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 30-09-2026.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 30-09-2026.pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 IOT - CA Certificate.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 13-07-2026.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 30-06-2026.pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 RERA - Q-4 25-26 Isle of Trees.pdf | 5 May 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 17-04-2026.pdf | 5 May 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 31-03-2026.pdf | 5 May 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: IOT - RERA Form 4 - Q3 FY26.pdf | 26 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 ISLE OF TREES - 31-12-2025.pdf | 26 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ISLE OF TREES 31-12-2025.pdf | 26 Jan 2026 |
| Auditor Report FY 2022-23File: 1 Auditor Report FY 2022-23.pdf | 26 Jun 2024 |
| Auditor Report FY 2021-22File: 2 Auditor Report FY 2021-22.pdf | 26 Jun 2024 |
| Auditor Report FY 2020-21File: 3 Auditor Report FY 2020-21.pdf | 26 Jun 2024 |
| Clarification on CapitalFile: 4 Clarification on Capital.pdf | 26 Jun 2024 |
| Balance sheet FY 2022-23File: 5 Balance sheet FY 2022-23.pdf | 26 Jun 2024 |
| Profit and Loss FY 2022-23File: 6 Profit and Loss FY 2022-23.pdf | 26 Jun 2024 |
| Balance sheet FY 2021-22File: 7 Balance sheet FY 2021-22.pdf | 26 Jun 2024 |
| Profit and loss FY 2021-22File: 8 Profit and loss FY 2021-22.pdf | 26 Jun 2024 |
| Financials BL P&L and Audit Report with UDIN FY 2020-21File: 9 Financials BL P&L and Audit Report with UDIN FY 2020-21.pdf | 26 Jun 2024 |
| Happiness Clarification on Single Plot and OrderFile: 1 Happiness Clarification on Single Plot and Order.pdf | 26 Jun 2024 |
| Happiness Clarification on CCFile: 2 Happiness Clarification on CC.pdf | 26 Jun 2024 |
| Happiness Clarification on Relnq DeedFile: 3 Happiness Clarification on Relnq Deed.pdf | 26 Jun 2024 |
| Zonal Regulation 2015File: 4 Zonal Regulation 2015.pdf | 26 Jun 2024 |
| Ranchenahalli Guidelines valueFile: 5 Ranchenahalli Guidelines value.pdf | 26 Jun 2024 |
| Amenities and Common Area detailsFile: 6 Amenities and Common Area details.pdf | 26 Jun 2024 |
| Proforma Agreement of SaleFile: 7 Proforma Agreement of Sale.pdf | 26 Jun 2024 |
| Legal OpinionFile: 8 Legal Opinion.pdf | 26 Jun 2024 |
| HHPDPL Source of funds letter with supporting docsFile: 10 HHPDPL Source of funds letter with supporting docs.pdf | 26 Jun 2024 |
| RTC, survey 85/2 | - |
| Mutation, survey 85/2 | - |
| Encumbrance Certificate, survey 85/2 | - |
| Conversion/Alienation Order, survey 85/2 | - |
| Sale/Title/Gift Deed, survey 85/2 | - |
| Khatha, survey 85/2 | - |
| RTC, survey 85/3B | - |
| Mutation, survey 85/3B | - |
| Encumbrance Certificate, survey 85/3B | - |
| Conversion/Alienation Order, survey 85/3B | - |
| Sale/Title/Gift Deed, survey 85/3B | - |
| Khatha, survey 85/3B | - |
| RTC, survey 85/4 | - |
| Mutation, survey 85/4 | - |
| Encumbrance Certificate, survey 85/4 | - |
| Conversion/Alienation Order, survey 85/4 | - |
| Sale/Title/Gift Deed, survey 85/4 | - |
| Khatha, survey 85/4 | - |
| Registration CertificateFile: Certificate of Incorporation_HHPDPL.pdf | - |
| Memorandum of AssociationFile: MOA.pdf | - |
| Article of AssociationFile: AOA.pdf | - |
| Organization StructureFile: Org chart.pdf | - |
| Certificate issued by CA Form 1File: Form - 1 CA Certificate RAC.pdf | - |
| Certificate issued by Architect Form 2File: FORM-2 ARCHITECT CERTIFICATE.pdf | - |
| Certificate issued by Engineer Form 3File: FORM-3 ENGINEER CERTIFICATE.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non litigation affidavit.pdf | - |
| Certificate from Chartered AccountFile: Form - 1 CA Certificate RAC.pdf | - |
| Balance Sheet 2022 - 2023File: Balance sheet FY 2022-23.pdf | - |
| Balance Sheet 2021 - 2022File: Balance sheet FY 2021-22.pdf | - |
| Balance Sheet 2020 - 2021File: Happiness FY 2020-21.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss FY 2022-23.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit and loss FY 2021-22.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Happiness FY 2020-21.pdf | - |
| Director's Report 2022 - 2023File: Directors Report FY 2022-23.pdf | - |
| Director's Report 2021 - 2022File: Directors Report FY 2021-22.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ISLE OF TREES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 42 registered projects within 2 km.
NAVA VRUKSHA
NAVA JYOTHI SHELTERS PRIVATE LIMITED
POULOMI FLORIQUE
POULOMI FLORIQUE LLP
Mirabelle
G Corp Homes Private Limited
DNR PARKLINK PHASE 2
DNR CORPORATION PVT LTD
NAVA SKANDA BELLAVITA
NAVA SKANDA PROJECTS
DNR PARKLINK PHASE 1
DNR CORPORATION PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: Happiness Harmony Property Developers Private Limited
Happiness Harmony Property Developers Private Limited has 1 registration on RERA Karnataka, including ISLE OF TREES. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ISLE OF TREES is delayed beyond 29 May 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ISLE OF TREES?
The registered promoter entity is Happiness Harmony Property Developers Private Limited, a company as per the filing. Its CIN U70200TN2018PTC121367 and GSTIN 29AAECH4663H1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ISLE OF TREES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ISLE OF TREES?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at ISLE OF TREES?
The professionals named in the filing: Architect: Mr. Vivek V. Shankar; Engineer: Vishnu Kumar; Chartered Accountant: Gopalan Muralidharan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ISLE OF TREES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback