Home / Browse projects / Bengaluru Urban, Karnataka / HSK URBAN LIVING

Registration approved No litigation declared Residential/Group Housing project

HSK URBAN LIVING

By HSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH)

RG-KA-45934 · RERA PRM/KA/RERA/1251/310/PR/060623/005974 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2027Possession promisedmoved 12 months from the original
7 of 17Construction stages donefurthest along: Plastering inside, 80%
109 of 160Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 134 documents Report an error

HSK URBAN LIVING is a Residential/Group Housing project by HSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH) in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/060623/005974 on 6 Jun 2023. Possession is promised by 1 Mar 2027. The completion date has moved by 12 months from the original filing. 51 of the 160 units on this registration are recorded sold or booked, and 7 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHSK URBAN LIVING
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560099
  • Pincode560099
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/060623/005974
  • ReraGenie IDRG-KA-45934

Builder

  • NameHSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH)
  • Entity typeProprietorship Firm
  • GSTIN29AJAPK9040R1ZL
  • Authorized SignatoryPARVATHAMMA KRISHNAIAH

Key dates

this monthRegisteredJun 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Jun 2023
  • Promised completion1 Mar 2027
  • Revised completionRevised to 1 Mar 2027 (originally 1 Mar 2026)
  • Buildings1 building record
  • Documents filed134 files

Current status

32%51 of 160 units booked
8.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HSK URBAN LIVING---1600160

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 17 construction stages are filed complete. The stage furthest along is Plastering inside, at 80%.

Building: 69% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification45%
Dadoing, Skirting, Flooring, Tiles work (All types)45%
Railing and Grill fixing45%
Electrification, Water supply and Sanitary Finishing45%
Painting40%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)45%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings40%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes60%
Water conservation/rain water harvesting/recharge of ground waterYes45%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes20%
Electricity supply transformer and substationYes60%
Storm water drainsYes20%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes60%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes45%
LiftsYes45%
Corridor/LobbiesYes45%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes40%
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,385 sq m
Named landowners1
LandownerVillageDistrict
PARVATHAMMA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 40.78 cr
Cost incurredRs 3.25 cr
Spent of the estimate7.97%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 34.93 crRs 2.89 cr
Administrative CostRs 5.40 cr-
On-site expenditure-Consultants FeesRs 45.00 lakhRs 35.87 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANI SAMBYAL
EngineerSYED ADNAN KHADER
Chartered AccountantBASAVARAJA H M

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/260331/005974Mar 2026 → Mar 2027

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00740/2025-HSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH)14/05/2025

Documents filed134

As listed on the registration, under the names the promoter filed them with; the newest 80 of 134 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/060623/005974 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) - SEP-2026.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU)- SEP-2026.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate (QU) JUN 2026.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) - JUN-2026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU)- JUN-2026.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate March 2026.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate - MAR-2026.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate - MAR-2026.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Engineer Certificate for Pending Work Completion ScheduleFile: 1 Engineer Certificate for Pending Work Completion Schedule.pdf26 Feb 2026
Engineer Certificate for Work Completion Schedule till DateFile: 1 Engineer Certificate for Work Completion Schedule till Date.pdf26 Feb 2026
Engineer LicenseFile: 1 Engineer License.pdf26 Feb 2026
Sold and Unsold Unit DetailsFile: 3 Sold and Unsold Unit Details.pdf26 Feb 2026
Affidavit for BESCOM NOCFile: 4 Affidavit for BESCOM NOC.pdf26 Feb 2026
Affidavit for KSPCB NOCFile: 4 Affidavit for KSPCB NOC.pdf26 Feb 2026
Affidavit for Water NOCFile: 4 Affidavit for Water NOC.pdf26 Feb 2026
Query Answer DocumentFile: Query Answer Document.pdf26 Feb 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 EngineerCertificate Dec 25.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Change of Land UseFile: Change of Land Use.pdf26 May 2023
KhathaFile: 1 Khatha.pdf18 May 2023
Single Plot PlanFile: 2 Single Plot Plan.pdf18 May 2023
Single Plot OrderFile: 3 Single Plot Order.pdf18 May 2023
Proprietor Registration CertiFile: 1 Proprietor Registration Certi.pdf13 Mar 2023
Form 1 CA CertificateFile: 2 Form 1 CA Certificate.pdf13 Mar 2023
FDs Supporting Doc for Source of fundFile: 3 FDs Supporting Doc for Source of fund.pdf13 Mar 2023
KhathaFile: 4 Khatha.pdf13 Mar 2023
Single Plot PlanFile: 6 Single Plot Plan.pdf13 Mar 2023
Single Plot OrderFile: 7 Single Plot Order.pdf13 Mar 2023
Change of Land UseFile: 8 Change of Land Use.pdf13 Mar 2023
Village MapFile: 9 Village Map.pdf13 Mar 2023
Approved Building PlanFile: 10 Approved Building Plan.pdf13 Mar 2023
Agreement of SaleFile: 12 Agreement of Sale.pdf13 Mar 2023
RTC, survey 64/3A-
Mutation, survey 64/3A-
Encumbrance Certificate, survey 64/3A-
Conversion/Alienation Order, survey 64/3A-
Sale/Title/Gift Deed, survey 64/3A-
Khatha, survey 64/3A-
Registration CertificateFile: GST.pdf-
Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect Certi.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer Certi.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 CA Certificate.pdf-
Balance Sheet 2021 - 2022File: BS with Schedules 21 22.pdf-
Balance Sheet 2020 - 2021File: BS with Schedules 20 21.pdf-
Balance Sheet 2019 - 2020File: BS with Schedules 19 20.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P&L 21 22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P&L 20 21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P&L 19 20.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 22 23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 21 22.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR 20 21.pdf-
Plan Approved Letter-
Electrical Noc with fee receipt-
Water Noc with fee Declaration-
Approved Building Plan-
Section Plan and Specification-
Sectional Elevation-
Project Specifications-
STABILITY CERTIFICATE-
Legal Report-
CONVERSION-

How this compares with Bengaluru Urban

32%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep HSK URBAN LIVING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmHSK URBAN LIVINGOther 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: HSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH)

HSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH) has 1 registration on RERA Karnataka, including HSK URBAN LIVING. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if HSK URBAN LIVING is delayed beyond 1 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HSK URBAN LIVING?

The registered promoter entity is HSK DEVELOPERS (PROP PARVATHAMMA KRISHNAIAH), a proprietorship firm as per the filing. Its GSTIN 29AJAPK9040R1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HSK URBAN LIVING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HSK URBAN LIVING?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at HSK URBAN LIVING?

The professionals named in the filing: Architect: ANI SAMBYAL; Engineer: SYED ADNAN KHADER; Chartered Accountant: BASAVARAJA H M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HSK URBAN LIVING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HSK URBAN LIVING. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HSK URBAN LIVING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.