Home / Browse projects / Vadodara, Gujarat / HARMONY SHIVAAY

Valid until 29 Jun 2023 Residential/Group Housing project

HARMONY SHIVAAY

By HARMONY DEVELOPERS

RG-GJ-56934 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA06522/A2R/EX1/040722 · Last updated on GujRERA portal: 14 May 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2023Possession promisedmoved 12 months from the original
24 of 25Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 60%
26 of 50Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

HARMONY SHIVAAY is a Residential/Group Housing project by HARMONY DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA06522/A2R/EX1/040722 on 26 Dec 2019. Possession is promised by 29 Jun 2023. The completion date has moved by 12 months from the original filing. 24 of the 50 units on this registration are recorded sold or booked, and 24 of 25 construction stages are filed complete.

At a glance

Project

  • NameHARMONY SHIVAAY
  • TypeResidential/Group Housing
  • Location
    • ESI HOSPITAL ROAD
    • NEAR ESI HOSPITAL
    • B/H ISKCON TEMPLE
    • GOTRI ROAD
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA06522/A2R/EX1/040722
  • ReraGenie IDRG-GJ-56934

Builder

  • NameHARMONY DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2019First promiseJun 2022Revised toJun 2023

Key facts

Registration and timeline

  • StatusValid until 29 Jun 2023
  • Registered on26 Dec 2019
  • Promised completion29 Jun 2023
  • Revised completionRevised to 29 Jun 2023 (originally 30 Jun 2022)
  • Buildings3 building records
  • Documents filed43 files

Current status

48%24 of 50 units booked
79.1%Of the estimated cost spent so far

Figures as on 14 May 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER-A---16016
TOWER-B---18018
TOWER-C-D---16016

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 14 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 25 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 60%.

TOWER-A92%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TOWER-B100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER-C-D100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 14 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes68%
Water supplyYes45%
Sewerage (chamber, lines, septic tank, STP)Yes67%
Storm water drainsYes40%
Landscaping and tree plantingYes35%
Street lightingYes40%
Community buildingsYes20%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes35%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes40%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes20%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,415 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.86 cr
Cost incurredRs 2.26 cr
Spent of the estimate79.06%
BuildingWingEstimatedIncurred
TOWER-ANARs 95.25 lakhRs 75.30 lakh
TOWER-BNARs 95.25 lakhRs 75.30 lakh
TOWER-C-DNARs 95.25 lakhRs 75.30 lakh

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerDR. VINUBHAI R. PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA06522/A2R/EX1/040722Applied May 2022; approved Jul 2022

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA06522/A2R/EX1/040722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)14 May 2022
Site photograph, TOWER-A14 May 2022
Site photograph, TOWER-B14 May 2022
Site photograph, TOWER-C-D14 May 2022
Engineer's certificate (Form 2)7 Apr 2022
Engineer's certificate annexure7 Apr 2022
Accountant's certificate (Form 3)7 Apr 2022
RERA registration certificate26 Dec 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

48%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep HARMONY SHIVAAY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmHARMONY SHIVAAYOther 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: HARMONY DEVELOPERS

HARMONY DEVELOPERS has 3 registrations on GujRERA, including HARMONY SHIVAAY and SWASTIK HARMONY. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if HARMONY SHIVAAY is delayed beyond 29 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of HARMONY SHIVAAY?

The registered promoter entity is HARMONY DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in HARMONY SHIVAAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HARMONY SHIVAAY?

The professionals named in the filing: Engineer: DR. VINUBHAI R. PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARMONY SHIVAAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARMONY SHIVAAY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARMONY SHIVAAY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.